Expertise

Project ControlsPlanning and Primavera P6Schedule AssuranceEOT ClaimsForensic Delay AnalysisProgramme ManagementPMO LeadershipDigital Project ControlsAll expertise

Framework

Project Controls Management System100-Point Schedule Assurance FrameworkHow I WorkOperating PrinciplesImplementation ChecklistsMaturity Model

Tools

Project Controls IntelligenceDecision Centre: start hereDirector’s 10-Minute ReviewForensic Delay LabProgramme DashboardProgramme SimulatorRisk and Early WarningExecutive Review GeneratorSchedule Assurance ChallengeProgramme Management toolsChecklists and templates

Academy

Learning pathwaysProfessional ReferencesPrimavera P6 GuidesThe SCL Protocol seriesGlossary

Insights

ArticlesCase StudiesProjectsDirector’s PlaybookRed Flags and Failure AtlasLessons from Major ProgrammesClaims and Delay articles

About

AboutExecutive ProfileDownload Executive CVLinkedIn
Search

Searches articles, case studies, guides and tools on this site. Runs in your browser — nothing is sent anywhere.

Lessons

Lessons from major programmes.

What the work taught, distilled. Each programme below is described only at the level appropriate for public professional discussion — the point is the transferable controls lesson, kept distinct from the project facts and free of any confidential detail.

Modon Properties · AED 28.1B · Abu Dhabi

Hudayriyat West Island Development

Employer-side project controls, programme governance and performance assurance across concurrent construction packages on a major mixed-use development.

Transferable lessons
  • At programme scale the challenge stops being any single schedule and becomes reconciliation — many contractors measured against one comparable standard. A bespoke assurance engine turned schedule quality from a monthly argument into a single, repeatable score.
  • Programme-level visibility means reading time, risk and change together across packages, so exposure in one shows up as a decision before it becomes delay across the whole programme.
  • Forensic rigour scales both ways — the same event-by-event discipline applied across the programme is what let a velodrome sub-project’s extension position resolve on the evidence.
Airfield infrastructure · AED 1.8B · Abu Dhabi

Abu Dhabi International Airport — Airfield

Lead scheduling and controls on airfield infrastructure — runways, tunnels beneath them, aircraft parking stands, radar towers, fire stations and ALCMS — delivered alongside live airport operations, not the passenger terminals.

Transferable lessons
  • When work happens around live operations, access windows and operational constraints — not the construction durations — often drive the real critical path. Constraint discipline becomes the job.
  • Heavy airside interface content means the schedule risk lives in the handoffs; interface milestones need owners and protected float, not optimism.
RTA · AED 148.7M · Dubai

Dubai Metro Route 2020

Project controls and schedule assurance on a fixed-opening rail extension delivered over a live network.

Transferable lessons
  • A fixed, publicly committed opening date inverts planning: you plan backwards from the milestone, and every window’s float is measured against a date that cannot move.
  • On a live network, interface and possession windows are the scarce resource — the controls task is protecting them, because they cannot be recovered once lost.
Abu Dhabi Housing Authority · AED 13.47B · Abu Dhabi, UAE

Riyadh City Infrastructure Programme

Programme planning across 14 construction and 2 design contracts on a city-scale Abu Dhabi development, leading 12 senior planners.

Transferable lessons
  • At city scale across many contracts, the controls task is standardisation — one baseline standard, one reporting rhythm, one EOT methodology applied consistently to every contract, so results stay comparable and defensible.
  • Consistent method is what lets a 291-day claim resolve to an approved 64 days — the discipline scales because it is the same discipline everywhere.
Muscat, Oman

Oman Botanical Garden

Integrated planning and controls across the design, procurement and construction interfaces on a landmark environmental development.

Transferable lessons
  • Where design, procurement and construction overlap, the schedule risk lives in the handoffs — not the construction bars. A late design package or a long-lead procurement item quietly becomes the critical path.
  • Integrating the three fronts in one logic-linked programme is what makes those handoffs visible before they bite.
Jacobs Mace JV · Dubai

Expo 2020 Dubai

Programme controls contribution on a landmark event programme delivered to a fixed, globally committed opening.

Transferable lessons
  • An immovable global deadline makes concurrency the core discipline — many packages finishing into the same window, where a slip anywhere competes for the same completion date.
  • Fixed-deadline programmes reward early, unglamorous discipline: the recovery options narrow as the date approaches, so exposure has to be surfaced early to be worth anything.