Schedule Health Checklist
A DCMA-based read on whether a programme is technically sound — before its dates are trusted. Thresholds are common industry guides; adapt them to your project.
Logic & network
- Missing logic ≤ 5% (activities without a predecessor and successor)
- Leads (negative lag) = 0
- Lags ≤ 5% of relationships
- Finish-to-start relationships ≥ 90%
Constraints & float
- Hard constraints ≤ 5% and justified
- High float (> 44 days) ≤ 5%
- Negative float = 0, or explained and being recovered
Durations & dates
- High duration (> 44 days) ≤ 5%
- No invalid dates (actuals in the future / forecasts in the past)
- Resources assigned where the method requires
Progress & critical path
- Missed tasks within tolerance
- Critical-path test passes (a deliberate large delay moves the finish)
- CPLI ≈ 1.0 or better
- BEI ≈ 0.95 or better