Calculator · Cost and performance
Earned Value and Earned Schedule Calculator
Cost and schedule performance from your own figures, with schedule variance measured in time.
Enter your own figures in any currency or unit, used consistently. The form opens with a fictional worked example so you can see how it reads. Calculations run in your browser; nothing is sent or stored. It does not connect to any scheduling or cost system.
Calculator How this tool works: inputs, method and limitations
- Purpose
- Turn planned value, earned value and actual cost into the standard performance indices, and measure schedule slippage in periods rather than money.
- Intended user
- Project controls managers, cost engineers and planners preparing a monthly performance view; managers who want to check a reported SPI or CPI.
- Output
- Variances, indices, earned schedule and an independent duration estimate, each with a one-line reading.
- How the result is produced
- Calculated.
- PCMS discipline
- Earned Value Management and Earned Schedule · Volume 3: Reporting and Performance Management
- Learn the method
- Earned value and earned schedule (Practitioner pathway)
- Worked example
- The tool opens with a fictional worked example; “Load example” restores it and “Clear” resets every input. Results can be downloaded as CSV or printed.
- Inputs
- Budget at completion (BAC)
- Planned value curve: cumulative PV for each reporting period of the plan
- Periods elapsed at the data date
- Earned value (EV) at the data date
- Actual cost (AC) at the data date
- Method
- SV = EV − PV; CV = EV − AC; SPI = EV ÷ PV; CPI = EV ÷ AC.
- Earned Schedule: find the last whole period whose cumulative PV does not exceed EV, then add the fraction of the next period that EV covers (linear between the two PV points).
- SV(t) = ES − AT; SPI(t) = ES ÷ AT; independent duration estimate = planned duration ÷ SPI(t).
- Limitations
- Only as good as the PV curve and the way EV is measured; weak progress rules give a precise-looking wrong answer.
- Programme-level indices can hide a critical package running late behind non-critical work running early.
- SPI(t) is a trend indicator, not a schedule forecast: the critical path decides completion.
- Suggested actions
- Agree the progress-measurement rules before relying on EV.
- Where SPI(t) and the scheduled forecast disagree, ask which is right and why.
- Break the indices down by package before acting on a programme-level number.
- How to read the result
- The result is indicative: a structured prompt for professional judgement, not a determination. Use it to decide what to check next, then confirm against the programme, the records and the contract.
- Related
- Expertise: Project Controls · Reference: Earned value standards · Case study: Hudayriyat West programme · 100-Point Framework · Not sure where to start? Decision Centre
Runs in your browser; nothing is sent to a server. A practitioner’s aid, not a certification or a contractual determination. See how the measures combine in the Programme Intelligence Dashboard. All tools →