Glossary
Project Controls Glossary
- Activity
- A discrete unit of work in a schedule, with a duration, logic links and usually resources — the building block of a programme.
- Actual CostAC
- The cost actually incurred for work performed to date; compared with earned value to measure cost performance.
- As-Built Programme
- A schedule reconstructed from records to show how the works were actually carried out — central to retrospective delay analysis.
- Baseline
- The approved, fixed version of a programme against which actual progress, cost and delay are measured; the contractual measure of record.
- Baseline Execution IndexBEI
- A DCMA metric comparing tasks completed against those baselined to be complete — a read on whether the plan is being executed to schedule.
- Budget at CompletionBAC
- The total planned budget for the scope of work — the sum of all planned value.
- Change Control
- The disciplined process of assessing, approving and incorporating changes to scope, time or cost so their impact is understood and recorded.
- Concurrent Delay
- Where an employer-risk and a contractor-risk event each independently affect the completion date over the same period — materially affecting entitlement.
- Constraint
- A date imposed on an activity that overrides logic. Unjustified hard constraints are a common source of hidden float and misleading critical paths.
- Cost Performance IndexCPI
- Earned value divided by actual cost. Below 1.0 indicates cost overrun; above 1.0, underrun.
- Critical Path
- The sequence of activities with the least total float that controls the completion date.
- Critical Path MethodCPM
- The scheduling technique that calculates activity dates and float from durations and logic, identifying the critical path.
- Critical Path Length IndexCPLI
- A DCMA metric measuring how much the critical path must be accelerated to meet the finish date; below 1.0 signals the finish is at risk.
- DCMA 14-Point Assessment
- A widely used set of fourteen checks on schedule quality — logic, leads, lags, relationship types, constraints, float, duration, dates, resources, missed tasks, the critical-path test, CPLI and BEI.
- Delay Analysis
- The forensic assessment of how events affected the completion date, to establish entitlement to an Extension of Time.
- Disruption
- Loss of productivity — work becoming less efficient than it should have been — which may cause cost without necessarily delaying completion.
- Earned ValueEV
- The budgeted value of work actually completed to date — the anchor of earned value management.
- Earned Value ManagementEVM
- A technique integrating scope, schedule and cost to measure performance and forecast outcomes using planned value, earned value and actual cost.
- Earned Schedule
- A refinement of EVM that expresses schedule performance in time units rather than cost, giving a more reliable late-project indicator.
- Estimate at CompletionEAC
- A forecast of total cost at completion based on performance to date.
- Extension of TimeEOT
- A contractual adjustment of the completion date reflecting delay for which the contractor is entitled to more time.
- Float
- Total float is how long an activity can slip without delaying completion; free float is how long it can slip without delaying its successor.
- Forensic Schedule Analysis
- The detailed, evidence-based examination of schedules and records to establish cause, effect and entitlement in delay disputes.
- Gantt Chart
- A bar-chart view of a schedule showing activities against time — the familiar visual layer over the underlying CPM network.
- Lag / Lead
- A lag is a delay imposed on a logic link; a lead (negative lag) is an overlap. Excessive lags or leads can distort a schedule and mask real logic.
- Longest Path
- The continuous chain of driving activities to completion, traced through each activity's driving predecessor regardless of float.
- Milestone
- A zero-duration marker of a significant point or contractual date in a programme.
- Mitigation
- Reasonable steps taken to reduce the effect of a delay — distinct from acceleration, and relevant to entitlement.
- Negative Float
- A signal that, as logic and constraints stand, a required date cannot be met — work is already behind where it needs to be.
- Open End
- An activity missing a predecessor or successor, breaking the network so delay does not flow through correctly. A quality schedule has essentially none.
- Planned ValuePV
- The budgeted value of work scheduled to be complete by a given date — the baseline for earned value comparison.
- PMO
- Programme or project management office — the function that sets the operating model, standards and governance under which delivery happens.
- Primavera P6
- Oracle's enterprise planning and scheduling tool, widely used for large construction and infrastructure programmes.
- Programme
- The time model of a project — activities, logic, durations and dates. In UK and GCC usage, 'programme' is the schedule.
- Recovery Programme
- A re-planned schedule intended to bring a delayed project back toward its completion date — credible only if genuinely achievable.
- Risk Register
- The live record of identified risks with likelihood, impact, ownership and mitigation.
- Schedule Assurance
- The independent validation that a programme is technically sound and reliable before it is trusted or accepted.
- Schedule Performance IndexSPI
- Earned value divided by planned value. Below 1.0 indicates behind schedule; above 1.0, ahead.
- Stage Gate
- A defined decision point between programme phases where progress, cost, risk and readiness are reviewed before authorising the next stage.
- Work Breakdown StructureWBS
- The hierarchical decomposition of scope into manageable packages — the backbone of how a programme is structured and reported.
- Window Analysis
- A delay-analysis method that examines the schedule in time slices, assessing the impact of events within each window against the programme then current.