Expertise

Project ControlsPlanning and Primavera P6Schedule AssuranceEOT ClaimsForensic Delay AnalysisProgramme ManagementPMO LeadershipDigital Project ControlsAll expertise

Framework

Project Controls Management System100-Point Schedule Assurance FrameworkHow I WorkOperating PrinciplesImplementation ChecklistsMaturity Model

Tools

Project Controls IntelligenceDecision Centre: start hereDirector’s 10-Minute ReviewForensic Delay LabProgramme DashboardProgramme SimulatorRisk and Early WarningExecutive Review GeneratorSchedule Assurance ChallengeProgramme Management toolsChecklists and templates

Academy

Learning pathwaysProfessional ReferencesPrimavera P6 GuidesThe SCL Protocol seriesGlossary

Insights

ArticlesCase StudiesProjectsDirector’s PlaybookRed Flags and Failure AtlasLessons from Major ProgrammesClaims and Delay articles

About

AboutExecutive ProfileDownload Executive CVLinkedIn
Search

Searches articles, case studies, guides and tools on this site. Runs in your browser — nothing is sent anywhere.

Management pathway · Contractor performance

Measuring Contractor Performance Fairly

Contractor performance measurement only works if contractors accept it as fair. That means the same measures for everyone, agreed in advance and backed by evidence.

By Rishi Javeri · 01-Nov-26 · 7 min read

Most programmes have several contractors working to different contracts. Without a common way of measuring them, performance discussions turn into opinion, and the strongest personality wins. A fair, consistent measurement framework changes that conversation.

Principles

  • One standard for everyone. The same measures, definitions and frequency for every contractor, published before work starts.
  • Measure what the contractor controls. Separate the contractor’s performance from the effects of employer delay, late information or access.
  • Evidence, not impression. Every score traceable to a record: a submission date, a review finding, a measured quantity.
  • Few measures, well chosen. Six to ten measures that drive behaviour beat thirty that nobody reads.
  • Feedback before escalation. Findings are shared and discussed before they go up the line.

What to measure

AreaExample measureEvidence
TimeMilestones achieved against the accepted programme; SPI(t)Programme updates, milestone certificates
Controls qualityProgramme updates accepted first time; assurance score trendReview records, assurance results
Progress reliabilityGap between reported and verified progressProgress verification samples
ResourcesMobilised labour and plant against the programmeDaily reports, site counts
Change and noticesNotices and change submissions on time and completeCorrespondence register
InterfacesInterface dates metInterface register

An example scorecard

A fictional month for two packages, each measure scored 1 (poor) to 5 (strong) against written criteria:

MeasurePackage APackage B
Milestones met42
Updates accepted first time52
Reported vs verified progress43
Resources against plan32
Notices complete and on time44
Interfaces met33
Average3.82.7

The value is not the average. It is the pattern: Package B’s controls quality and milestone performance are low together, which points to a planning problem worth a focused meeting, not a general warning letter.

Pitfalls

  • Changing the measures mid-contract.
  • Scoring on the PMC’s opinion rather than records.
  • Using the scorecard as a claims weapon, which ends cooperation.
  • Never telling the contractor how to improve the score.

Check your understanding

Three questions. Choose an answer in your head, then open it to compare.

1Which measure says most about a contractor's controls discipline?

  1. Number of pages in the monthly report
  2. Share of programme updates accepted first time against the agreed standard
  3. Size of the site team
  4. Number of meetings attended
Show the answer

B. Share of programme updates accepted first time against the agreed standard First-time acceptance against a published standard is objective, comparable between contractors and directly linked to the quality of their controls.

2Why separate contractor-caused from employer-caused delay in a scorecard?

  1. It is not necessary
  2. So the contractor is measured on what it controls; mixing them makes the scorecard unfair and easy to dispute
  3. To support a claim
  4. Because the contract requires it
Show the answer

B. So the contractor is measured on what it controls; mixing them makes the scorecard unfair and easy to dispute A scorecard that blames the contractor for employer delay loses credibility immediately. Measure what the contractor controls, and record the rest separately.

3What should happen before a poor score is escalated?

  1. Nothing; escalate straight away
  2. The finding and its evidence are shared with the contractor, who has the chance to respond
  3. The score is averaged with last month's
  4. The PMC changes the measure
Show the answer

B. The finding and its evidence are shared with the contractor, who has the chance to respond Sharing evidence first keeps the process fair and usually fixes the problem faster than escalation.

Self-paced reading for practitioners. Not a course, certificate or accredited qualification. Worked examples use fictional figures.