Expertise

Project ControlsPlanning and Primavera P6Schedule AssuranceEOT ClaimsForensic Delay AnalysisProgramme ManagementPMO LeadershipDigital Project ControlsAll expertise

Framework

Project Controls Management System100-Point Schedule Assurance FrameworkHow I WorkOperating PrinciplesImplementation ChecklistsMaturity Model

Tools

Project Controls IntelligenceDecision Centre: start hereDirector’s 10-Minute ReviewForensic Delay LabProgramme DashboardProgramme SimulatorRisk and Early WarningExecutive Review GeneratorSchedule Assurance ChallengeProgramme Management toolsChecklists and templates

Academy

Learning pathwaysProfessional ReferencesPrimavera P6 GuidesThe SCL Protocol seriesGlossary

Insights

ArticlesCase StudiesProjectsDirector’s PlaybookRed Flags and Failure AtlasLessons from Major ProgrammesClaims and Delay articles

About

AboutExecutive ProfileDownload Executive CVLinkedIn
Search

Searches articles, case studies, guides and tools on this site. Runs in your browser — nothing is sent anywhere.

Case Studies

Evidence, worked through.

Quantified outcomes from forensic delay analysis, EOT assessment and digital schedule assurance — the methodology behind the numbers, with confidentiality preserved.

Forensic Delay Analysis · EOT
291 → 64
days · claimed to approved

291 Days Claimed, 64 Days Approved

How a 291-day Extension of Time claim was tested event by event against the contemporaneous record, and resolved to a defensible 64 days — a figure the Engineer and an independent specialist each reached within a few days.

Context
Riyadh City Infrastructure Programme, Abu Dhabi — the infrastructure-handover milestone.
Challenge
A 291-day extension-of-time claim built on 17 delay events across 9 milestones, most framed identically.
Method
Retrospective, windowed analysis with rules fixed in advance; each event tested against the contemporaneous record and the path driving the affected milestone.
Result
64 days approved. Independent assessments by the Engineer (66 days) and a forensic specialist (60 days) landed within a six-day band.
Read the case study →
Forensic Delay Analysis
426 → 91
days · claimed to approved

426 Days Reduced to 91

Forensic review of a 426-day EOT position — programme analysis, critical-path cause and effect, and the evidence behind the 91 days approved.

Context
Hudayriyat West velodrome, Abu Dhabi — the Engineer's assessment on the Employer's behalf.
Challenge
A 426-day EOT position to final completion, built from 16 delay events across design, procurement and construction.
Method
Windowed longest-path analysis across nine windows, tracking the driving path as it moved; each event tested against the contract and the record.
Result
91 days approved on the evidence, with every rejected day tied to a recorded reason.
Read the case study →
Digital Project Controls · Schedule Assurance
25% → 83%
baseline conformance · 100-point framework

Schedule Quality: 25% to 83%

How structured, repeatable baseline-review comments against a 100-point Employer framework lifted one package programme from around 25% to over 83% conformance — and held it there.

Context
One package programme on Hudayriyat West, Abu Dhabi: the contractor's baseline and revised programmes.
Challenge
Initial conformance of around 25% against the 100-Point Employer Schedule Assurance Framework — schedules not reliable for progress, forecasting or decisions.
Method
Every submission run through a Python and Primavera P6 assurance engine against the 100-point framework, with DCMA 14-point checks as a supporting reference; structured comments closed out each cycle.
Result
Conformance rose to over 83% against the 100-point framework and held. It is a programme-specific measure, not a DCMA score or an external benchmark.
Read the case study →
Project Controls Leadership
16 → 1
contracts · unified to one controls standard

One Controls Standard, 16 Contracts

Leading the planning function across a city-scale programme — 16 contracts, 12 senior planners, one standard that made the whole programme governable.

Context
AED 13.47B urban-infrastructure programme, Abu Dhabi — Employer-side Programme Planning Manager.
Challenge
16 contracts and 14 independently built schedules with inconsistent coding, and the interfaces that drive the programme missing from all of them.
Method
A common standard — coding, a fragnet library and interface capture — and a reconciled master programme of 15,000+ activities, with a team of twelve senior planners.
Result
One governable programme environment, with comparable information across every contract.
Read the case study →
Project Controls · Programme Governance
AED 28.1B
flagship programme · integrated controls

AED 28.1B Hudayriyat West

Leading integrated project controls across a flagship AED 28.1B island-development programme — one defensible view of time, cost, risk and performance.

Context
AED 28.1B island development in Abu Dhabi, delivered through seven concurrent construction packages; integrated controls led within the EllisDon PMC.
Challenge
Each package used its own methodology, software, WBS and reporting format, so there was no reconciled programme picture to decide on.
Method
A Project Controls Framework and procedures manual as one common standard, a federated P6 environment and 100-point assurance every cycle.
Result
A single reconciled programme picture; the standard adopted as the Employer's template; a planning function of fifteen professionals.
Read the case study →