Sports & Entertainment · Al Ain, UAE

Hazza Bin Zayed Stadium

Integrated planning on a fast-track stadium, with EOT and forensic claims strategy supporting arbitration.

PlanningEOTClaims
Interior of Hazza Bin Zayed Stadium showing the stands and pitch Al Ain, UAE · AED 698M

Project at a Glance

Location
Al Ain, UAE
Sector
Sports & Entertainment
Value
AED 698M
Role
Planning Engineer
Delivery
BAM International
Period
2012 — 2014

A landmark 25,000-seat football stadium in Al Ain, delivered on a demanding fast-track programme that compressed design, procurement and construction into overlapping fronts.

The controls challenge

Fast-track work multiplies interface risk and the potential for delay and change. As Planning Engineer with BAM International, I delivered integrated planning and controls, and developed the EOT and forensic claims strategy — capturing cause, effect and evidence as events unfolded.

The insight

Entitlement is built during delivery, not after it. The contemporaneous record a planner keeps under fast-track pressure is exactly the record a claim later depends on.

Project Gallery

This page describes Rishi Javeri's project-controls role within the programme and does not imply sole delivery of the asset. Figures are drawn from Rishi's own record and are subject to confirmation of disclosable scope; no confidential schedules, dashboards or commercially sensitive material are shown. Imagery to be supplied as owned or licensed only.