PCMS methodology
Employer-Side Controls Implementation Checklists How to establish or improve an integrated controls function on a multi-package, multi-contractor programme: eight checklists in the order they are usually needed, each linked to the PCMS volume that carries it.
Original and generic: these are not any employer’s controlled templates or requirements. Tick items as you go; ticks stay in this browser tab only. Print or save as PDF to keep a copy.
01 Mobilisation 02 Governance structure 03 Baseline acceptance 04 Progress, cost and forecast integration 05 Reporting 06 Contractor controls 07 Assurance and audit 08 Continuous improvement and close-out 01 Mobilisation PCMS V1, V6 · When: Before the first contractor baseline is due · Deliverables: Controls plan, team structure, reporting calendar
02 Governance structure PCMS V1 · When: At mobilisation, reviewed at each gate · Deliverables: Delegations matrix, terms of reference, decision log
03 Baseline acceptance PCMS V2, V7 · When: Each baseline submission and any re-baseline · Deliverables: Acceptance record with closeable comments
04 Progress, cost and forecast integration PCMS V2, V3 · When: Every reporting period · Deliverables: Verified progress, reconciled forecast
05 Reporting PCMS V3 · When: Every reporting period · Deliverables: Board report and contractor compliance record
06 Contractor controls PCMS V6 · When: Monthly, and at contract milestones · Deliverables: Contractor scorecard and surveillance log
07 Assurance and audit PCMS V7 · When: Quarterly, and when indicators turn red · Deliverables: Assurance report and corrective actions
08 Continuous improvement and close-out PCMS V7, V1 · When: At each gate and at closure · Deliverables: Lessons log and close-out record