Expertise

Project ControlsPlanning and Primavera P6Schedule AssuranceEOT ClaimsForensic Delay AnalysisProgramme ManagementPMO LeadershipDigital Project ControlsAll expertise

Framework

Project Controls Management System100-Point Schedule Assurance FrameworkHow I WorkOperating PrinciplesImplementation ChecklistsMaturity Model

Tools

Project Controls IntelligenceDecision Centre: start hereDirector’s 10-Minute ReviewForensic Delay LabProgramme DashboardProgramme SimulatorRisk and Early WarningExecutive Review GeneratorSchedule Assurance ChallengeProgramme Management toolsChecklists and templates

Academy

Learning pathwaysProfessional ReferencesPrimavera P6 GuidesThe SCL Protocol seriesGlossary

Insights

ArticlesCase StudiesProjectsDirector’s PlaybookRed Flags and Failure AtlasLessons from Major ProgrammesClaims and Delay articles

About

AboutExecutive ProfileDownload Executive CVLinkedIn
Search

Searches articles, case studies, guides and tools on this site. Runs in your browser — nothing is sent anywhere.

Schedule Assurance

15 Warning Signs of a Poor Construction Schedule

A programme is a claim about the future, and like any claim it can be sound or hollow. Most poor schedules fail in the same recognisable ways.

By Rishi JaveriPublished 28-Jul-26Updated 12-Aug-268 min read

No single sign is fatal — every real programme has a few. The danger is the pattern.

Broken logic (1–4)

Open ends that break the network; dangling logic linked only at one end; excessive leads that force false overlaps; and logic that doesn’t respond when you move a key activity.

Float & constraints (5–8)

Constraint abuse that overrides logic; unexplained negative float; implausibly high float masking missing links; and a critical path running through the wrong work.

Durations & dates (9–11)

Round-number durations estimated by feel; marathon activities that hide risk; and invalid dates that mean the schedule isn’t being updated with discipline.

Progress & behaviour (12–15)

Progress that only ever moves forward; a completion date that never moves despite accumulating delay; a recovery programme with no method; and — most telling — a team that cannot explain its own critical path.

What to do about it

The remedy is a standard, not suspicion: turn each sign into a measurable test with the schedule health checklist, and automate it, so quality becomes a baseline everyone works to rather than a monthly argument.