Expertise

Project ControlsPlanning and Primavera P6Schedule AssuranceEOT ClaimsForensic Delay AnalysisProgramme ManagementPMO LeadershipDigital Project ControlsAll expertise

Framework

Project Controls Management System100-Point Schedule Assurance FrameworkHow I WorkOperating PrinciplesImplementation ChecklistsMaturity Model

Tools

Project Controls IntelligenceDecision Centre: start hereDirector’s 10-Minute ReviewForensic Delay LabProgramme DashboardProgramme SimulatorRisk and Early WarningExecutive Review GeneratorSchedule Assurance ChallengeProgramme Management toolsChecklists and templates

Academy

Learning pathwaysProfessional ReferencesPrimavera P6 GuidesThe SCL Protocol seriesGlossary

Insights

ArticlesCase StudiesProjectsDirector’s PlaybookRed Flags and Failure AtlasLessons from Major ProgrammesClaims and Delay articles

About

AboutExecutive ProfileDownload Executive CVLinkedIn
Search

Searches articles, case studies, guides and tools on this site. Runs in your browser — nothing is sent anywhere.

Forensic Delay Analysis

426 Days Reduced to 91

426 → 91 days · claimed to approved

Forensic review of a 426-day EOT position — programme analysis, critical-path cause and effect, and the evidence behind the 91 days approved.

At a glance

Project context
Hudayriyat West Island Development, Abu Dhabi (velodrome package), AED 28.1B programme.
Challenge
A contractor extension of time position of 426 days to final completion, built from 16 delay events.
Initial condition
Taken at face value, it would have moved completion by more than a year and reset the delay-damages position.
Intervention
Every event screened for validity before any day was quantified, then tested for causation and criticality.
Methodology
Windowed longest-path analysis across nine windows, each between an approved baseline or update and the next data date.
Results
The employer-side assessment supported 91 days on the evidence, and 91 days were approved. Each of the 335 days not accepted was tied to a recorded reason: contractor risk, off the driving path, or invalid under the contract. A later revised claim of 711 days was approved at 97 days.
Professional contribution
The windowed analysis and the assessment, carried out within the EllisDon PMC.
Lessons learned
Sequence collapses a headline: validity, then causation, then criticality, and no payment for delay off the driving path.
Tools and methods
Forensic Delay Lab: windows analysis · AACE forensic schedule analysis

01 — The Position

A contractor extension-of-time position of 426 days to final completion, built from 16 delay events spanning design, procurement and construction. Taken at face value it would have moved the completion milestone by well over a year and reset the delay-damages position along with it. The task was not to negotiate that number downward but to test it — event by event, against the contract and against the programme actually driving completion — as the Engineer’s assessment of the claim on the Employer’s behalf.

02 — The Evidence

The approved baseline, every contemporaneous programme update at its data date, the instruction and variation record, and the correspondence fixing when each event was notified and when it was resolved. Entitlement was tested against that contemporaneous record — what the programme actually showed at the time, update by update — not against a single as-planned-impacted model built after the event. Confidential project records limit the level of detail that can be published; what follows is the method, not the parties or the figures behind it.

03 — The Programme Analysis

A windowed, longest-path analysis. The programme was sliced into nine windows, each opening at an approved baseline or a contemporaneous update and closing at the next data date, so the path driving completion could be identified as it stood in that window rather than assumed constant across the job. Slippage and recovery were measured window by window, and the driving path was tracked as it migrated between design, procurement and construction.

04 — Event Mapping

Every event was first screened for contractual validity, then located in the window in which it arose and decomposed along the chain that actually delivered each work package — request for proposal, recommendation, instruction, award, detailed design, fabrication, delivery, construction. Breaking each event into that chain made it possible to see which link had actually slipped, and whose risk that link was, before a single day was attributed to completion.

426
days · 16 events
→
Validity screen
contract test
→
9-window longest path
critical path
→
91
days assessed
From a 426-day claim to a 91-day assessment — screened for validity, then tested window by window against the path actually driving completion.

05 — Cause & Effect

Several events failed the validity screen outright — including one where the contractor claimed time to correct logic it had itself omitted from the approved baseline; sub-events where the governing instruction expressly directed the contractor to hold to baseline durations, so the claimed “additional” time had no contractual footing; and events where no proper notice had been given under the conditions of contract. The events that survived were then apportioned link by link along the delivery chain: slippage in the contractor’s own procurement steps stayed with the contractor, and the time it later recovered was credited back, while genuine Employer-risk delay in instructions and design approvals was isolated on its own. Only after that apportionment was any event tested for a demonstrable effect on completion.

06 — Critical Path

In several windows the longest path ran through the contractor’s own procurement and construction sequence, not through any Employer act. Employer-risk delay that was real but sat off the driving path in its window earned nothing — non-critical delay does not move completion, however large it looks on paper. The critical path was followed as it migrated window to window, and only delay that sat on it, in the window where it actually bit, was carried forward.

07 — Entitlement / Assessment

Three filters had now been applied in sequence — contractual validity, then causation and apportionment, then criticality. What survived all three was a small number of Employer-risk instruction and design events that were valid under the contract, Employer-caused in fact, and sitting on the path driving completion in the window where they arose — not the sixteen the headline claim rested on. Their net critical effect on the completion milestone was what could properly be assessed as entitlement.

08 — The Decision

91 days. The Employer-risk delay that was valid under the contract, Employer-caused in fact, and critical to completion — assessed on the longest path, window by window. The 335 days between the claim and the assessment were not argued away; they were accounted for, event by event, as contractor-risk, off the driving path, or contractually invalid.

09 — The Outcome

Delay periods at a glance
StageDaysBy whom
Claimed426Contractor, to final completion
Assessed91Engineer’s assessment on the Employer’s behalf (this analysis)
Approved91The figure approved
Revised claim (later)711Contractor’s subsequent revised claim
Approved on the revised claim97The figure approved

The assessment came to 91 days on the evidence, and 91 days were approved. Because every rejected day was tied to a specific, contemporaneously-recorded reason — the contractor’s own risk, off the driving path, or invalid under the contract — the assessment stood up line by line rather than as a single negotiated figure. A claim reduced this way holds because it can be walked back through the same record that built it.

10 — Director’s Lesson

The discipline that collapses a headline is sequence: screen every event for contractual validity before a single day is quantified, then test causation, then test criticality — and refuse to pay for delay that is genuine but sits off the path driving completion. A 426-day headline is a claim. Ninety-one days is what the contract, the causation and the contemporaneous programme could each independently support.

Apply this to your programme

Facing a large, multi-event EOT position? Start by checking:

  • Does each event pass a contractual validity screen before anything else?
  • In which window does it arise — and is it on the longest path there?
  • Is claimed Employer delay actually driving completion, or sitting on float?
  • Has the contractor’s own delay been apportioned out?

Then put it to work: Forensic Delay Analysis · EOT Review Checklist · Critical Path Stability · Playbook — Claims & EOT.

Follow the thread

Case study → method → evidence → decision: Forensic Delay Analysis · Critical Path Stability · Field note: what negative float tells me · Director’s Playbook. See the decision framework behind it in How I Work.

Author
Rishi Javeri · Project Controls & Programme Governance · FCIArb | FIE | PMP | PSP | MCIOB | MAPM

This case study describes Rishi Javeri's professional project-controls role and methodology; it does not disclose confidential parties, contracts, schedules or commercially sensitive material, and does not imply sole delivery of the programme. It describes professional practice, not legal advice.

Next step

This case applies forensic delay analysis, window by window.

A related question? Discuss a professional enquiry, after reading How I Work.