Decision support

Have a project-controls problem? Start here.

Identify the situation, understand what to examine first, and move directly to the relevant tool, framework, case study or Director’s perspective. Not a chatbot — a structured decision-support library built around one practitioner’s methodology.

Reporting is not interpretation

Signal → Interpretation → Decision

Signal

SPI reads 0.94. The programme is reported as “slightly behind.”

Interpretation

Production is below plan — but SPI alone does not prove contractual completion is delayed. It says nothing about the critical path.

Decision

Examine the controlling path, remaining float and the activities driving completion — then decide whether the end date is actually at risk.