Expertise

Project ControlsPlanning and Primavera P6Schedule AssuranceEOT ClaimsForensic Delay AnalysisProgramme ManagementPMO LeadershipDigital Project ControlsAll expertise

Framework

Project Controls Management System100-Point Schedule Assurance FrameworkHow I WorkOperating PrinciplesImplementation ChecklistsMaturity Model

Tools

Project Controls IntelligenceDecision Centre: start hereDirector’s 10-Minute ReviewForensic Delay LabProgramme DashboardProgramme SimulatorRisk and Early WarningExecutive Review GeneratorSchedule Assurance ChallengeProgramme Management toolsChecklists and templates

Academy

Learning pathwaysProfessional ReferencesPrimavera P6 GuidesThe SCL Protocol seriesGlossary

Insights

ArticlesCase StudiesProjectsDirector’s PlaybookRed Flags and Failure AtlasLessons from Major ProgrammesClaims and Delay articles

About

AboutExecutive ProfileDownload Executive CVLinkedIn
Search

Searches articles, case studies, guides and tools on this site. Runs in your browser — nothing is sent anywhere.

Checklist

Schedule Health Checklist

Purpose

A quick technical read on whether a programme is sound — before its dates are trusted.

Who it’s for

Planners and controls reviewers checking any Primavera P6 programme.

When to use it

On any baseline or update you need to rely on.

Key areas covered
  • Logic, leads & lags
  • Constraints & float
  • Durations & dates
  • Critical-path tests
  • CPLI & BEI
Related framework Baseline Integrity →
Download PDF ↓ // Tick items on screen for your own review

A DCMA-based read on whether a programme is technically sound — before its dates are trusted. Thresholds are common industry guides; adapt them to your project.

Logic & network

  • Missing logic ≤ 5% (activities without a predecessor and successor)
  • Leads (negative lag) = 0
  • Lags ≤ 5% of relationships
  • Finish-to-start relationships ≥ 90%

Constraints & float

  • Hard constraints ≤ 5% and justified
  • High float (> 44 days) ≤ 5%
  • Negative float = 0, or explained and being recovered

Durations & dates

  • High duration (> 44 days) ≤ 5%
  • No invalid dates (actuals in the future / forecasts in the past)
  • Resources assigned where the method requires

Progress & critical path

  • Missed tasks within tolerance
  • Critical-path test passes (a deliberate large delay moves the finish)
  • CPLI ≈ 1.0 or better
  • BEI ≈ 0.95 or better