Methodology

Forensic Delay Analysis

Reconstructing, from the programme and the record, how specific events actually affected completion — so entitlement rests on evidence another analyst could reproduce, not on the story a claim would prefer to tell.

This sits beneath Forecast Integrity in the wider framework, and alongside the capability set out under delay analysis and Extension of Time.

Evidence of thinking
Problem

A claimed extension-of-time position that has to be tested against the record.

Method

Windowed, longest-path forensic analysis — validity, criticality and causation, event by event.

Evidence

The baseline, the contemporaneous updates, and the instruction and correspondence record.

Decision

The Employer-risk critical delay that is actually demonstrable.

Outcome

A defensible, evidence-based entitlement rather than a negotiated number.

Why it becomes difficult

The simple version collapses under its own complexity.

By the time a delay is disputed, “the job is late, so we’re owed time” has usually stopped being true in any simple sense. A credible analysis has to hold several hard things at once.

Concurrent events

Several delays running at once, each arguably driving completion over the same window.

A migrating critical path

The path that controls completion moves as the work progresses — what was critical in month four may not be in month nine.

Baseline integrity

If the accepted programme is weak, everything measured against it inherits the weakness.

Mitigation & acceleration

Recovery effort masks delay; the analysis has to see through it to what actually happened.

Contractor vs Employer risk

The same slip can be excusable, compensable, or neither — depending on whose risk it was.

Contemporaneous records

A claim is only as strong as the record made while events unfolded; reconstruction reads differently.

Causation, not correlation

Two things going wrong together is not proof that one caused the other.

Effect on the milestone

Only delay that reaches a contractual completion milestone moves entitlement.

100% 50% 0% Programme duration → Cumulative % slip Planned Actual
Planned versus actual cumulative progress. Delay shows in the data as a widening gap between the curves; the horizontal distance at completion is the slip the analysis has to explain — event by event, on the critical path.

The analytical workflow

From contract to entitlement.

Every step is measured against the contemporaneous record. Skip one and the result stops being reproducible — which is the only thing that makes a determination defensible.

01

Contract

↓

What the contract requires — notice provisions, risk allocation, the completion milestones that matter.

02

Baseline

↓

The accepted, logic-linked programme the analysis is measured against.

03

Updates

↓

Contemporaneous progress — establishing where the driving path actually ran when each event bit.

04

Delay events

↓

Each event isolated, evidenced, and tested for a valid contractual trigger.

05

Critical path

↓

Which path drove completion in each window — and how it migrated across the programme.

06

Causation

↓

Cause and effect demonstrated rather than asserted; concurrency identified honestly.

07

Time impact

↓

The days each event genuinely added to completion — net of float and mitigation.

08

Entitlement

The Employer-risk critical delay that supports an extension of time — kept separate from the money question.

Contract → Baseline → Updates → Delay events → Critical path → Causation → Time impact → Entitlement

Choosing the method

No single correct method — a correct method for the evidence.

AACE 29R-03 recognises a family of techniques — impacted as-planned, time impact analysis, as-planned versus as-built, windows, and collapsed as-built — each with a proper application and a characteristic weakness. Selection is driven by the records, the programme quality, the timing and the purpose; the real test is whether an independent analyst, given the same records, would reach a comparable result. Where the choice of method is doing the work the evidence should be doing, it is advocacy, not assessment. This is set out in full in how a delay is measured, with the honest treatment of concurrency and risk ownership alongside it.

Get in touch

Discuss forensic delay analysis, critical-path cause and effect, and Extension of Time.