Module · Programme leadership
Programme Simulator
You are the project controls director on a 42-month, AED 5 billion infrastructure programme. Over twelve stages, from baseline approval to the Board, you choose how to respond. Each choice changes schedule, cost, risk, governance and delivery confidence, and some come back later.
Fictional scenario. Corala Bay Infrastructure Programme, its projects, contractors and figures are invented for teaching. They do not describe any real programme, client or contractor.
| Project | Scope | Budget (AED m) | Contractor |
|---|---|---|---|
| P1 | Roads and bridges | 1,800 | Contractor Alpha |
| P2 | Utilities and networks | 1,200 | Contractor Beta |
| P3 | Marine works | 1,100 | Contractor Gamma |
| P4 | Public realm and buildings | 900 | Contractor Delta |
| Programme | 5,000 | 42 months | |
- 01Baseline approval
- 02Schedule slippage
- 03Contractor underperformance
- 04Design delays
- 05Procurement constraints
- 06Interface failures
- 07Cost escalation
- 08Change control
- 09Emerging risks
- 10Extension of time submission
- 11Programme recovery
- 12Executive escalation
Module How this tool works: inputs, method and limitations
- Purpose
- Practise the judgement calls of programme controls leadership and see how they play out across schedule, cost, risk, governance and delivery confidence.
- Intended user
- Controls managers stepping up to director level, programme managers, and teams using it as a workshop exercise.
- Output
- A running dashboard, the outcome of each decision, a trajectory chart, strengths and weaknesses with the stronger response, a decision log and a printable assessment.
- How the result is produced
- Scenario model with author-set effects. Results depend on ratings or estimates you enter; they are not measured performance.
- PCMS discipline
- Programme and project governance · Volume 1: Governance
- Learn the method
- Project controls operating models (Leadership pathway)
- Inputs
- One of three responses at each of twelve stages, from baseline approval to Board escalation
- Method
- Each response applies stated effects to five measures; risk, governance and confidence are held between 0 and 100.
- Some earlier responses set conditions that change later effects, for example a weak baseline makes later slippage harder to see.
- Decision score: 2 for the strongest response, 1 for a mixed one, 0 for a weak one. Ratings on each measure use stated thresholds.
- Limitations
- Fictional scenario; effects are set by the author to illustrate typical consequences, not predicted from data.
- Real decisions have more options and more context than three choices can show.
- Suggested actions
- Run it as a team and discuss the choices where people disagreed.
- Compare the lessons with your own programme’s current decisions.
- How to read the result
- The result is indicative: a structured prompt for professional judgement, not a determination. Use it to decide what to check next, then confirm against the programme, the records and the contract.
- Related
- Expertise: Programme Management and Governance · Reference: Programme governance standards · Case study: 16 contracts under one standard · 100-Point Framework · Not sure where to start? Decision Centre
Runs in your browser; nothing is sent to a server. A practitioner’s aid, not a certification or a contractual determination. See how the measures combine in the Programme Intelligence Dashboard. All tools →