Expertise

Project ControlsPlanning and Primavera P6Schedule AssuranceEOT ClaimsForensic Delay AnalysisProgramme ManagementPMO LeadershipDigital Project ControlsAll expertise

Framework

Project Controls Management System100-Point Schedule Assurance FrameworkHow I WorkOperating PrinciplesImplementation ChecklistsMaturity Model

Tools

Project Controls IntelligenceDecision Centre: start hereDirector’s 10-Minute ReviewForensic Delay LabProgramme DashboardProgramme SimulatorRisk and Early WarningExecutive Review GeneratorSchedule Assurance ChallengeProgramme Management toolsChecklists and templates

Academy

Learning pathwaysProfessional ReferencesPrimavera P6 GuidesThe SCL Protocol seriesGlossary

Insights

ArticlesCase StudiesProjectsDirector’s PlaybookRed Flags and Failure AtlasLessons from Major ProgrammesClaims and Delay articles

About

AboutExecutive ProfileDownload Executive CVLinkedIn
Search

Searches articles, case studies, guides and tools on this site. Runs in your browser — nothing is sent anywhere.

AACE International

AACE forensic schedule analysis (RP 29R-03)

Recommended Practice 29R-03: Forensic Schedule AnalysisRevision of 25-Apr-11 · Recommended practice · Free to AACE members; purchase for othersOfficial source →
Recommended Practice 52R-06: Time Impact Analysis, as applied in construction2006 · Recommended practice · Free to AACE members; purchase for othersOfficial source →
Edition checked 02-Nov-26.

01What it covers

A shared vocabulary and technical protocols for analysing delay with critical path schedules after the event. 29R-03 classifies methods by whether they observe the schedules as they were or model events into them, whether they are static or dynamic, additive or subtractive, and whether they use one baseline or many. It then sets out nine method implementation protocols (MIP 3.1 to 3.9).

02Why it matters

Delay experts on opposing sides frequently use different methods and get different answers. A common taxonomy lets each side, and the tribunal, see exactly which method was used and test whether it was applied properly.

03Key principles

  • Say which method is used, and why it suits the contract, the records and the question being asked.
  • Observational methods look at contemporaneous or reconstructed schedules; modelled methods insert or remove delays and recalculate.
  • Validate the baseline and updates before relying on them, and document every change made to them.
  • The practice is a reference, not a rigid standard: a reasoned departure from it is not automatically an error.

04Practical application

  • State the method by its 29R-03 classification in any delay report, alongside the SCL name where one is used.
  • Keep the schedule updates and their native files as the project goes, so observational methods remain possible later.
  • Use a prospective time impact analysis (52R-06) for live events, and keep retrospective methods for disputes.

05Common mistakes

  • Naming a method loosely (“windows analysis”) without saying how it was implemented.
  • Changing the logic of contemporaneous updates without disclosing and justifying each change.
  • Presenting a technical delay result as if it decided entitlement or liability.
Guidance, contract and law. 29R-03 is a technical recommended practice. It deliberately leaves causation, risk allocation and entitlement to the contract and the law. SCL method names and 29R-03 protocols correspond only approximately.