Baseline Programme Review Checklist
Verify a contractor's baseline programme is technically sound before you accept it — because the baseline you accept is the one you'll be measured against.
Employer / PMC project controls, planners and PMs reviewing a submitted baseline.
On first baseline submission, and on any re-baseline or major revision.
- Baseline Integrity (29 checks)
- Logic & Network Integrity (18)
- Progress Integrity (6)
- Forecast Integrity (10)
- Critical Path & Float (9)
- Governance & Reporting (28)
These are the 100 checks of the 100-Point Employer Schedule Assurance Framework, for reviewing a contractor’s baseline programme before you accept it, because the baseline you accept is the one you will be measured against. They are grouped into 16 areas, and each area sits under one of the framework’s six assurance dimensions. The DCMA 14-point checks sit within the framework as a recognised schedule-quality reference; the PDF maps each check to the related DCMA metric where one applies. The scoring rules that turn findings into the Schedule Assurance Score are not published.
A “No” is a question to resolve before accepting the baseline. Tick items on screen as you go, or download the PDF for Yes / No / N/A columns and space for findings. Adapt duration limits and thresholds to your contract.
1. Schedule Submission & Contract Dates
Baseline Integrity · 7 checks
- 1.1 Baseline submitted within the period stipulated in the Contract (e.g. 28 calendar days from Commencement / NTP) for the Engineer's consent.
- 1.2 Data Date of the Baseline equals the Notice to Proceed (NTP) date.
- 1.3 Baseline early start = NTP date; late finish is equal to or before the Contractual Completion Date stipulated in the Contract.
- 1.4 Full contract scope is represented, including provisional sums / prime-cost items.
- 1.5 Schedule contains no activities for work outside the original contract scope.
- 1.6 All contractual / key completion and interim (sectional) milestones are shown as zero-duration milestone activities; major phase/stage transitions carry milestones.
- 1.7 Milestone dates (start / interim / finish) align with the Contract; control milestones agreed with the Employer.
2. WBS & Coding
Governance & Reporting · 8 checks
- 2.1 WBS covers the entire scope of works, aligned to a WBS dictionary; each element detailed sufficiently for accurate monitoring & control.
- 2.2 WBS titles logical and representative; top-level WBS conforms to contract type (D&B or Traditional); sub-WBS levels submitted for agreement prior to official submission.
- 2.3 WBS supports the required execution / phasing / staging strategy.
- 2.4 Long-lead items categorised separately under each relevant procurement / utility WBS.
- 2.5 Activity IDs are logical and representative of activity type, location and stage.
- 2.6 Activity descriptions accurately summarise scope and location; similar tasks in different areas are distinctly worded and identifiable.
- 2.7 Each activity reflects a single trade (no combined multi-trade activities, e.g. 'formwork, rebar & concrete').
- 2.8 Activity code structure sufficient to sort/filter (type, location, responsible crew, phase, BOQ, system, etc.); no blank activity codes.
3. Project Calendars
Logic & Network Integrity · 5 checks
- 3.1 Calendars reflect applicable public holidays, religious observances and seasonal reduced hours and rest days for the jurisdiction.
- 3.2 A multi-year calendar is adopted; working-week definition (days, hours, shift start/finish) stated and consistent with the narrative.
- 3.3 A 5-day x 8-hour calendar (incl. public-sector holidays) created and assigned to Authority / Employer review & approval activities.
- 3.4 A 7-day calendar created and assigned to (overseas) material-shipment activities.
- 3.5 All calendars created as project calendars (not global); every activity on the correct calendar; assignments will not create float discrepancies in future updates.
4. Activity Durations
Baseline Integrity · 4 checks
- 4.1 Durations based on realistic productivity rates, quantities and resources — not reverse-engineered to force a target/contractual completion date; no odd/arbitrary durations.
- 4.2 Construction activity original duration below the programme limit (e.g. < 21 calendar days, or < 10 days per the guidelines) unless justified.
- 4.3 Only long-lead fabrication / delivery activities exceed the standard duration limit; justification provided.
- 4.4 Durations allowed for Authority approvals are reasonable and consistent with comparable projects.
5. Logic, Relationships, Lags & Open Ends
Logic & Network Integrity · 7 checks
- 5.1 No open ends: every activity has at least one predecessor and one successor. Only open start = Award/NTP start milestone; only open finish = Completion (CCD) finish milestone.
- 5.2 No negative lags / leads (lead time) anywhere in the schedule.
- 5.3 Lags minimised and justified; no FS+lag on the critical / near-critical path; positive lags limited to genuine cases (curing, formwork strike, scaffold up/down).
- 5.4 At least ~90% of relationships are Finish-to-Start; SS relationships paired with FF to avoid dangling logic; no Start-to-Finish (SF) relationships.
- 5.5 No redundant / duplicate relationships.
- 5.6 Retained-logic scheduling option to be used in updates (progress override not permitted).
- 5.7 Construction sequence follows the approved construction methodology.
6. Constraints & Float
Critical Path & Float · 4 checks
- 6.1 Constraints minimised, used only to control sectional/contract milestones where required; hard constraints (Mandatory, Start-On, Finish-On) avoided; where unavoidable, applied only to the first (start) or last (finish) activity on the path.
- 6.2 No negative float in the Baseline.
- 6.3 No unrealistically high total/free float; excessive float (e.g. > 44 working days) justified by the Contractor or corrected with proper logic.
- 6.4 Submittal / procurement activities carry adequate float to absorb possible resubmission iterations.
7. Critical Path
Critical Path & Float · 5 checks
- 7.1 Critical activity defined as total float = 0; number of critical / near-critical activities reasonable for the scope; all driving sequences presented and substantiated.
- 7.2 Critical path runs continuously from project start to completion, driven by mandatory (hard) logic — not by constraints, lags or discretionary/preferential logic.
- 7.3 Critical path does not run unjustifiably through Employer / Client-controlled activities.
- 7.4 Multiple float paths reviewed; most-critical and near-critical path identified for each interim milestone.
- 7.5 Critical-path integrity test — a deliberate large lag on a critical activity pushes project completion, confirming a sound driving path.
8. Procurement, Engineering & Preconstruction
Baseline Integrity · 7 checks
- 8.1 Design, engineering, procurement, submittal and NOC activities detailed and realistically estimated.
- 8.2 Subcontractor selection / prequalification activities included.
- 8.3 Each submittal split into two activities (1. prepare/submit, 2. review/approve); submittal priority/order reflected where a sequence is required.
- 8.4 Shop-drawing & method-statement approvals precede the related construction; material-submittal approval precedes the fabrication activity.
- 8.5 Long-lead & free-issue items clearly identified; delivery linked to installation (SS/FF with logical lags, or first-on-site lot segregated) rather than a blanket FS.
- 8.6 Contractor design development (D&B) shown in sufficient, phased detail for the Employer to gauge design status.
- 8.7 Comprehensive procurement / shop-drawing / material-submittal logs (planned, forecast, actual dates) provided; drawing register resource-loaded per the Particular Conditions.
9. Resource & Cost Loading / Progress Measurement
Progress Integrity · 6 checks
- 9.1 Activities realistically loaded with manpower, material and equipment resources.
- 9.2 Fully cost-loaded; values reconcilable to BOQ bill numbers.
- 9.3 Progress measurement based on agreed weightages; weight-factor and cost-allocation calculations provided.
- 9.4 Earning rules aligned with monthly payment claims (payment on verified site progress, not update percentages).
- 9.5 Resource / cost histograms and S-curves reasonable; peaks achievable and checked against production rates.
- 9.6 Major-commodity KPI calculations provided.
10. Schedule Integrity & Software Settings
Logic & Network Integrity · 6 checks
- 10.1 Scheduling log report (e.g. P6 log) run and reviewed; schedule recalculated prior to submission.
- 10.2 No zero-duration activities other than milestones; no activities in progress in the Baseline.
- 10.3 Duration type set appropriately (e.g. Fixed Duration & Units); % Complete type set to Physical; Activity type correct (Task Dependent for work, Start/Finish milestones).
- 10.4 All resources / codes / calendars are project-specific, not global; POBS removed; correct software version exported.
- 10.5 Spell-check performed on all activity descriptions.
- 10.6 Invalid-dates check — no forecast / remaining work before the Data Date and no actual dates after it (date integrity).
11. UAE Authority Approvals & NOCs
Baseline Integrity · 6 checks
- 11.1 All applicable authority-approval and NOC activities included with realistic durations — e.g. Municipality (ADM / DM), Civil Defence, utility authorities, roads & transport, telecom, environment, aviation-height and master-developer NOCs relevant to the project location.
- 11.2 Building / construction permit and affection-plan / site-possession activities shown as predecessors to site works.
- 11.3 Utility connection applications (power, water, drainage, irrigation, district cooling, telecom) raised early, reflecting each authority's own application-to-energization lead time.
- 11.4 Third-party service diversions and existing-utility clearance (NOC to excavate / permit-to-dig) and utility surveys included before excavation.
- 11.5 Environmental permits (e.g. CEMP / environment-agency approval) and any marine, coastal or dredging permits included where applicable, with seasonal restrictions.
- 11.6 Sustainability-certification activities included where mandated — Estidama Pearl Rating (Abu Dhabi), Al Sa'fat / Green Building (Dubai) or equivalent — across design, construction and final rating.
12. Programme Narrative & Supporting Documents
Governance & Reporting · 11 checks
- 12.1 Narrative describes construction methodology, logistics and manpower / equipment allocation & availability.
- 12.2 Assumed working hours and calendars stated.
- 12.3 Shop-drawing, procurement and long-lead schedules included (local vs overseas identified).
- 12.4 Programme risk register with possible mitigating measures included.
- 12.5 Budgeted-cost curve (renamed from 'Earned Value' pre-progress) and the weightage-based progress S-curve included; both carried into weekly / monthly updates.
- 12.6 Sequence of work precise and quantified (durations / dates); vague terms ('approximately', 'later on', 'almost') avoided.
- 12.7 Crew sizes and trades specified numerically; crew-movement plan provided (preferably graphical, monthly, on project layouts).
- 12.8 Critical path for each contractual milestone explained in the narrative with a programme extract per path.
- 12.9 Scope matrix (Excel) reflecting detailed phased scope and quantities provided.
- 12.10 Programme layout columns include Activity ID, Name, Original Duration, Quantities (major activities), Unit, Early/Late Start & Finish, Total Float, Budgeted Cost.
- 12.11 Review/workflow durations in the document-management system considered for all submittals; variation / instruction workflow durations reflected per the Contract.
13. Utilities Energization & Handover Authorities
Baseline Integrity · 5 checks
- 13.1 Permanent-power energization treated as a long-lead critical item; substation / transformer / metering and authority energization sequenced early, not at the very end.
- 13.2 Civil Defence final inspection and fire-safety NOC shown as predecessors to occupancy / Taking-Over.
- 13.3 Lift / escalator authority inspection and registration included before handover.
- 13.4 Building Completion Certificate (BCC) / municipality completion and permanent utility connections sequenced ahead of the Completion milestone.
- 13.5 Snagging, de-snagging, Testing & Commissioning, integrated systems testing and demonstration periods realistically durated and linked to handover.
14. UAE Calendars, Weather & Productivity
Forecast Integrity · 5 checks
- 14.1 Statutory summer midday-break period (mid-June to mid-September work-hour restriction) reflected in the relevant calendar / productivity for outdoor works.
- 14.2 Hot-weather and high-humidity productivity impacts in summer months reflected in durations, rather than uniform year-round rates.
- 14.3 Allowance for sandstorm / fog / rain non-working days based on historical regional weather data.
- 14.4 Ramadan reduced working hours applied to affected calendars and, where relevant, to productivity — not treated only as holidays.
- 14.5 Hot-weather concreting controls (temperature limits, night pours, ice/chilled water) reflected in concrete sequencing / durations where relevant.
15. Logistics, Marine & Ground Conditions
Forecast Integrity · 5 checks
- 15.1 Overseas material import lead times include shipping plus UAE customs clearance and port handling, not shipping alone.
- 15.2 Abnormal / heavy-load transport, road-closure and crane / heavy-lift permits (roads authority / municipality / police escort) included where required.
- 15.3 Enabling / early works, demolition, UXO or archaeological clearance (where applicable) and site clearance shown before main works.
- 15.4 Ground improvement, dewatering, piling permits and vibration-monitoring constraints reflected; ground-improvement settlement / surcharge waiting periods justified as long-duration activities.
- 15.5 Marine works (reclamation, dredging, quay / marine structures) reflect tidal windows, vessel mobilization and environmental seasonal windows where applicable.
16. Schedule Health & Controls Good Practice
Governance & Reporting · 9 checks
- 16.1 Terminal float / time contingency between planned completion and the Contractual Completion Date is transparent; float ownership stated (Contractor early-completion vs shared float).
- 16.2 Activity density is balanced — enough detail for control without excessive fragmentation; a 2-week / 90-day look-ahead is derivable from the baseline.
- 16.3 Level-of-Effort / hammock / summary activities (if used) are identified and do not drive or distort the critical path.
- 16.4 Baseline formally saved / versioned in the tool (baseline assigned) to enable variance reporting in updates.
- 16.5 Milestone and activity naming follow a consistent convention; interim milestones traceable to contract sectional completions.
- 16.6 Interface milestones with the Employer, other contractors, enabling-works and free-issue / novated design are captured and dated.
- 16.7 Mobilization, insurances (CAR / WC), performance security and advance-payment-guarantee activities precede the works they gate.
- 16.8 Weather and risk contingency are declared as such, not hidden inside inflated durations or lags.
- 16.9 A schedule health / quality run (e.g. DCMA 14-point) is performed and documented as part of the submission.