Expertise

Project ControlsPlanning and Primavera P6Schedule AssuranceEOT ClaimsForensic Delay AnalysisProgramme ManagementPMO LeadershipDigital Project ControlsAll expertise

Framework

Project Controls Management System100-Point Schedule Assurance FrameworkHow I WorkOperating PrinciplesImplementation ChecklistsMaturity Model

Tools

Project Controls IntelligenceDecision Centre: start hereDirector’s 10-Minute ReviewForensic Delay LabProgramme DashboardProgramme SimulatorRisk and Early WarningExecutive Review GeneratorSchedule Assurance ChallengeProgramme Management toolsChecklists and templates

Academy

Learning pathwaysProfessional ReferencesPrimavera P6 GuidesThe SCL Protocol seriesGlossary

Insights

ArticlesCase StudiesProjectsDirector’s PlaybookRed Flags and Failure AtlasLessons from Major ProgrammesClaims and Delay articles

About

AboutExecutive ProfileDownload Executive CVLinkedIn
Search

Searches articles, case studies, guides and tools on this site. Runs in your browser — nothing is sent anywhere.

Calculator · Cost and performance

Earned Value and Earned Schedule Calculator

Cost and schedule performance from your own figures, with schedule variance measured in time.

Enter your own figures in any currency or unit, used consistently. The form opens with a fictional worked example so you can see how it reads. Calculations run in your browser; nothing is sent or stored. It does not connect to any scheduling or cost system.

Whole reporting periods to the data date.
One value per period, from period 1 to the planned finish, separated by spaces, new lines or semicolons. The number of values is the planned duration. Commas are read as thousands separators.
Calculator How this tool works: inputs, method and limitations
Purpose
Turn planned value, earned value and actual cost into the standard performance indices, and measure schedule slippage in periods rather than money.
Intended user
Project controls managers, cost engineers and planners preparing a monthly performance view; managers who want to check a reported SPI or CPI.
Output
Variances, indices, earned schedule and an independent duration estimate, each with a one-line reading.
How the result is produced
Calculated.
PCMS discipline
Earned Value Management and Earned Schedule · Volume 3: Reporting and Performance Management
Learn the method
Earned value and earned schedule (Practitioner pathway)
Worked example
The tool opens with a fictional worked example; “Load example” restores it and “Clear” resets every input. Results can be downloaded as CSV or printed.
Inputs
  • Budget at completion (BAC)
  • Planned value curve: cumulative PV for each reporting period of the plan
  • Periods elapsed at the data date
  • Earned value (EV) at the data date
  • Actual cost (AC) at the data date
Method
  • SV = EV − PV; CV = EV − AC; SPI = EV ÷ PV; CPI = EV ÷ AC.
  • Earned Schedule: find the last whole period whose cumulative PV does not exceed EV, then add the fraction of the next period that EV covers (linear between the two PV points).
  • SV(t) = ES − AT; SPI(t) = ES ÷ AT; independent duration estimate = planned duration ÷ SPI(t).
Limitations
  • Only as good as the PV curve and the way EV is measured; weak progress rules give a precise-looking wrong answer.
  • Programme-level indices can hide a critical package running late behind non-critical work running early.
  • SPI(t) is a trend indicator, not a schedule forecast: the critical path decides completion.
Suggested actions
  • Agree the progress-measurement rules before relying on EV.
  • Where SPI(t) and the scheduled forecast disagree, ask which is right and why.
  • Break the indices down by package before acting on a programme-level number.
How to read the result
The result is indicative: a structured prompt for professional judgement, not a determination. Use it to decide what to check next, then confirm against the programme, the records and the contract.