Expertise

Project ControlsPlanning and Primavera P6Schedule AssuranceEOT ClaimsForensic Delay AnalysisProgramme ManagementPMO LeadershipDigital Project ControlsAll expertise

Framework

Project Controls Management System100-Point Schedule Assurance FrameworkHow I WorkOperating PrinciplesImplementation ChecklistsMaturity Model

Tools

Project Controls IntelligenceDecision Centre: start hereDirector’s 10-Minute ReviewForensic Delay LabProgramme DashboardProgramme SimulatorRisk and Early WarningExecutive Review GeneratorSchedule Assurance ChallengeProgramme Management toolsChecklists and templates

Academy

Learning pathwaysProfessional ReferencesPrimavera P6 GuidesThe SCL Protocol seriesGlossary

Insights

ArticlesCase StudiesProjectsDirector’s PlaybookRed Flags and Failure AtlasLessons from Major ProgrammesClaims and Delay articles

About

AboutExecutive ProfileDownload Executive CVLinkedIn
Search

Searches articles, case studies, guides and tools on this site. Runs in your browser — nothing is sent anywhere.

Project Controls Intelligence

Forecast Integrity

Does the forecast reflect what is actually happening?

What it is

Whether the forecast completion date is credible — a reflection of real progress and logic, not what the programme would prefer to show.

Why it matters

Leadership plans, commits and mitigates on the forecast. A forecast that isn’t honest is worse than no forecast, because decisions are made on it.

What to check

  • Does the forecast follow from real progress and logic, or from a constraint?
  • Has the critical path been re-tested for this update?
  • Are any recovery assumptions realistic and evidenced?
  • Is remaining float genuine or artificial?
  • Does the forecast reconcile with the slippage trend?

Common warning signs

  • A completion date pinned by a hard constraint
  • Recovery that assumes impossible productivity
  • Float that appears from nowhere
  • A forecast that never moves despite visible slippage

Practical approach

Rebuild the forecast from the driving path and real progress; test recovery against evidence; strip artificial float. An honest forecast is one leadership can plan against.