Case Studies
Evidence, worked through.
Quantified outcomes from forensic delay analysis, EOT assessment and digital schedule assurance — the methodology behind the numbers, with confidentiality preserved.
291 Days Claimed, 64 Days Approved
How a 291-day Extension of Time claim was tested event by event against the contemporaneous record, and resolved to a defensible 64 days — a figure the Engineer and an independent specialist each reached within a few days.
- Context
- Riyadh City Infrastructure Programme, Abu Dhabi — the infrastructure-handover milestone.
- Challenge
- A 291-day extension-of-time claim built on 17 delay events across 9 milestones, most framed identically.
- Method
- Retrospective, windowed analysis with rules fixed in advance; each event tested against the contemporaneous record and the path driving the affected milestone.
- Result
- 64 days approved. Independent assessments by the Engineer (66 days) and a forensic specialist (60 days) landed within a six-day band.
426 Days Reduced to 91
Forensic review of a 426-day EOT position — programme analysis, critical-path cause and effect, and the evidence behind the 91 days approved.
- Context
- Hudayriyat West velodrome, Abu Dhabi — the Engineer's assessment on the Employer's behalf.
- Challenge
- A 426-day EOT position to final completion, built from 16 delay events across design, procurement and construction.
- Method
- Windowed longest-path analysis across nine windows, tracking the driving path as it moved; each event tested against the contract and the record.
- Result
- 91 days approved on the evidence, with every rejected day tied to a recorded reason.
Schedule Quality: 25% to 83%
How structured, repeatable baseline-review comments against a 100-point Employer framework lifted one package programme from around 25% to over 83% conformance — and held it there.
- Context
- One package programme on Hudayriyat West, Abu Dhabi: the contractor's baseline and revised programmes.
- Challenge
- Initial conformance of around 25% against the 100-Point Employer Schedule Assurance Framework — schedules not reliable for progress, forecasting or decisions.
- Method
- Every submission run through a Python and Primavera P6 assurance engine against the 100-point framework, with DCMA 14-point checks as a supporting reference; structured comments closed out each cycle.
- Result
- Conformance rose to over 83% against the 100-point framework and held. It is a programme-specific measure, not a DCMA score or an external benchmark.
One Controls Standard, 16 Contracts
Leading the planning function across a city-scale programme — 16 contracts, 12 senior planners, one standard that made the whole programme governable.
- Context
- AED 13.47B urban-infrastructure programme, Abu Dhabi — Employer-side Programme Planning Manager.
- Challenge
- 16 contracts and 14 independently built schedules with inconsistent coding, and the interfaces that drive the programme missing from all of them.
- Method
- A common standard — coding, a fragnet library and interface capture — and a reconciled master programme of 15,000+ activities, with a team of twelve senior planners.
- Result
- One governable programme environment, with comparable information across every contract.
AED 28.1B Hudayriyat West
Leading integrated project controls across a flagship AED 28.1B island-development programme — one defensible view of time, cost, risk and performance.
- Context
- AED 28.1B island development in Abu Dhabi, delivered through seven concurrent construction packages; integrated controls led within the EllisDon PMC.
- Challenge
- Each package used its own methodology, software, WBS and reporting format, so there was no reconciled programme picture to decide on.
- Method
- A Project Controls Framework and procedures manual as one common standard, a federated P6 environment and 100-point assurance every cycle.
- Result
- A single reconciled programme picture; the standard adopted as the Employer's template; a planning function of fifteen professionals.