Expertise

Project ControlsPlanning and Primavera P6Schedule AssuranceEOT ClaimsForensic Delay AnalysisProgramme ManagementPMO LeadershipDigital Project ControlsAll expertise

Framework

Project Controls Management System100-Point Schedule Assurance FrameworkHow I WorkOperating PrinciplesImplementation ChecklistsMaturity Model

Tools

Project Controls IntelligenceDecision Centre: start hereDirector’s 10-Minute ReviewForensic Delay LabProgramme DashboardProgramme SimulatorRisk and Early WarningExecutive Review GeneratorSchedule Assurance ChallengeProgramme Management toolsChecklists and templates

Academy

Learning pathwaysProfessional ReferencesPrimavera P6 GuidesThe SCL Protocol seriesGlossary

Insights

ArticlesCase StudiesProjectsDirector’s PlaybookRed Flags and Failure AtlasLessons from Major ProgrammesClaims and Delay articles

About

AboutExecutive ProfileDownload Executive CVLinkedIn
Search

Searches articles, case studies, guides and tools on this site. Runs in your browser — nothing is sent anywhere.

Digital Project Controls · Schedule Assurance

Schedule Quality: 25% to 83%

25% → 83% baseline conformance · 100-point framework

How structured, repeatable baseline-review comments against a 100-point Employer framework lifted one package programme from around 25% to over 83% conformance — and held it there.

At a glance

Project context
Hudayriyat West Island Development, Abu Dhabi: one package programme, the contractor’s baseline and revised programmes.
Challenge
A contractor’s schedules that could not be relied on for progress, forecasting or delay assessment.
Initial condition
About 25% conformance with the 100-Point Employer Schedule Assurance Framework, with most review comments unresolved.
Intervention
Every submission scored the same way each cycle, with structured, closeable comments and close-out tracked as the measure.
Methodology
A Python and Primavera P6 assurance engine applying the 100-point framework, with the DCMA 14-point checks as a supporting reference.
Results
Conformance rose from about 25% to over 83% against the 100-point framework (not a DCMA score) and held there.
Professional contribution
Developing the 100-point framework and the assurance engine, and running the assurance cycle with the controls team and contractors.
Lessons learned
The comments mattered more than the score: closeable comments against a defined standard turn argument into a tracked improvement.
Tools and methods
Schedule Assurance Challenge · 100-Point Schedule Assurance Framework

01 — The Position

On one package of the works, the contractor’s baseline and revised programmes were reviewed against the 100-Point Employer Schedule Assurance Framework, and initial conformance sat at around 25% on the framework’s 100-point scale, with most review comments unresolved. In plain terms: schedules that could not be relied on for progress measurement, forecasting or management decisions.

02 — The Evidence

Each Primavera P6 submission from the package contractor, cycle by cycle, and the structured review comments raised against it under the 100-point checklist — one specific, closeable comment per non-conformance, not a blanket pass or fail. Confidential project records limit the level of detail that can be published.

03 — The Programme Analysis

Every submission was run against the 100-point framework through a Python and Primavera P6 assurance engine, using the DCMA 14-point checks as a recognised schedule-quality reference within the broader, programme-specific structure. The output was not a score alone — it was a structured comment set per check, each tied to a dimension and a close-out path, so “this programme is weak” became a specific list of things to fix.

25%
baseline conformance
→
100-point
review comments issued
→
Close-out
every cycle
→
83%
conformance, held
Each submission on the package scored against the 100-point framework, with a specific, closeable comment per non-conformance — tracked to over 83% conformance, and held.

04 — Event Mapping

The review comments were mapped across the six assurance dimensions — baseline, logic and network, progress, forecast, critical path and float, governance and reporting — so the pattern of weakness was visible, not just the count. Each comment had an owner and a route to closure, and closure on re-verification, cycle on cycle, became the measure.

05 — Cause & Effect

Low comment compliance meant the programme could not be trusted — open logic, constraint-driven dates, progress that did not reconcile. At around 25%, the programme was a long way short of the framework’s requirements.

06 — Critical Path

A recurring class of comment was a critical path driven by constraints rather than logic. Until those specific comments were closed, no forecast built on the programme could be trusted — which is why the assurance comments, not the headline dates, were the thing to drive.

07 — Entitlement / Assessment

The conformance score — around 25% at the outset — was a defined, repeatable measure: a Schedule Assurance Score on the framework’s 100-point scale, scored identically every cycle. It is not a DCMA score, an industry benchmark, or an externally certified result.

08 — The Decision

Score every submission the same way, every cycle; issue structured, closeable comments rather than opinions; track comment close-out as the metric; re-issue what stays open; and make the score and the open comments visible to governance — so improvement was owned, not hoped for.

09 — The Outcome

Conformance rose from around 25% to over 83% against the 100-point Employer Schedule Assurance Framework, and held there. Operationally: reliable baselines, verifiable progress, forecasts worth planning against, and an assurance standard applied the same way every cycle.

10 — Director’s Lesson

The score was never the point — the comments were. A repeatable assurance measure, plus specific closeable comments against a defined framework, turns ‘is this programme any good?’ from a monthly argument into a tracked, improving number — and gives the contractor a clear path to a baseline everyone can rely on.

Apply this to your programme

Want programmes you can actually rely on? Start by checking:

  • Are you scoring every submission the same way, every cycle?
  • Do your review comments map to specific, closeable findings — not opinions?
  • Is the critical path logic-driven, or held by constraints?
  • Is the conformance trend visible to governance?

Then put it to work: 100-Point Framework · Schedule Health Check · Schedule Health Checklist · Playbook — Baseline Assurance.

Follow the thread

Case study → method → evidence → decision: 100-Point Framework · Digital Project Controls · Schedule Health Check · Director’s Playbook. See the decision framework behind it in How I Work.

Author
Rishi Javeri · Project Controls & Programme Governance · FCIArb | FIE | PMP | PSP | MCIOB | MAPM

This case study describes Rishi Javeri's professional project-controls role and methodology; it does not disclose confidential parties, contracts, schedules or commercially sensitive material, and does not imply sole delivery of the programme. It describes professional practice, not legal advice.

Next step

This case applies the 100-point Employer Schedule Assurance Framework.

A related question? Discuss a professional enquiry, after reading How I Work.