Expertise

Project ControlsPlanning and Primavera P6Schedule AssuranceEOT ClaimsForensic Delay AnalysisProgramme ManagementPMO LeadershipDigital Project ControlsAll expertise

Framework

Project Controls Management System100-Point Schedule Assurance FrameworkHow I WorkOperating PrinciplesImplementation ChecklistsMaturity Model

Tools

Project Controls IntelligenceDecision Centre: start hereDirector’s 10-Minute ReviewForensic Delay LabProgramme DashboardProgramme SimulatorRisk and Early WarningExecutive Review GeneratorSchedule Assurance ChallengeProgramme Management toolsChecklists and templates

Academy

Learning pathwaysProfessional ReferencesPrimavera P6 GuidesThe SCL Protocol seriesGlossary

Insights

ArticlesCase StudiesProjectsDirector’s PlaybookRed Flags and Failure AtlasLessons from Major ProgrammesClaims and Delay articles

About

AboutExecutive ProfileDownload Executive CVLinkedIn
Search

Searches articles, case studies, guides and tools on this site. Runs in your browser — nothing is sent anywhere.

Schedule Assurance

How to Review a Primavera P6 Baseline

The baseline you accept is the one you'll be measured against — and the one every future delay claim is argued from. Here's how to review one before you sign it off.

By Rishi JaveriPublished 07-Jul-26Updated 12-Aug-267 min read

Accepting a baseline is one of the most consequential things a controls function does, and one of the most rushed. Get it wrong and every downstream number inherits the error.

Start with scope, not dates

Before touching logic, confirm the programme actually contains the full scope of works. Missing scope is the most common and most damaging defect — and the hardest to argue about later.

Test the logic

Every activity should have a predecessor and a successor. Relationships should be predominantly finish-to-start, with leads and lags justified. The real test: push a key activity out and see whether completion moves sensibly. If nothing moves, the logic isn’t doing its job.

Interrogate the critical path

The critical path should run through genuinely constraining work, and should be reconciled against the longest path. If it threads through trivial activities, constraints or logic are distorting it.

Constraints, durations, acceptance

Most hard constraints should not be there; each one needs justification. Durations should trace to a resourcing basis, not round numbers. And acceptance should be recorded as “a sound measure of record” with any qualifications noted — not as agreement on the dates themselves.

Rishi JaveriProject Controls & Programme Governance · FCIArb · FIE · PMP · PSP · MCIOB · MAPM