Schedule assessment frameworks: DCMA, GAO, PMI and the 100-point framework
01What it covers
Three published ways of judging a schedule. DCMA’s 14 metrics measure symptoms against thresholds. GAO’s ten best practices describe what a reliable schedule does, grouped into four characteristics: comprehensive, well constructed, credible and controlled. PMI’s practice standard assesses whether a schedule model has the components it should and uses them properly.
02Why it matters
They answer different questions. Treating a metric score as proof of a sound schedule, or using one framework for a job it was not designed for, is one of the most common assurance errors.
03Key principles
- DCMA’s metrics are diagnostic prompts: a result outside a threshold tells the reviewer where to look, not that the schedule fails.
- GAO’s practices cover the whole life of the schedule: capturing all work, logic, resources, durations, traceability, a valid critical path, reasonable float, schedule risk analysis, honest updating and a maintained baseline.
- PMI’s conformance approach checks completeness and correct use of schedule components rather than numerical thresholds.
- An employer’s acceptance standard, such as the 100-Point Employer Schedule Assurance Framework, is a separate decision rule: whether this submission is acceptable under this contract.
04Practical application
- Use DCMA metrics to triage a large update quickly and decide where to investigate.
- Use GAO’s practices to structure a full schedule review and to explain findings to executives.
- Use the employer’s acceptance standard to accept or reject a submission, and record the reasons against the contract requirements.
05Common mistakes
- Reporting “passed DCMA” as if it meant the schedule is reliable.
- Calling a bespoke employer framework a DCMA assessment, or the reverse.
- Checking structure only, and never testing whether the critical path and progress reflect the work on site.
06PCMS discipline
07Related tools
08Further reading
- The 100-Point Schedule Assurance Framework
- 15 warning signs of a poor schedule
- DCMA-EA PAM 200.1, EVMS Program Analysis Pamphlet, section 4: 14 Point Schedule Metrics (publisher)
- GAO Schedule Assessment Guide: Best Practices for Project Schedules (GAO-16-89G) (publisher)
- Practice Standard for Scheduling (publisher)
Written in my own words to explain principles; it does not reproduce the publication and implies no endorsement by DCMA, US GAO, PMI. Not legal advice.
Other references
- SCL Delay and Disruption Protocol (2nd Ed.): Reference Guide
- The GAO schedule and cost guides
- AACE forensic schedule analysis (RP 29R-03)
- AACE planning and scheduling practices
- Earned value management: EIA-748-E and ISO 21508
- Risk and change: ISO 31000 and AACE practices
- Programme governance: PMI, ISO 21503 and MSP