Schedule
RedForecast 18-Nov-28 against contract 30-Sep-28
▼ worsening since last month
- SPI(t) 0.92
- 7 of 10 milestones met when due
- Critical path migrated 2 times in 4 updates
Expertise
Project ControlsPlanning and Primavera P6Schedule AssuranceEOT ClaimsForensic Delay AnalysisProgramme ManagementPMO LeadershipDigital Project ControlsAll expertiseFramework
Project Controls Management System100-Point Schedule Assurance FrameworkHow I WorkOperating PrinciplesImplementation ChecklistsMaturity ModelTools
Project Controls IntelligenceDecision Centre: start hereDirector’s 10-Minute ReviewForensic Delay LabProgramme DashboardProgramme SimulatorRisk and Early WarningExecutive Review GeneratorSchedule Assurance ChallengeProgramme Management toolsChecklists and templatesProgramme intelligence
Illustrative · fictional programme and dataProgramme Meridian (Mixed-use development: two towers, podium, public realm), month 12 of 24, data date 31-Oct-26. Every figure below is calculated by the same functions as the public tools, from one fictional data set, to show how controls data should flow into an executive view.
Not connected to Primavera P6, a cost system, Aconex, Power BI or any live data. Money in AED million. RAG ratings follow the platform definitions.
2 areas red and 4 amber of 6 rated. Schedule is red: the façade package now drives completion and forecast completion has moved later for three updates running. Three decisions are needed before the Board report.
Forecast 18-Nov-28 against contract 30-Sep-28
▼ worsening since last month
47.6% reported: a 3.8-point gap
▼ worsening since last month
+4.1% on budget of 4,800
▼ worsening since last month
Expected exposure after mitigation (was 205)
▲ improving since last month
Schedule quality, budget-weighted (was 64%)
▲ improving since last month
2 actions to act on now
■ unchanged since last month
| Measure | Value | RAG | Trend | Thresholds (green · amber · red) | Source |
|---|---|---|---|---|---|
| Forecast completion against contract | +7 weeks | Red | ▼ worsening | on or before the contract date · up to 4 weeks late · more than 4 weeks late | Programme update |
| SPI(t) | 0.92 | Amber | ▼ worsening | at or above 0.95 · 0.90 to below 0.95 · below 0.90 | Earned Value Calculator |
| CPI | 0.94 | Amber | ▼ worsening | at or above 0.95 · 0.90 to below 0.95 · below 0.90 | Earned Value Calculator |
| EAC against budget | +4.1% | Amber | ▼ worsening | at or below budget · up to 5% over · more than 5% over | Cost Forecast Calculator |
| Milestones met when due | 7 of 10 | Amber | ▲ improving | 90% or more · 70% to below 90% · below 70% | Milestone register |
| Pending change older than 60 days | 11 | Red | ▼ worsening | fewer than 3 items · 3 to 9 items · 10 or more items | Change register |
| Risks above escalation threshold | 1 | Amber | ■ unchanged | none · 1 or 2 · 3 or more | Risk and Early Warning |
| Schedule quality score | 73% | Amber | ▲ improving | 80% or more · 60% to below 80% · below 60% | Schedule Health Check |
| Milestone | Baseline | Forecast / actual | Float (d) | Status |
|---|---|---|---|---|
| Basement complete | 15-Aug-26 | 02-Sep-26 | — | Achieved late |
| Tower 1 frame topped out | 15-Oct-26 | 20-Oct-26 | — | Achieved late |
| Building watertight, tower 1 | 30-Nov-26 | 25-Jan-27 | -38 | Forecast late |
| Energisation | 31-Mar-27 | 05-May-27 | -35 | Forecast late |
| Façade complete | 30-Apr-27 | 18-Jun-27 | -49 | Forecast late |
| MEP first fix complete | 31-May-27 | 14-Jun-27 | 6 | Near-critical |
| Handover zone A | 30-Jun-28 | 15-Aug-28 | -46 | Forecast late |
| Practical completion | 30-Sep-28 | 18-Nov-28 | -49 | Forecast late |
Critical path: 2 migrations in four updates; core critical activities F900, S100, S200. 5 milestones in negative float, 1 near-critical. Stability monitor →
■ Planned value · ■ Earned value · ■ Actual cost · ┆ data date
| Month | PV | EV | AC | SPI(t) | CPI |
|---|---|---|---|---|---|
| 7 | 987 | 937 | 966 | 0.97 | 0.97 |
| 8 | 1,244 | 1,162 | 1,210 | 0.96 | 0.96 |
| 9 | 1,519 | 1,395 | 1,453 | 0.95 | 0.96 |
| 10 | 1,806 | 1,634 | 1,720 | 0.94 | 0.95 |
| 11 | 2,101 | 1,874 | 1,973 | 0.93 | 0.95 |
| 12 | 2,400 | 2,113 | 2,248 | 0.92 | 0.94 |
| Package | SPI | CPI | Forecast delay | Reported | Verified | Schedule | Cost |
|---|---|---|---|---|---|---|---|
| A · Structure | 0.98 | 0.97 | +1 wks | 62% | 61% | Amber | Green |
| B · Façade | 0.81 | 0.90 | +7 wks | 49% | 44% | Red | Amber |
| C · MEP | 0.93 | 0.95 | +3 wks | 47% | 39% | Amber | Amber |
| D · Fit-out and public realm | 0.54 | 0.85 | +5 wks | 18% | 17% | Red | Red |
The programme average hides package B: it drives completion while A and C run close to plan. Package D’s low SPI reflects a late start that is not yet on the critical path.
| Basis | EAC | Variance at completion | TCPI |
|---|---|---|---|
| Past variance will not recur | 4,935 | -135 | 1.00 |
| Cost performance continues | 5,107 | -307 | 0.94 |
| Cost and schedule pressure both continue | 5,495 | -695 | 0.83 |
| Bottom-up estimate | 4,938 | -138 | 1.00 |
| Reported forecast (forecast) | 4,997 | -197 | — |
The reported EAC is within the formula range but below the cost-performance-continues estimate. It excludes pending change of about 215 (assumption). To finish within budget, remaining work needs a CPI of 1.05 against 0.94 achieved. Test it →
| Risk or opportunity | Owner | Residual score | Residual exposure | Trend |
|---|---|---|---|---|
| R06 Utility connection date | Interface manager | 16 ▲ | 21 | Stable |
| R03 Summer labour shortage, MEP | Contractor C | 12 | 35 | New |
| R02 Fire strategy approval late | Design manager | 9 | 20 | Stable |
| O01 Prefabricated bathroom pods (opportunity) | Design manager | 9 | 35 | New |
| R01 Façade supplier capacity | Package manager B | 8 | 36 | Up |
| R04 End-user design changes, fit-out | No owner | 6 | 18 | Up |
Risk-adjusted forecast 5,092 (forecast, expected-value method, no confidence level). Change: 38 items pending, about 215, 11 older than 60 days (was 8). Risk and Early Warning →
| Package | Schedule quality | Report compliance | Performance rating* | Weakest measure* |
|---|---|---|---|---|
| A · Structure | 86% | 98% | 3.95 / 5 | Resources against plan, Interfaces met |
| B · Façade | 58% | 62% · 4 d late | 2.50 / 5 | Milestones met, Updates accepted first time, Resources against plan |
| C · MEP | 71% | 86% · 1 d late | 2.78 / 5 | Reported vs verified progress |
| D · Fit-out and public realm | 69% | 96% | 3.30 / 5 | Interfaces met |
*Judgement-based ratings against written criteria, not measured performance. Schedule quality and report compliance are checked against defined criteria.
| Interface | From → to | Need | Forecast | Status |
|---|---|---|---|---|
| IF-01 Fire authority inspection before zone A access · critical | Authority (via employer) → D Fit-out | 2026-10-15 | 2026-11-20 | Overdue |
| IF-02 Permanent power for energisation · critical | Utility (via employer) → C MEP | 2026-11-30 | 2027-01-10 | At risk |
| IF-04 MEP riser access levels 1–5 | A Structure → C MEP | 2026-11-10 | 2026-11-10 | Due in 30 days |
| IF-03 Façade bays 1–3 handed to fit-out | B Façade → D Fit-out | 2026-12-15 | 2026-12-15 | On track |
Control tower
Score 77 of 100 on twelve indicators; 10 triggered, 1 not known.
| Update | Overlap | Joined | Left | Finish |
|---|---|---|---|---|
| Month 9 → Month 10 | 100% | — | — | -7 d |
| Month 10 → Month 11 | 43% | B300, B310 | S110, S120 | -14 d |
| Month 11 → Month 12 | 43% | B320, K400 | S100, S200 | -14 d |
Aged change is rising (8 → 11). Pending change is not yet in the budget or the baseline, so the EAC and the forecast completion both understate the exposure until it is decided.
Change Impact Assessment →| # | Action | Owner | Priority | Category | Overdue |
|---|---|---|---|---|---|
| 1 | Decide on façade recovery programme | Programme director | 25 | Act now | — |
| 2 | Confirm fire authority inspection date | No owner | 18 | Act now | 16 d |
| 3 | Close out 11 aged change requests | Commercial lead | 15 | Plan | 21 d |
| 4 | Verify MEP progress on levels 1–5 | Controls lead | 12 | Quick win | — |
| 5 | Assign owner to end-user change risk R04 | Risk manager | 10 | Quick win | 7 d |
| 6 | Issue revised reporting template to contractors | Controls lead | 6 | Quick win | — |
Each panel is computed at build time from the demonstration data by the same functions the public tools run in your browser. In a real programme the inputs would come from the source systems named on the Controls System page; here they are fictional.
| Panel | Inputs → tool | Function |
|---|---|---|
| Schedule | Programme update → Float Consumption Analyser, Critical Path Stability Monitor | floatConsumption, cpStability |
| Progress | Measured quantities → Progress Measurement Assessment; PV/EV → Earned Value Calculator | progressAssessment, earnedValue |
| Cost and forecast | Budget, EV, AC, ETC → Cost Forecast Calculator | costForecast |
| Risk and change | Risk register → Risk and Early Warning; early-warning answers | riskRegister, earlyWarning |
| Assurance and governance | Package quality scores, report checks → Reporting Compliance Checker; interfaces → Interface Tracker; ratings → Scorecard | reportingCompliance, interfaceTracker, contractorScorecard |
| Decision intelligence | Action log → Management Action Prioritisation; all of the above → health rules | prioritiseActions, programmeHealth |
Used by every tool, this dashboard and the review generator, so a rating means the same thing everywhere. Reading aids, not an industry standard.
| Measure | Green | Amber | Red |
|---|---|---|---|
| Performance index (SPI, SPI(t), CPI) | at or above 0.95 | 0.90 to below 0.95 | below 0.90 |
| Forecast completion against contract | on or before the contract date | up to 4 weeks late | more than 4 weeks late |
| Estimate at completion against budget | at or below budget | up to 5% over | more than 5% over |
| Key milestones achieved when due | 90% or more | 70% to below 90% | below 70% |
| Pending change older than 60 days | fewer than 3 items | 3 to 9 items | 10 or more items |
| Risks above the escalation threshold | none | 1 or 2 | 3 or more |
| Schedule quality score | 80% or more | 60% to below 80% | below 60% |
| Total float | more than 10 days | 1 to 10 days (near-critical) | zero or negative (critical) |