Module · Schedule assurance
Schedule Assurance Challenge
Below is update 6 of a fictional contract schedule: an interchange with civil works and traffic systems. Thirteen defects have been seeded into it. Review it as an employer-side assurance team would, mark each activity you think is defective, then check your review.
Data date: day 120. Contract completion: day 400. Forecast completion in this update: day 430. Total float is measured against the contract date. Days are treated as working days. Fictional; not based on any real project, and nothing is sent or stored.
What to look for
- Logic: every activity needs a predecessor and a successor, except the start and the finish.
- Relationships: leads, long lags and relationship types that do not match how the work is really done.
- Constraints, durations and float that hide or distort the critical path.
- Progress: actual dates in the future, and work started out of sequence.
- The baseline, resources, and what is actually driving completion.
Module How this tool works: inputs, method and limitations
- Purpose
- Practise reviewing a schedule update the way an employer-side assurance team would, and learn why passing a metric is not the same as having a sound schedule.
- Intended user
- Planners, schedulers, PMC reviewers and project controls managers.
- Output
- Your score, an explanation of every seeded defect, the DCMA metrics for the network and the three views side by side.
- How the result is produced
- Calculated (critical path method) on a fictional schedule with seeded defects.
- PCMS discipline
- Schedule and project controls assurance · Volume 7: Audit and Compliance
- Learn the method
- 15 warning signs of a poor schedule (Advanced pathway)
- Inputs
- Your review: for each activity, the defect category you believe applies, or none
- Method
- Forward and backward pass on the fictional network at the data date, with total float measured against the contract completion date.
- DCMA 14-point metrics computed as published in DCMA-EA PAM 200.1 (2012), used as prompts for investigation, not pass or fail.
- Your review scored against the seeded answer key: right activity and category 1 point, right activity with the wrong category 0.5, a flag on a sound activity −0.25.
- Each defect mapped to the dimension and checklist check of the 100-Point Employer Schedule Assurance Framework under which it falls; the 100 checks are published, but its scoring rules are not, and they are not applied here.
- Limitations
- A teaching network of 20 activities; real schedules have thousands and need software.
- Days are treated as working days; calendars are not modelled.
- Hard constraints are recorded and counted but not applied to the dates.
- Not an assessment of any real schedule, and not the 100-point framework itself.
- Suggested actions
- Review logic and progress before reading any metric.
- Investigate every metric that flags; do not treat a pass as proof.
- Keep the employer’s acceptance standard separate from DCMA’s diagnostic metrics.
- How to read the result
- The result is indicative: a structured prompt for professional judgement, not a determination. Use it to decide what to check next, then confirm against the programme, the records and the contract.
- Related
- Expertise: Schedule Assurance · Reference: Schedule assessment frameworks · Case study: Schedule quality 25% to 83% · 100-Point Framework · Not sure where to start? Decision Centre
Runs in your browser; nothing is sent to a server. A practitioner’s aid, not a certification or a contractual determination. See how the measures combine in the Programme Intelligence Dashboard. All tools →