Expertise

Project ControlsPlanning and Primavera P6Schedule AssuranceEOT ClaimsForensic Delay AnalysisProgramme ManagementPMO LeadershipDigital Project ControlsAll expertise

Framework

Project Controls Management System100-Point Schedule Assurance FrameworkHow I WorkOperating PrinciplesImplementation ChecklistsMaturity Model

Tools

Project Controls IntelligenceDecision Centre: start hereDirector’s 10-Minute ReviewForensic Delay LabProgramme DashboardProgramme SimulatorRisk and Early WarningExecutive Review GeneratorSchedule Assurance ChallengeProgramme Management toolsChecklists and templates

Academy

Learning pathwaysProfessional ReferencesPrimavera P6 GuidesThe SCL Protocol seriesGlossary

Insights

ArticlesCase StudiesProjectsDirector’s PlaybookRed Flags and Failure AtlasLessons from Major ProgrammesClaims and Delay articles

About

AboutExecutive ProfileDownload Executive CVLinkedIn
Search

Searches articles, case studies, guides and tools on this site. Runs in your browser — nothing is sent anywhere.

Decision support

Have a project-controls problem? Start here.

Identify the situation, understand what to examine first, and move directly to the relevant tool, framework, case study or Director’s perspective. Not a chatbot — a structured decision-support library built around one practitioner’s methodology.

Also here: Project Controls Toolkit · Director’s Playbook · Schedule Health Check

Guided pathway

The contractor’s recovery programme looks unrealistic.

Eight short questions about what you have and what you know, then any warning signs you have seen. The result organises your answers into what to verify, what evidence to ask for and what to review first. It runs in your browser; nothing is sent or stored. For a two-minute score instead, use the Recovery Programme Check.

Step A · What you have and what you know

Do you have the accepted baseline and the latest programme update?Native programme files, not PDFs.
Is the actual progress in the current update supported by evidence?Site diaries, inspection records, measured quantities.
Do you understand the current critical path and how the forecast completion is derived?
Have logic changes, new constraints and shortened remaining durations been compared with the previous update?
Are the recovery assumptions quantified — which activities, how much time, through which measures?
Do the resources, productivity rates and working arrangements support the proposed recovery?Labour and plant, achieved output rates, shifts, hours, access.
Are key milestones and interfaces achievable on the recovery dates?Approvals, authority inspections, third-party works, access dates.
Has the contractor said whether the measures are mitigation or acceleration?Mitigation is usually at the contractor’s cost; acceleration may need an instruction and payment.

Step B · Have you seen any of these? (optional)

Sample management conclusion · fictional example

“Package C has submitted a recovery programme that restores contractual completion from a forecast nine weeks late. We have not accepted it. The recovery depends on finishing-trade productivity well above anything achieved to date, with no additional labour mobilised, and the critical path has moved from MEP to façade without explanation. Progress on two of five floors has not yet been verified. We have asked for resourced recovery logic, evidence of achieved productivity, and the contractor’s position on mitigation versus acceleration. Until we report a reviewed position at the next monthly meeting, management should continue to plan on the nine-week forecast.”

Illustrative only: how a senior project-controls reviewer might summarise such a review for management. It is not a real project outcome and not a contractual or legal determination.

Pathway How this tool works: inputs, method and limitations
Purpose
Structure the review of a recovery programme that looks unrealistic, and produce a short management summary.
Intended user
Programme managers, PMC and employer representatives.
Output
A readiness reading, prioritised areas to verify, an evidence list, red flags and a copyable summary.
How the result is produced
Guided review, rule-based.
PCMS discipline
Productivity and performance measurement · Volume 2: Planning, Scheduling and Progress Management
Learn the method
What I check before I trust a recovery programme (Management pathway)
Inputs
  • Eight yes / partly / no / not known answers
  • Any red flags observed
Method
  • Answers other than “yes” map to areas to verify, evidence to request and the decision each affects.
  • Priorities follow Signal → Interpretation → Evidence → Decision → Action.
Limitations
  • Organises your knowledge; it does not analyse the programme file.
Suggested actions
  • Send the evidence list as a single information request.
  • Report a reviewed position, not the contractor’s, at the next management meeting.
How to read the result
The result is indicative: a structured prompt for professional judgement, not a determination. Use it to decide what to check next, then confirm against the programme, the records and the contract.
Related
Expertise: Project Controls · Reference: Earned value standards · Case study: Hudayriyat West programme · 100-Point Framework · Not sure where to start? Decision Centre

Runs in your browser; nothing is sent to a server. A practitioner’s aid, not a certification or a contractual determination. See how the measures combine in the Programme Intelligence Dashboard. All tools →

Reporting is not interpretation

Signal → Interpretation → Decision

Signal

SPI reads 0.94. The programme is reported as “slightly behind.”

Interpretation

Production is below plan — but SPI alone does not prove contractual completion is delayed. It says nothing about the critical path.

Decision

Examine the controlling path, remaining float and the activities driving completion — then decide whether the end date is actually at risk.