Expertise

Project ControlsPlanning and Primavera P6Schedule AssuranceEOT ClaimsForensic Delay AnalysisProgramme ManagementPMO LeadershipDigital Project ControlsAll expertise

Framework

Project Controls Management System100-Point Schedule Assurance FrameworkHow I WorkOperating PrinciplesImplementation ChecklistsMaturity Model

Tools

Project Controls IntelligenceDecision Centre: start hereDirector’s 10-Minute ReviewForensic Delay LabProgramme DashboardProgramme SimulatorRisk and Early WarningExecutive Review GeneratorSchedule Assurance ChallengeProgramme Management toolsChecklists and templates

Academy

Learning pathwaysProfessional ReferencesPrimavera P6 GuidesThe SCL Protocol seriesGlossary

Insights

ArticlesCase StudiesProjectsDirector’s PlaybookRed Flags and Failure AtlasLessons from Major ProgrammesClaims and Delay articles

About

AboutExecutive ProfileDownload Executive CVLinkedIn
Search

Searches articles, case studies, guides and tools on this site. Runs in your browser — nothing is sent anywhere.

Module · Schedule assurance

Schedule Assurance Challenge

Below is update 6 of a fictional contract schedule: an interchange with civil works and traffic systems. Thirteen defects have been seeded into it. Review it as an employer-side assurance team would, mark each activity you think is defective, then check your review.

Data date: day 120. Contract completion: day 400. Forecast completion in this update: day 430. Total float is measured against the contract date. Days are treated as working days. Fictional; not based on any real project, and nothing is sent or stored.

What to look for
  • Logic: every activity needs a predecessor and a successor, except the start and the finish.
  • Relationships: leads, long lags and relationship types that do not match how the work is really done.
  • Constraints, durations and float that hide or distort the critical path.
  • Progress: actual dates in the future, and work started out of sequence.
  • The baseline, resources, and what is actually driving completion.
IDActivityDur.PredecessorsConstraintBaselineActualForecastFloatRes.Your finding
S00 Notice to proceed 0 — — 0–0 0–0 complete — N
P01 Project management and supervision (level of effort) 430rem. 310 S00 FS — 0–400 0–… 0–430 -30 Y
A10 Mobilisation 20 S00 FS — 0–20 0–22 complete — Y
A20 Enabling works and site clearance 25 A10 FS — 20–45 22–50 complete — Y
C05 Traffic management plan approval 30 S00 FS — 0–30 5–126 complete — Y
A30 Utility diversions 40rem. 30 A20 FS, C05 FS — 45–85 50–… 50–150 -42 Y
A40 Piling 40rem. 30 A30 FS — 85–125 110–… 110–150 -12 Y
A50 Pile caps and piers 44 A40 FS Mandatory finish, day 230 125–169 — 150–194 -12 Y
A55 Deck concrete 44 A50 FS — 169–213 — 194–238 -12 Y
A60 Deck waterproofing 15 A55 SS — 213–228 — 194–209 17 Y
A70 Road surfacing 30 A60 FS, A55 FS — 228–258 — 238–268 -12 Y
A80 Road markings and signs 10 A70 FS -5 — 253–263 — 263–273 127 Y
B10 Traffic systems design approval 30 S00 FS — 0–30 0–34 complete — Y
B20 Procure traffic signals and ITS equipment 90rem. 60 B10 FS — 30–120 40–… 40–180 76 Y
B30 Install signals and ITS 40 B20 FS, A70 FS — 258–298 — 268–308 -12 N
B40 Testing and commissioning 44 B30 FS +30 — 328–372 — 338–382 -12 Y
D10 Street lighting installation 20 — — 263–283 — 120–140 260 Y
L10 Landscaping 25 A20 FS — 300–325 — 120–145 255 Y
C10 Handover documentation 30 B40 FS — none — 382–412 -12 Y
Z99 Completion 0 A80 FS, C10 FS, D10 FS, P01 FS — 400–400 — 430–430 -30 N
Module How this tool works: inputs, method and limitations
Purpose
Practise reviewing a schedule update the way an employer-side assurance team would, and learn why passing a metric is not the same as having a sound schedule.
Intended user
Planners, schedulers, PMC reviewers and project controls managers.
Output
Your score, an explanation of every seeded defect, the DCMA metrics for the network and the three views side by side.
How the result is produced
Calculated (critical path method) on a fictional schedule with seeded defects.
PCMS discipline
Schedule and project controls assurance · Volume 7: Audit and Compliance
Learn the method
15 warning signs of a poor schedule (Advanced pathway)
Inputs
  • Your review: for each activity, the defect category you believe applies, or none
Method
  • Forward and backward pass on the fictional network at the data date, with total float measured against the contract completion date.
  • DCMA 14-point metrics computed as published in DCMA-EA PAM 200.1 (2012), used as prompts for investigation, not pass or fail.
  • Your review scored against the seeded answer key: right activity and category 1 point, right activity with the wrong category 0.5, a flag on a sound activity −0.25.
  • Each defect mapped to the dimension and checklist check of the 100-Point Employer Schedule Assurance Framework under which it falls; the 100 checks are published, but its scoring rules are not, and they are not applied here.
Limitations
  • A teaching network of 20 activities; real schedules have thousands and need software.
  • Days are treated as working days; calendars are not modelled.
  • Hard constraints are recorded and counted but not applied to the dates.
  • Not an assessment of any real schedule, and not the 100-point framework itself.
Suggested actions
  • Review logic and progress before reading any metric.
  • Investigate every metric that flags; do not treat a pass as proof.
  • Keep the employer’s acceptance standard separate from DCMA’s diagnostic metrics.
How to read the result
The result is indicative: a structured prompt for professional judgement, not a determination. Use it to decide what to check next, then confirm against the programme, the records and the contract.
Related
Expertise: Schedule Assurance · Reference: Schedule assessment frameworks · Case study: Schedule quality 25% to 83% · 100-Point Framework · Not sure where to start? Decision Centre

Runs in your browser; nothing is sent to a server. A practitioner’s aid, not a certification or a contractual determination. See how the measures combine in the Programme Intelligence Dashboard. All tools →