Expertise

Project ControlsPlanning and Primavera P6Schedule AssuranceEOT ClaimsForensic Delay AnalysisProgramme ManagementPMO LeadershipDigital Project ControlsAll expertise

Framework

Project Controls Management System100-Point Schedule Assurance FrameworkHow I WorkOperating PrinciplesImplementation ChecklistsMaturity Model

Tools

Project Controls IntelligenceDecision Centre: start hereDirector’s 10-Minute ReviewForensic Delay LabProgramme DashboardProgramme SimulatorRisk and Early WarningExecutive Review GeneratorSchedule Assurance ChallengeProgramme Management toolsChecklists and templates

Academy

Learning pathwaysProfessional ReferencesPrimavera P6 GuidesThe SCL Protocol seriesGlossary

Insights

ArticlesCase StudiesProjectsDirector’s PlaybookRed Flags and Failure AtlasLessons from Major ProgrammesClaims and Delay articles

About

AboutExecutive ProfileDownload Executive CVLinkedIn
Search

Searches articles, case studies, guides and tools on this site. Runs in your browser — nothing is sent anywhere.

Primavera P6 Practical Guides

Recovery Programmes

A genuine plan, or a work of fiction.

What it is

A revised programme intended to pull a slipping project back toward its completion date.

Why it matters

A recovery programme is either credible or fiction, and most fail on the same unrealistic assumptions. Testing it is a core controls task.

In practice

  • Test the recovery against evidence — is the assumed productivity achievable given actuals to date?
  • Check what has actually been compressed: durations cut, logic relaxed, resources assumed but not secured?
  • A recovery that relies on stripping float or overlapping everything is not credible.
  • Recovery has to be resourced — more work in less time needs the people to do it.

Watch for

  • Durations halved with no method statement behind them.
  • Logic relaxed (FS changed to SS) purely to shorten the path.
  • Assumed productivity that was never actually achieved on the job.