Baseline Review Checklist
What to verify before you accept a contractor’s baseline programme — because the baseline you accept is the one you will be measured against.
- Scope & structure — complete against contract; logical WBS and coding.
- Logic — no open ends; predominantly finish-to-start; the network responds when a key activity moves.
- Critical path — runs through genuinely constraining work; reconciled against the longest path.
- Constraints & calendars — every hard constraint justified; no unexplained negative float.
- Durations & resources — realistic, with a resourcing basis.
- Acceptance — recorded as a sound measure of record, not agreement on dates.