Expertise

Project ControlsPlanning and Primavera P6Schedule AssuranceEOT ClaimsForensic Delay AnalysisProgramme ManagementPMO LeadershipDigital Project ControlsAll expertise

Framework

Project Controls Management System100-Point Schedule Assurance FrameworkHow I WorkOperating PrinciplesImplementation ChecklistsMaturity Model

Tools

Project Controls IntelligenceDecision Centre: start hereDirector’s 10-Minute ReviewForensic Delay LabProgramme DashboardProgramme SimulatorRisk and Early WarningExecutive Review GeneratorSchedule Assurance ChallengeProgramme Management toolsChecklists and templates

Academy

Learning pathwaysProfessional ReferencesPrimavera P6 GuidesThe SCL Protocol seriesGlossary

Insights

ArticlesCase StudiesProjectsDirector’s PlaybookRed Flags and Failure AtlasLessons from Major ProgrammesClaims and Delay articles

About

AboutExecutive ProfileDownload Executive CVLinkedIn
Search

Searches articles, case studies, guides and tools on this site. Runs in your browser — nothing is sent anywhere.

Project Controls Intelligence

Baseline Integrity

Is the programme technically credible?

What it is

The baseline is the accepted, logic-linked programme every measurement is made against. Baseline integrity is whether that programme is technically sound enough to trust before its dates carry any weight.

Why it matters

If the baseline is weak, everything downstream — progress, forecast, delay analysis, entitlement — inherits the weakness. You cannot measure delay against a programme that was never sound.

What to check

  • Is it formally accepted, not just issued?
  • Is it fully logic-linked, with no open ends or dangling activities?
  • Are hard constraints minimal and justified?
  • Are durations, calendars and resourcing realistic?
  • Does the critical path make engineering sense?

Common warning signs

  • Open ends and dangling logic
  • Hard constraints driving the completion date
  • A critical path running through improbable activities
  • Durations that don’t match the resource assumption
  • A baseline never formally accepted

Practical approach

Test the baseline against a defined standard — logic, constraints, float, durations, critical path — before it is accepted. The 100-point assurance engine automates exactly these checks so “good” is objective, not a monthly argument.