| Programme and project governance | Govern | V1 | Programme director | Employer objectives and delegated authorities; Contract structure and packaging; Approval thresholds | Decision and escalation map; Delegation of authority for controls decisions; Meeting and approval rhythm | Decisions taken within the agreed cycle; Escalations resolved at the right level | Every controls decision has a named owner and an evidence requirement; Escalation thresholds are written down and used | Setup Check |
| Planning and scheduling | Plan & measure | V2 | Planning lead | Scope and work breakdown; Construction method and sequence; Calendars, resources and constraints | Integrated master programme; Contractor and package programmes; Programme narratives | Logic completeness; Constraint usage; Critical path continuity | Open ends, hard constraints and long lags reviewed every update; Critical path traced from completion | Schedule Health Check |
| Baseline management and control | Plan & measure | V2 | Planning lead | Submitted programme and budget; Acceptance criteria; Approved change | Accepted baseline with recorded conditions; Baseline revision log; Re-baseline decisions | Baseline acceptance cycle time; Unexplained baseline changes | Acceptance separated from quality: the baseline is reviewed, not only approved; Every revision traceable to approved change | 5-Minute Baseline Check |
| Progress measurement and performance management | Plan & measure | V2 | Planning lead | Rules of credit and milestone weights; Site records and quantities; Inspection and test records | Measured progress by package; Planned versus actual curves; Verified progress statements | Gap between reported and verified progress; Share of progress supported by records | Sample-verify reported progress every cycle; Rules of credit applied consistently across contractors | Progress Measurement Assessment |
| Earned Value Management and Earned Schedule | Plan & measure | V3 | Controls manager | Budgeted baseline (planned value); Measured progress (earned value); Actual cost | CPI, SPI and SPI(t); Variances by package; Performance trends | CPI; SPI(t); Schedule variance in time | PV, EV and AC drawn from the same structure and cut-off; Indices broken down before they are acted on | Earned Value Calculator |
| Interface management | Plan & measure | V2 | Interface manager | Package boundaries; Access, approval and third-party dates; Design and procurement schedules | Interface register with dates and owners; Interface milestones in the master programme | Interfaces overdue; Interfaces without a programme date | Each interface has a giving and a receiving party and a date in both programmes | Interface Management Tracker |
| Productivity and performance measurement | Plan & measure | V2 | Planning lead | Quantities installed; Labour and plant deployed; Planned rates | Achieved rates by trade; Productivity trends; Evidence for recovery assumptions | Achieved versus planned output rate | Recovery assumptions compared with rates actually achieved | Recovery review pathway |
| Cost management, forecasting and EAC | Forecast & respond | V3 | Cost lead | Budget and commitments; Actual cost; Approved and pending change; Performance indices | Estimate at completion with its basis; Variance at completion; Cost forecast trend | EAC movement month to month; TCPI against CPI achieved | Forecast tested against formula estimates; Pending change and risk shown separately from the base forecast | Cost Forecast Calculator |
| Risk and opportunity management | Forecast & respond | V3 | Risk manager | Risk workshops and registers; Programme and cost structure; Emerging issues from reporting | Owned risk register with responses; Risk exposure in the forecast; Early-warning list | Responses overdue; Risks that became issues without warning | Each significant risk linked to the programme activities it affects; Responses tracked to completion | Risk and Early Warning |
| Change and configuration management | Forecast & respond | V1 | Controls manager | Change requests and instructions; Impact assessments; Approval decisions | Change register and pipeline; Approved baseline revisions; Configuration record | Change pipeline value and age; Approved versus pending change | Every approved change reflected in programme and budget; Pending change visible to decision-makers | Change Impact Assessment |
| Claims, delay analysis and EOT management | Forecast & respond | V2 | Delay and claims lead | Notices and delay events; Updated programmes; Contemporaneous records | Delay event register; Time impact assessments; Determinations and their basis | Delay events assessed within the cycle; Notices on time | Cause, effect and evidence established for each event; Method chosen to suit the records available | Forensic Delay Lab |
| Reporting, dashboards and decision intelligence | Forecast & respond | V3 | Controls manager | Verified performance data; Forecasts and exposure; Decisions pending | Weekly, monthly and board reports; Executive dashboard; Decision log | Reports on time; Decisions requested versus taken | Every report states the decision required; Data in reports reconciled to source | Executive Review Generator |
| Schedule and project controls assurance | Assure & improve | V7 | Assurance lead | Programme submissions; Assurance criteria; Previous findings | Assurance scores and findings; Corrective actions; Trend of quality over time | Assurance score trend; Findings closed on time | Same criteria applied to every contractor, every cycle | Schedule Health Check |
| Contractor performance monitoring and surveillance | Assure & improve | V6 | Package managers | Contractual reporting obligations; Submissions and their quality; Site surveillance | Contractor performance view; Surveillance findings; Escalation where needed | Submissions on time and accepted first time; Findings repeated across cycles | Findings evidenced and shared with the contractor before escalation | Contractor Performance Scorecard |
| Data governance, auditability and continuous improvement | Assure & improve | V5 | Data and BI lead | Source systems and owners; Reconciliation rules; Lessons learned | Data ownership map; Reconciliation and audit trail; Improvement actions | Reconciliation breaks; Improvement actions closed | Each reported figure traceable to its source system and cut-off; Baseline lineage recorded | Critical Path Stability Monitor |