Checklist

Schedule Health Checklist

// Tick items on screen for your own review

A DCMA-based read on whether a programme is technically sound — before its dates are trusted. Thresholds are common industry guides; adapt them to your project.

Logic & network

  • Missing logic ≤ 5% (activities without a predecessor and successor)
  • Leads (negative lag) = 0
  • Lags ≤ 5% of relationships
  • Finish-to-start relationships ≥ 90%

Constraints & float

  • Hard constraints ≤ 5% and justified
  • High float (> 44 days) ≤ 5%
  • Negative float = 0, or explained and being recovered

Durations & dates

  • High duration (> 44 days) ≤ 5%
  • No invalid dates (actuals in the future / forecasts in the past)
  • Resources assigned where the method requires

Progress & critical path

  • Missed tasks within tolerance
  • Critical-path test passes (a deliberate large delay moves the finish)
  • CPLI ≈ 1.0 or better
  • BEI ≈ 0.95 or better