Module · Risk and opportunity management
Risk and Early Warning
Two parts. First, twelve early-warning indicators that show whether a programme is heading for trouble before the completion date moves. Second, a working risk register: heat maps, expected exposure, what mitigation is buying, a risk-adjusted forecast and what needs escalating.
Runs in your browser. The register opens with a fictional example; your own entries are kept only in this browser. Exposure is calculated by expected value, a simple deterministic method. This is not a simulation and gives no confidence levels.
Early-warning indicators
For each, is the signal present on your programme now? Answer “not known” rather than guess; unknowns are reported as information gaps.
Risk and opportunity register
Ratings 1 (low) to 5 (high). Probability ratings stand for 10, 30, 50, 70 and 90%. Cost in any unit used consistently; time in days. Residual columns are after mitigation; leave them blank if mitigation has no effect yet.
Module How this tool works: inputs, method and limitations
- Purpose
- Spot programme trouble before it reaches the completion date, and keep a risk register that shows exposure, ownership and what mitigation is buying.
- Intended user
- Risk managers, controls leads and programme directors preparing a monthly risk review.
- Output
- An early-warning band with the indicators driving it; inherent and residual heat maps; exposure, mitigation effect and risk-adjusted forecast; escalations, ownership gaps, trend and exposure by milestone.
- How the result is produced
- Calculated from judgement-based ratings. Results depend on ratings or estimates you enter; they are not measured performance.
- PCMS discipline
- Risk and opportunity management · Volume 3: Reporting and Performance Management
- Learn the method
- Reading a schedule risk analysis (Advanced pathway)
- Inputs
- Answers to twelve early-warning indicators (present, partly, absent, not known)
- Risks and opportunities: owner, probability and impact ratings 1–5, cost and time effect, linked milestone, mitigation, residual ratings and effects, trend
- Optional base cost forecast and an escalation score threshold
- Method
- Early warning: weighted share of indicators present (partly counts half); “not known” is excluded and reported as a gap. Bands: 50% and above act now, 25% and above watch closely; a critical indicator present raises the band.
- Score = probability rating × impact rating (1–25). Probability ratings map to mid-band probabilities of 10, 30, 50, 70 and 90%.
- Expected exposure = mapped probability × cost (or days). Mitigation effect = 1 − residual exposure ÷ inherent exposure.
- Risk-adjusted forecast = base forecast + residual risk exposure − opportunity exposure. Escalate risks whose residual score reaches the threshold.
- Limitations
- Expected value is a simple deterministic method, not a simulation; it does not produce confidence levels.
- Schedule exposure is summed by milestone for visibility; delays on parallel paths do not add up in reality.
- Ratings are judgements; their value depends on consistent definitions.
- Suggested actions
- Give every risk scoring 10 or more an owner and a mitigation.
- Report residual, not inherent, exposure in the forecast.
- Treat indicators marked “not known” as information requests.
- How to read the result
- The result is indicative: a structured prompt for professional judgement, not a determination. Use it to decide what to check next, then confirm against the programme, the records and the contract.
- Related
- Expertise: Project Controls · Reference: Risk and change standards · Case study: Hudayriyat West programme · 100-Point Framework · Not sure where to start? Decision Centre
Runs in your browser; nothing is sent to a server. A practitioner’s aid, not a certification or a contractual determination. See how the measures combine in the Programme Intelligence Dashboard. All tools →