AACE International
AACE forensic schedule analysis (RP 29R-03)
01What it covers
A shared vocabulary and technical protocols for analysing delay with critical path schedules after the event. 29R-03 classifies methods by whether they observe the schedules as they were or model events into them, whether they are static or dynamic, additive or subtractive, and whether they use one baseline or many. It then sets out nine method implementation protocols (MIP 3.1 to 3.9).
02Why it matters
Delay experts on opposing sides frequently use different methods and get different answers. A common taxonomy lets each side, and the tribunal, see exactly which method was used and test whether it was applied properly.
03Key principles
- Say which method is used, and why it suits the contract, the records and the question being asked.
- Observational methods look at contemporaneous or reconstructed schedules; modelled methods insert or remove delays and recalculate.
- Validate the baseline and updates before relying on them, and document every change made to them.
- The practice is a reference, not a rigid standard: a reasoned departure from it is not automatically an error.
04Practical application
- State the method by its 29R-03 classification in any delay report, alongside the SCL name where one is used.
- Keep the schedule updates and their native files as the project goes, so observational methods remain possible later.
- Use a prospective time impact analysis (52R-06) for live events, and keep retrospective methods for disputes.
05Common mistakes
- Naming a method loosely (“windows analysis”) without saying how it was implemented.
- Changing the logic of contemporaneous updates without disclosing and justifying each change.
- Presenting a technical delay result as if it decided entitlement or liability.
06PCMS discipline
07Related tools
08Further reading
- AACE 29R-03 explained
- What is delay analysis?
- Recommended Practice 29R-03: Forensic Schedule Analysis (publisher)
- Recommended Practice 52R-06: Time Impact Analysis, as applied in construction (publisher)
Written in my own words to explain principles; it does not reproduce the publication and implies no endorsement by AACE International. Not legal advice.
Other references
- SCL Delay and Disruption Protocol (2nd Ed.): Reference Guide
- Schedule assessment frameworks: DCMA, GAO, PMI and the 100-point framework
- The GAO schedule and cost guides
- AACE planning and scheduling practices
- Earned value management: EIA-748-E and ISO 21508
- Risk and change: ISO 31000 and AACE practices
- Programme governance: PMI, ISO 21503 and MSP