Expertise

Project ControlsPlanning and Primavera P6Schedule AssuranceEOT ClaimsForensic Delay AnalysisProgramme ManagementPMO LeadershipDigital Project ControlsAll expertise

Framework

Project Controls Management System100-Point Schedule Assurance FrameworkHow I WorkOperating PrinciplesImplementation ChecklistsMaturity Model

Tools

Project Controls IntelligenceDecision Centre: start hereDirector’s 10-Minute ReviewForensic Delay LabProgramme DashboardProgramme SimulatorRisk and Early WarningExecutive Review GeneratorSchedule Assurance ChallengeProgramme Management toolsChecklists and templates

Academy

Learning pathwaysProfessional ReferencesPrimavera P6 GuidesThe SCL Protocol seriesGlossary

Insights

ArticlesCase StudiesProjectsDirector’s PlaybookRed Flags and Failure AtlasLessons from Major ProgrammesClaims and Delay articles

About

AboutExecutive ProfileDownload Executive CVLinkedIn
Search

Searches articles, case studies, guides and tools on this site. Runs in your browser — nothing is sent anywhere.

Home / Insights / SCL Protocol series

Series guide

The SCL Protocol, in Practice

Delay, disruption and extension of time — one practical concept at a time. A plain-English guide to the Society of Construction Law Delay and Disruption Protocol, written to be used on a live project, not filed on a shelf.

Each part uses a real site scenario, shows what the planner, the claims team and the project manager each need from it, and ends with the one line worth remembering. One principle runs through all of it: the Protocol is guidance, not law. The contract, the governing law, the facts and the evidence decide entitlement.

Learning path UnderstandAnalyseEvidenceExplainDefend

10 of 24 published · a new part each week

Fundamentals

What the Protocol is, and the ideas everything else rests on.

Records & Assessment

Why the record and the timing of assessment decide most outcomes.

Delay Analysis

The two lenses, the six methods, and how to choose between them.

Part 9

Prospective vs Retrospective: Two Different Jobs

Analysing delay before it happens and after it happened are two different jobs.

6 min read
Part 10

The Six Methods at a Glance

The Protocol lists six methods and names no favourite. That's deliberate.

5 min read
Part 11 · publishes 27-Nov-26

Impacted As-Planned: The Theoretical One

A useful "what if" on a perfect plan — as long as you remember it's hypothetical.

Part 12 · publishes 04-Dec-26

Time Impact Analysis: The Contemporaneous Workhorse

A P6 file is not a time machine.

Part 13 · publishes 11-Dec-26

Time Slice Windows: Following the Critical Path as It Moves

The critical path isn't fixed — good analysis follows it as it moves.

Part 14 · publishes 18-Dec-26

As-Planned vs As-Built Windows: The Forensic Favourite

What you planned, what happened, and where they diverged — that gap is your analysis.

Part 15 · publishes 25-Dec-26

Retrospective Longest Path & Collapsed As-Built

"But for this event, when would we have finished?" — powerful, and easy to abuse.

Part 16 · publishes 01-Jan-27

Choosing the Right Method: Records Decide, Not Preference

You pick the method your records can actually stand behind.

Concurrency

The narrow test for true concurrency, and what it does to time and money.

Part 17 · publishes 08-Jan-27

Concurrent Delay: The Topic Everyone Argues About

Two delays at once is NOT automatically concurrent delay.

Part 18 · publishes 15-Jan-27

True vs Apparent Concurrency

If only one delay was driving the finish, you have a queue, not concurrency.

Part 19 · publishes 22-Jan-27

Concurrency: Time Yes, Money Maybe

Concurrency can hand you the time and still deny the money.

Programme & EOT

Float, the link between time and money, mitigation and acceleration.

Part 20 · publishes 29-Jan-27

Float: Who Owns It and Why the Fight Matters

Float has no owner until the contract gives it one.

Part 21 · publishes 05-Feb-27

EOT ≠ Money: The Link Everyone Assumes

An extension of time doesn't automatically get you paid.

Part 22 · publishes 12-Feb-27

Mitigation vs Acceleration: Know Which One You're Doing

"Mitigate the delay" does not mean "throw money and men at it."

Advanced

Recovery programmes and global claims.

Part 23 · publishes 19-Feb-27

Recovery & Revised Programmes: Evidence or Fiction?

A revised programme is either a tool or a work of fiction.

Part 24 · publishes 26-Feb-27

Global Claims: Why "Everything Caused Everything" Is Hard

"It was all so chaotic we can't separate the causes" is usually a last resort.

Try it: the Forensic Delay Lab Run a Time Impact Analysis step by step on a fictional programme: fragnets, critical path migration and concurrency. SCL Protocol 2017 — Project Controls Quick Reference Key concepts, the six methods, concurrency, EOT and an evidence checklist — on one page you can print.

Primary reference: Society of Construction Law, Delay and Disruption Protocol, 2nd Edition, February 2017. Educational commentary, not legal advice; outcomes depend on the contract, the governing law, the facts and the evidence.