Expertise

Project ControlsPlanning and Primavera P6Schedule AssuranceEOT ClaimsForensic Delay AnalysisProgramme ManagementPMO LeadershipDigital Project ControlsAll expertise

Framework

Project Controls Management System100-Point Schedule Assurance FrameworkHow I WorkOperating PrinciplesImplementation ChecklistsMaturity Model

Tools

Project Controls IntelligenceDecision Centre: start hereDirector’s 10-Minute ReviewForensic Delay LabProgramme DashboardProgramme SimulatorRisk and Early WarningExecutive Review GeneratorSchedule Assurance ChallengeProgramme Management toolsChecklists and templates

Academy

Learning pathwaysProfessional ReferencesPrimavera P6 GuidesThe SCL Protocol seriesGlossary

Insights

ArticlesCase StudiesProjectsDirector’s PlaybookRed Flags and Failure AtlasLessons from Major ProgrammesClaims and Delay articles

About

AboutExecutive ProfileDownload Executive CVLinkedIn
Search

Searches articles, case studies, guides and tools on this site. Runs in your browser — nothing is sent anywhere.

DCMA, US GAO, PMI

Schedule assessment frameworks: DCMA, GAO, PMI and the 100-point framework

DCMA-EA PAM 200.1, EVMS Program Analysis Pamphlet, section 4: 14 Point Schedule MetricsOctober 2012 · Government guidance · Public releaseOfficial source →
GAO Schedule Assessment Guide: Best Practices for Project Schedules (GAO-16-89G)December 2015 · Government guidance · FreeOfficial source →
Practice Standard for Scheduling3rd edition, 2019 · Practice standard · Purchase; free to PMI membersOfficial source →
Edition checked 02-Nov-26.

01What it covers

Three published ways of judging a schedule. DCMA’s 14 metrics measure symptoms against thresholds. GAO’s ten best practices describe what a reliable schedule does, grouped into four characteristics: comprehensive, well constructed, credible and controlled. PMI’s practice standard assesses whether a schedule model has the components it should and uses them properly.

02Why it matters

They answer different questions. Treating a metric score as proof of a sound schedule, or using one framework for a job it was not designed for, is one of the most common assurance errors.

03Key principles

  • DCMA’s metrics are diagnostic prompts: a result outside a threshold tells the reviewer where to look, not that the schedule fails.
  • GAO’s practices cover the whole life of the schedule: capturing all work, logic, resources, durations, traceability, a valid critical path, reasonable float, schedule risk analysis, honest updating and a maintained baseline.
  • PMI’s conformance approach checks completeness and correct use of schedule components rather than numerical thresholds.
  • An employer’s acceptance standard, such as the 100-Point Employer Schedule Assurance Framework, is a separate decision rule: whether this submission is acceptable under this contract.

04Practical application

  • Use DCMA metrics to triage a large update quickly and decide where to investigate.
  • Use GAO’s practices to structure a full schedule review and to explain findings to executives.
  • Use the employer’s acceptance standard to accept or reject a submission, and record the reasons against the contract requirements.

05Common mistakes

  • Reporting “passed DCMA” as if it meant the schedule is reliable.
  • Calling a bespoke employer framework a DCMA assessment, or the reverse.
  • Checking structure only, and never testing whether the critical path and progress reflect the work on site.
Guidance, contract and law. DCMA, GAO and PMI publish general guidance. The 100-Point Employer Schedule Assurance Framework is Rishi Javeri’s own employer-side method; its 100 checks are published as a checklist, its scoring rules are not, and it is not a DCMA assessment.

06PCMS discipline

07Related tools

08Further reading

Written in my own words to explain principles; it does not reproduce the publication and implies no endorsement by DCMA, US GAO, PMI. Not legal advice.