Expertise

Project ControlsPlanning and Primavera P6Schedule AssuranceEOT ClaimsForensic Delay AnalysisProgramme ManagementPMO LeadershipDigital Project ControlsAll expertise

Framework

Project Controls Management System100-Point Schedule Assurance FrameworkHow I WorkOperating PrinciplesImplementation ChecklistsMaturity Model

Tools

Project Controls IntelligenceDecision Centre: start hereDirector’s 10-Minute ReviewForensic Delay LabProgramme DashboardProgramme SimulatorRisk and Early WarningExecutive Review GeneratorSchedule Assurance ChallengeProgramme Management toolsChecklists and templates

Academy

Learning pathwaysProfessional ReferencesPrimavera P6 GuidesThe SCL Protocol seriesGlossary

Insights

ArticlesCase StudiesProjectsDirector’s PlaybookRed Flags and Failure AtlasLessons from Major ProgrammesClaims and Delay articles

About

AboutExecutive ProfileDownload Executive CVLinkedIn
Search

Searches articles, case studies, guides and tools on this site. Runs in your browser — nothing is sent anywhere.

Programme intelligence

Illustrative · fictional programme and data

Programme Intelligence Dashboard

Programme Meridian (Mixed-use development: two towers, podium, public realm), month 12 of 24, data date 31-Oct-26. Every figure below is calculated by the same functions as the public tools, from one fictional data set, to show how controls data should flow into an executive view.

Not connected to Primavera P6, a cost system, Aconex, Power BI or any live data. Money in AED million. RAG ratings follow the platform definitions.

Overall programme healthRed

2 areas red and 4 amber of 6 rated. Schedule is red: the façade package now drives completion and forecast completion has moved later for three updates running. Three decisions are needed before the Board report.

Cost and forecast

Amber
EAC 4,997

+4.1% on budget of 4,800

▼ worsening since last month

  • CPI 0.94; TCPI to budget 1.05
  • Formula range 4,935 to 5,495
  • Reported EAC sits within the range

KPI scorecard

MeasureValueRAGTrendThresholds (green · amber · red)Source
Forecast completion against contract+7 weeksRed▼ worseningon or before the contract date · up to 4 weeks late · more than 4 weeks lateProgramme update
SPI(t)0.92Amber▼ worseningat or above 0.95 · 0.90 to below 0.95 · below 0.90Earned Value Calculator
CPI0.94Amber▼ worseningat or above 0.95 · 0.90 to below 0.95 · below 0.90Earned Value Calculator
EAC against budget+4.1%Amber▼ worseningat or below budget · up to 5% over · more than 5% overCost Forecast Calculator
Milestones met when due7 of 10Amber▲ improving90% or more · 70% to below 90% · below 70%Milestone register
Pending change older than 60 days11Red▼ worseningfewer than 3 items · 3 to 9 items · 10 or more itemsChange register
Risks above escalation threshold1Amber■ unchangednone · 1 or 2 · 3 or moreRisk and Early Warning
Schedule quality score73%Amber▲ improving80% or more · 60% to below 80% · below 60%Schedule Health Check

Schedule and progress

Key milestone outlook

MilestoneBaselineForecast / actualFloat (d)Status
Basement complete15-Aug-2602-Sep-26—Achieved late
Tower 1 frame topped out15-Oct-2620-Oct-26—Achieved late
Building watertight, tower 130-Nov-2625-Jan-27-38Forecast late
Energisation31-Mar-2705-May-27-35Forecast late
Façade complete30-Apr-2718-Jun-27-49Forecast late
MEP first fix complete31-May-2714-Jun-276Near-critical
Handover zone A30-Jun-2815-Aug-28-46Forecast late
Practical completion30-Sep-2818-Nov-28-49Forecast late

Critical path: 2 migrations in four updates; core critical activities F900, S100, S200. 5 milestones in negative float, 1 near-critical. Stability monitor →

Planned against earned and actual cost

01,2002,4003,6004,800 M0M6M12M18M24

■ Planned value · ■ Earned value · ■ Actual cost · ┆ data date

Chart data
MonthPVEVACSPI(t)CPI
79879379660.970.97
81,2441,1621,2100.960.96
91,5191,3951,4530.950.96
101,8061,6341,7200.940.95
112,1011,8741,9730.930.95
122,4002,1132,2480.920.94

By package

PackageSPICPIForecast delayReportedVerifiedScheduleCost
A · Structure0.980.97+1 wks62%61%AmberGreen
B · Façade0.810.90+7 wks49%44%RedAmber
C · MEP0.930.95+3 wks47%39%AmberAmber
D · Fit-out and public realm0.540.85+5 wks18%17%RedRed

The programme average hides package B: it drives completion while A and C run close to plan. Package D’s low SPI reflects a late start that is not yet on the critical path.

Cost and forecast

Budget4,800
Commitments3,950
Actual cost2,248
Reported EAC4,997
BasisEACVariance at completionTCPI
Past variance will not recur4,935-1351.00
Cost performance continues5,107-3070.94
Cost and schedule pressure both continue5,495-6950.83
Bottom-up estimate4,938-1381.00
Reported forecast (forecast)4,997-197—

The reported EAC is within the formula range but below the cost-performance-continues estimate. It excludes pending change of about 215 (assumption). To finish within budget, remaining work needs a CPI of 1.05 against 0.94 achieved. Test it →

Risk and change

Inherent exposure321
Residual exposure130
Opportunities35
Early warningAct now
Risk or opportunityOwnerResidual scoreResidual exposureTrend
R06 Utility connection dateInterface manager16 ▲21Stable
R03 Summer labour shortage, MEPContractor C1235New
R02 Fire strategy approval lateDesign manager920Stable
O01 Prefabricated bathroom pods (opportunity)Design manager935New
R01 Façade supplier capacityPackage manager B836Up
R04 End-user design changes, fit-outNo owner618Up

Risk-adjusted forecast 5,092 (forecast, expected-value method, no confidence level). Change: 38 items pending, about 215, 11 older than 60 days (was 8). Risk and Early Warning →

Assurance, contractors and interfaces

PackageSchedule qualityReport compliancePerformance rating*Weakest measure*
A · Structure86%98%3.95 / 5Resources against plan, Interfaces met
B · Façade58%62% · 4 d late2.50 / 5Milestones met, Updates accepted first time, Resources against plan
C · MEP71%86% · 1 d late2.78 / 5Reported vs verified progress
D · Fit-out and public realm69%96%3.30 / 5Interfaces met

*Judgement-based ratings against written criteria, not measured performance. Schedule quality and report compliance are checked against defined criteria.

Interfaces and constraints

InterfaceFrom → toNeedForecastStatus
IF-01 Fire authority inspection before zone A access · criticalAuthority (via employer) → D Fit-out2026-10-152026-11-20Overdue
IF-02 Permanent power for energisation · criticalUtility (via employer) → C MEP2026-11-302027-01-10At risk
IF-04 MEP riser access levels 1–5A Structure → C MEP2026-11-102026-11-10Due in 30 days
IF-03 Façade bays 1–3 handed to fit-outB Façade → D Fit-out2026-12-152026-12-15On track

Control tower

Early warnings, critical path movement and the change pipeline.

Early warnings · Act now

Score 77 of 100 on twelve indicators; 10 triggered, 1 not known.

  • Yes The critical path has changed without an explanation.
  • Yes Forecast completion has moved later in two or more consecutive updates.
  • Yes Interface dates between packages are being missed.
  • Yes Pending change older than 60 days is growing.
  • Yes The forecast assumes productivity above rates achieved so far.
All indicators →

Critical path movement

UpdateOverlapJoinedLeftFinish
Month 9 → Month 10100%——-7 d
Month 10 → Month 1143%B300, B310S110, S120-14 d
Month 11 → Month 1243%B320, K400S100, S200-14 d
Critical Path Stability Monitor →

Change pipeline

Pending items38
Pending value215
Older than 60 days11
Last month8

Aged change is rising (8 → 11). Pending change is not yet in the budget or the baseline, so the EAC and the forecast completion both understate the exposure until it is decided.

Change Impact Assessment →

Decisions and actions

Decisions required this month

  1. Accept the façade recovery programme, or require resourced logic first?Recovery relies on output 30% above the best month achieved on package B. Recommendation (judgement): Note it, request resourced logic, keep the 7-week forecast until evidenced. Test it →
  2. Release contingency for the five largest aged change items?11 items older than 60 days sit outside the forecast. Recommendation (judgement): Decide the five largest before the Board report; show the rest as exposure. Test it →
  3. Escalate the fire authority inspection to programme director level?Critical interface IF-01 is overdue and holds zone A access. Recommendation (judgement): Escalate this week. Test it →

Management actions, ranked

#ActionOwnerPriorityCategoryOverdue
1Decide on façade recovery programmeProgramme director25Act now—
2Confirm fire authority inspection dateNo owner18Act now16 d
3Close out 11 aged change requestsCommercial lead15Plan21 d
4Verify MEP progress on levels 1–5Controls lead12Quick win—
5Assign owner to end-user change risk R04Risk manager10Quick win7 d
6Issue revised reporting template to contractorsControls lead6Quick win—

Generate the monthly review from these figures →

How the figures flow

Each panel is computed at build time from the demonstration data by the same functions the public tools run in your browser. In a real programme the inputs would come from the source systems named on the Controls System page; here they are fictional.

PanelInputs → toolFunction
ScheduleProgramme update → Float Consumption Analyser, Critical Path Stability MonitorfloatConsumption, cpStability
ProgressMeasured quantities → Progress Measurement Assessment; PV/EV → Earned Value CalculatorprogressAssessment, earnedValue
Cost and forecastBudget, EV, AC, ETC → Cost Forecast CalculatorcostForecast
Risk and changeRisk register → Risk and Early Warning; early-warning answersriskRegister, earlyWarning
Assurance and governancePackage quality scores, report checks → Reporting Compliance Checker; interfaces → Interface Tracker; ratings → ScorecardreportingCompliance, interfaceTracker, contractorScorecard
Decision intelligenceAction log → Management Action Prioritisation; all of the above → health rulesprioritiseActions, programmeHealth

Common definitions and RAG thresholds

Used by every tool, this dashboard and the review generator, so a rating means the same thing everywhere. Reading aids, not an industry standard.

MeasureGreenAmberRed
Performance index (SPI, SPI(t), CPI)at or above 0.950.90 to below 0.95below 0.90
Forecast completion against contracton or before the contract dateup to 4 weeks latemore than 4 weeks late
Estimate at completion against budgetat or below budgetup to 5% overmore than 5% over
Key milestones achieved when due90% or more70% to below 90%below 70%
Pending change older than 60 daysfewer than 3 items3 to 9 items10 or more items
Risks above the escalation thresholdnone1 or 23 or more
Schedule quality score80% or more60% to below 80%below 60%
Total floatmore than 10 days1 to 10 days (near-critical)zero or negative (critical)
Money
Any currency unit, used consistently; shown to one decimal place. Demonstration data is in AED million.
Indices
SPI, SPI(t), CPI, TCPI shown to two decimal places. 1.00 means exactly on plan.
Time
Calendar days unless stated; weeks where the measure is reported to executives. Positive delay = later than planned.
Percentages
Whole numbers, except progress gaps shown to one decimal place in percentage points.
Ratings
Judgement-based ratings (1–5) are labelled as such and never presented as measured performance.
Planned value (PV)
Budgeted cost of work scheduled to date.
Earned value (EV)
Budgeted cost of work actually performed, from measured progress.
Actual cost (AC)
Cost incurred for the work performed.
Earned schedule (ES)
The point in the plan at which today’s EV was due to be earned.
SPI(t)
Earned schedule ÷ actual time. Preferred to SPI for schedule performance.
EAC
Estimate at completion: forecast final cost, with its basis stated.
TCPI
Cost efficiency the remaining work needs to meet a target.
Total float
How far an activity can slip before it delays completion.
Expected exposure
Probability × impact, summed. Not a confidence level.
Residual
After mitigation has taken effect.
Fact / Forecast / Assumption / Judgement
Fact: measured or recorded. Forecast: a projected value. Assumption: a condition the forecast depends on. Judgement: a stated professional view.