Out-of-Sequence Progress

When reality ignores the logic — and the forecast breaks.

What it is

Progress that happens in an order the logic did not predict — a successor started before its predecessor finished.

Why it matters

Out-of-sequence progress means the network no longer reflects reality; the forecast and critical path can be wrong until the logic is corrected.

In practice

  • P6 resolves it through the scheduling option Retained Logic or Progress Override — the choice changes the forecast.
  • Retained Logic keeps the remaining relationships; Progress Override ignores them for the progressed work.
  • Persistent out-of-sequence progress is a signal the logic is wrong, not just the sequence.
  • Re-logic the network rather than repeatedly overriding it.

Watch for

  • Leaving Progress Override on by default, quietly shortening the forecast.
  • Treating out-of-sequence as noise rather than a symptom of bad logic.
  • A critical path that only makes sense once the sequence is fixed.