Expertise

Project ControlsPlanning and Primavera P6Schedule AssuranceEOT ClaimsForensic Delay AnalysisProgramme ManagementPMO LeadershipDigital Project ControlsAll expertise

Framework

Project Controls Management System100-Point Schedule Assurance FrameworkHow I WorkOperating PrinciplesImplementation ChecklistsMaturity Model

Tools

Project Controls IntelligenceDecision Centre: start hereDirector’s 10-Minute ReviewForensic Delay LabProgramme DashboardProgramme SimulatorRisk and Early WarningExecutive Review GeneratorSchedule Assurance ChallengeProgramme Management toolsChecklists and templates

Academy

Learning pathwaysProfessional ReferencesPrimavera P6 GuidesThe SCL Protocol seriesGlossary

Insights

ArticlesCase StudiesProjectsDirector’s PlaybookRed Flags and Failure AtlasLessons from Major ProgrammesClaims and Delay articles

About

AboutExecutive ProfileDownload Executive CVLinkedIn
Search

Searches articles, case studies, guides and tools on this site. Runs in your browser — nothing is sent anywhere.

Model

Project Controls Maturity Model

A practical model for assessing where a programme’s controls capability actually sits — and what changes to move it up a level.

Five levels, from reporting the past to informing the decision in front of leadership. It is a practitioner’s model — a way to have an honest conversation about capability — not an externally certified industry standard.

05

Decision Intelligence

Executive decision support.

Typical capability

Controls output drives the decision leadership must make.

Typical weakness

A demanding standard to sustain, cycle after cycle.

Sustained by

The top of the model — held by consistent discipline.

04

Predictive

Early warning.

Typical capability

Emerging exposure is seen before it hits completion.

Typical weakness

Insight may still not reach or change executive decisions.

Enables progression

Framing exposure and options around the decision itself.

03

Integrated

Connected controls.

Typical capability

Time, risk, change and reporting are read together.

Typical weakness

Still explains the present more than the emerging future.

Enables progression

Trend analysis, early warning and forecast confidence.

02

Controlled

Structured baseline & reporting.

Typical capability

The programme is measured reliably every cycle.

Typical weakness

Dimensions aren’t joined up; risk and change sit apart.

Enables progression

Integrating time, risk, change and governance.

01

Reactive

Historical reporting.

Typical capability

Status is assembled after the fact.

Typical weakness

No forward visibility; decisions lag events.

Enables progression

An accepted baseline and structured progress measurement.

Reactive → Controlled → Integrated → Predictive → Decision Intelligence

Using the model

Most programmes are more than one level at once.

A programme can have a strong baseline (Controlled) while its risk and change sit in a spreadsheet nobody reads (still Reactive on that dimension). The point of the model is not a single score — it is to see where the gaps are, and to move the weakest dimension up. Each level is built on Integrity-Led Project Controls: you cannot be Predictive on a baseline you cannot trust.

Maturity Centre · self-assessment

Where is your project controls capability today?

Rate each of twelve areas on the five-level scale. The anchors describe levels 1, 3 and 5; choose 2 or 4 where you sit between them, or leave an area unrated if you do not know. You get a profile by area, the gaps, the priorities, recommended actions and a 12-month improvement outline you can print.

Self-assessed and indicative. Not independently verified, not an industry benchmark and not a certification.

01Governance
1 · Reactive
Decisions are made ad hoc; authority and escalation are unclear.
3 · Integrated
Decision rights, thresholds and escalation are defined and used across the programme.
5 · Decision Intelligence
Governance acts on controls evidence routinely; decisions are logged with their basis.
02Planning and scheduling
1 · Reactive
Programmes are produced for submission and rarely used to manage.
3 · Integrated
Programmes follow one standard, with sound logic, and are integrated into a master view.
5 · Decision Intelligence
The programme is the trusted model for decisions and scenarios at every level.
03Cost management
1 · Reactive
Cost is tracked as spend against budget after the event.
3 · Integrated
Budgets, commitments, actuals and forecasts are reconciled each period.
5 · Decision Intelligence
Outturn forecasts are evidence-based, risk-adjusted and trusted by the board.
04Progress measurement
1 · Reactive
Progress is reported as estimated percentages with little evidence.
3 · Integrated
Agreed rules of credit are applied and reported progress is sample-verified.
5 · Decision Intelligence
Progress, earned value and productivity are measured consistently and drive forecasts.
05Risk management
1 · Reactive
A register exists but is not linked to time or cost.
3 · Integrated
Owned risks have responses and are linked to the programme and forecast.
5 · Decision Intelligence
Risk exposure shapes forecasts and decisions before issues arise.
06Change control
1 · Reactive
Change is recorded late and the baseline drifts.
3 · Integrated
All change passes through one process and is reflected in programme and budget.
5 · Decision Intelligence
The change pipeline is visible and decided on in time to protect the forecast.
07Commercial integration
1 · Reactive
Commercial and schedule teams report separately and disagree.
3 · Integrated
Time, cost and change values are reconciled across teams each period.
5 · Decision Intelligence
One integrated view of time, cost and entitlement supports every commercial decision.
08Reporting
1 · Reactive
Reports describe status; decisions are not requested.
3 · Integrated
A fixed reporting rhythm with consistent measures, trends and exposure.
5 · Decision Intelligence
Every report states the decision required, with evidence and options.
09Digital systems
1 · Reactive
Data is re-keyed between spreadsheets; sources disagree.
3 · Integrated
Each data type has a source system and owner; reports draw from reconciled data.
5 · Decision Intelligence
Automated checks and analysis run on governed data with a full audit trail.
10Assurance
1 · Reactive
Submissions are accepted without systematic checking.
3 · Integrated
Programmes and data are checked against the same criteria every cycle.
5 · Decision Intelligence
Assurance trends drive corrective action and contractor improvement.
11Contractor management
1 · Reactive
Contractor reporting varies by contract and is rarely challenged.
3 · Integrated
One reporting standard applies to all contractors, with consistent review.
5 · Decision Intelligence
Contractor performance is measured fairly and improves through feedback.
12Leadership and capability
1 · Reactive
Controls is seen as reporting support; skills vary widely.
3 · Integrated
Defined roles, competence expectations and a controls lead with access to leadership.
5 · Decision Intelligence
Controls leadership shapes programme decisions and develops its people.
Self-assessment How this tool works: inputs, method and limitations
Purpose
Show where controls capability is strongest and weakest, which areas to improve first, and in what order.
Intended user
Controls leads, programme directors and PMO heads planning improvement.
Output
Overall indicative level, a profile by area, key gaps, priority areas with recommended actions, a 12-month outline and a printable summary.
How the result is produced
Self-assessment, not externally verified. Results depend on ratings or estimates you enter; they are not measured performance.
PCMS discipline
Schedule and project controls assurance · Volume 7: Audit and Compliance
Learn the method
15 warning signs of a poor schedule (Advanced pathway)
Inputs
  • A level from 1 (Reactive) to 5 (Decision Intelligence) for each of twelve areas, using the written anchors for levels 1, 3 and 5
  • Areas can be left unrated; at least six are needed
Method
  • Average of the rated areas, rounded down, held to no more than one level above the weakest area.
  • Gaps: areas at least one level below the average. Priorities: the three lowest areas, with foundational areas (governance, planning, progress measurement) first on ties.
  • Outline: the two top priorities in the first three months, remaining priorities and gaps next, then areas at the overall level.
Limitations
  • Self-assessed and indicative; not independently verified, not an industry benchmark and not a certification.
  • Different people rate differently: use the same group each time for a fair trend.
Suggested actions
  • Plan improvement around the weakest foundational area first.
  • Repeat the assessment each quarter with the same people.
How to read the result
The result is indicative: a structured prompt for professional judgement, not a determination. Use it to decide what to check next, then confirm against the programme, the records and the contract.