Expertise

Project ControlsPlanning and Primavera P6Schedule AssuranceEOT ClaimsForensic Delay AnalysisProgramme ManagementPMO LeadershipDigital Project ControlsAll expertise

Framework

Project Controls Management System100-Point Schedule Assurance FrameworkHow I WorkOperating PrinciplesImplementation ChecklistsMaturity Model

Tools

Project Controls IntelligenceDecision Centre: start hereDirector’s 10-Minute ReviewForensic Delay LabProgramme DashboardProgramme SimulatorRisk and Early WarningExecutive Review GeneratorSchedule Assurance ChallengeProgramme Management toolsChecklists and templates

Academy

Learning pathwaysProfessional ReferencesPrimavera P6 GuidesThe SCL Protocol seriesGlossary

Insights

ArticlesCase StudiesProjectsDirector’s PlaybookRed Flags and Failure AtlasLessons from Major ProgrammesClaims and Delay articles

About

AboutExecutive ProfileDownload Executive CVLinkedIn
Search

Searches articles, case studies, guides and tools on this site. Runs in your browser — nothing is sent anywhere.

Expertise

Extension of Time (EOT) Claims

Time entitlement established the way it has to be defended — event by event, along the critical path.

An Extension of Time adjusts the completion date to reflect delay the Contractor is entitled to more time for. The gap between days claimed and days awarded is usually a gap in discipline, not entitlement — which is where a rigorous approach earns its keep.

What EOT entitlement rests on

Entitlement is not a single number; it is the sum of individual delay events, each established on its own basis:

  • a valid contractual mechanism and timely notice;
  • a delay event that is the Employer’s risk under the contract;
  • a cause-and-effect link traced to the critical path of the programme current at the time;
  • honest treatment of any concurrent delay;
  • assessment against the baseline, updated programmes and as-built records.

Method

The technique is matched to the timing and records — typically Time Impact Analysis for prospective assessment, or windows and as-built methods retrospectively (see delay analysis for the methods in full). Each event is modelled, not asserted, and its effect on completion demonstrated rather than claimed.

Mitigation, acceleration and risk allocation

Reasonable mitigation is expected and assessed distinctly from acceleration — the cost of buying time back. Underpinning all of it is the contract’s allocation of risk between Employer and Contractor, which decides not just how much time is due but who pays for it.

Assessment that holds

Whether preparing or reviewing, the test is the same: would this survive independent scrutiny? On a major Abu Dhabi infrastructure programme, a 291-day claim was assessed to an approved 64 days — a figure that sat between the Engineer’s 66 and an independent specialist’s 60, and stood because every day was traceable. The reviewer’s discipline is set out in how to assess an EOT claim; broader claims strategy in construction claims.

This describes professional project-controls and claims practice; it is not legal advice.

Discuss this capability for your programme.

Connect →

Frequently asked questions

What does an extension of time assessment need to show?

That a qualifying event occurred, that notice was given as the contract requires, that the event delayed the critical path to completion or a key milestone, and by how much, supported by contemporaneous records.

What is a time impact analysis?

A prospective method that inserts a fragnet representing the delay event into the most recent accepted programme update and measures the change in completion. It is the method many contracts and the SCL Protocol favour for contemporaneous assessment.

How is concurrent delay treated?

It depends on the contract and the governing law. The SCL Protocol’s guidance is that a contractor delay running alongside an employer delay should not reduce the extension of time due for the employer delay, but compensation is treated differently. Contract terms take precedence.

Is a delay analysis a legal opinion?

No. A delay analysis is technical evidence about cause and effect on the programme. Entitlement depends on the contract and the law, and formal legal advice comes from lawyers. The analysis on this site is professional methodology, not legal advice or representation.

Across the platform