Expertise

Project ControlsPlanning and Primavera P6Schedule AssuranceEOT ClaimsForensic Delay AnalysisProgramme ManagementPMO LeadershipDigital Project ControlsAll expertise

Framework

Project Controls Management System100-Point Schedule Assurance FrameworkHow I WorkOperating PrinciplesImplementation ChecklistsMaturity Model

Tools

Project Controls IntelligenceDecision Centre: start hereDirector’s 10-Minute ReviewForensic Delay LabProgramme DashboardProgramme SimulatorRisk and Early WarningExecutive Review GeneratorSchedule Assurance ChallengeProgramme Management toolsChecklists and templates

Academy

Learning pathwaysProfessional ReferencesPrimavera P6 GuidesThe SCL Protocol seriesGlossary

Insights

ArticlesCase StudiesProjectsDirector’s PlaybookRed Flags and Failure AtlasLessons from Major ProgrammesClaims and Delay articles

About

AboutExecutive ProfileDownload Executive CVLinkedIn
Search

Searches articles, case studies, guides and tools on this site. Runs in your browser — nothing is sent anywhere.

Project Controls Intelligence

Progress Integrity

Is reported progress measurable and defensible?

What it is

Whether reported progress represents actual, evidenced project progress — not optimism, not round numbers, not a figure produced to hit a reporting date.

Why it matters

Every forecast and every claim rests on progress. If reported percent-complete cannot be evidenced, the forecast built on it is fiction and the claim will not survive scrutiny.

What to check

  • Is progress measured the same way every cycle?
  • Is it evidenced by records and quantities, not asserted?
  • Do actual start and finish dates reconcile with the contemporaneous record?
  • Is earned value consistent with physical progress?
  • Is out-of-sequence progress explained?

Common warning signs

  • Progress that only ever moves forward
  • Round-number percentages
  • Actual dates that don’t match site records
  • Physical progress lagging the reported percentage
  • Sudden catch-up just before a reporting date

Practical approach

Measure progress against a fixed rule every cycle, reconcile actual dates to the record, and separate earned from claimed. This is the difference between schedule updating and schedule control.