Project Controls · Programme Governance
AED 28.1B Hudayriyat West
Leading integrated project controls across a flagship AED 28.1B island-development programme — one defensible view of time, cost, risk and performance.
At a glance
- Project context
- Modon’s AED 28.1B Hudayriyat West Island Development, Abu Dhabi: seven concurrent construction packages, each with its own contractor.
- Challenge
- Ten ways of planning and reporting (Primavera P6, MS Project and spreadsheets) made the programme impossible to read as one.
- Initial condition
- Fragmented package views, with no common coding, progress rules or reporting format.
- Intervention
- A common controls standard and procedures manual for every package, with integrated assurance, earned value, risk and change.
- Methodology
- Schedule assurance, earned value, contractor surveillance and an executive dashboard on one data set.
- Results
- One reconciled programme picture across the seven packages, the standard adopted as the employer’s template, and the baseline-review discipline reused on other Abu Dhabi programmes.
- Professional contribution
- Leading the employer-side integrated project controls function across all seven packages within the EllisDon PMC, with the wider PMC and package teams.
- Lessons learned
- At this scale the controls challenge is consistency and reconciliation, not any single schedule.
- Tools and methods
- Project Controls Management System · Programme Intelligence Dashboard
01 — The Position
A flagship AED 28.1B island-development programme delivered through seven concurrent construction packages — a velodrome, a sports hotel, phase-one infrastructure, a high-performance centre, a sports hub and more — each let to a different contractor, each with its own planning methodology, software (Primavera P6, MS Project, even Excel), work-breakdown structure and reporting format. There was no centralised controls structure and no reconciled programme picture: the Employer received inconsistent information, and programme-level decisions could not be made on it. The role: leading the Employer-side integrated project controls function across all seven packages within the PMC.
02 — The Evidence
Ten contractors’ programmes and updates in incompatible formats, progress reports in varied templates with different earning rules, and the Employer’s own procedures and FIDIC-based contracts. Confidential project records limit the level of detail that can be published. Project facts are programme context, distinct from any individual contribution — this was a team effort across the programme’s planning function and its contractors.
03 — The Programme Analysis
The core problem was not any single schedule — it was that ten different ways of working made the programme impossible to read as one. The answer was a common standard: a Project Controls Framework and procedures manual defining, for every package, the schedule format, WBS and activity coding, progress-measurement rules, earned-value method, reporting templates and interface protocols — so that ten submissions became one comparable picture.
04 — Event Mapping
Package-level time, cost, risk, change and performance were mapped onto that standard through a federated Primavera P6 Enterprise — contractors maintained their detailed schedules but pushed summary milestones into a programme master schedule — fed by a synchronised reporting calendar that consolidated ten independent submissions into one integrated programme report for the Employer’s leadership each cycle. Schedule assurance (100-point), earned value, risk and change sat in one structure.
05 — Cause & Effect
Without integration, exposure surfaces as delay after the fact; integrated, it surfaces as a decision in time. When one infrastructure package hit unforeseen ground conditions, the integrated programme identified the knock-on impact immediately and let it be contained to a matter of weeks, against a forecast that could otherwise have run to months. Soft impressions that “a contractor is slipping” became evidenced, governable signals.
06 — Critical Path
Schedule assurance and forensic delay analysis kept the programme’s driving paths honest. The same discipline that resolved a velodrome extension position event by event — 426 days claimed, 91 assessed — was applied at programme scale, every contractor submission scored against the 100-Point Employer Schedule Assurance Framework. The baseline-review standard behind it was sound enough that the Employer went on to adopt it across other Abu Dhabi programmes.
07 — Entitlement / Assessment
The assessment leadership needed was continuous and evidence-based: is each package reliable, where is the real exposure, which contractor is slipping and why, and what decision does it require now. Alongside it, direct contractual advice to the Employer under the FIDIC conditions — extension-of-time entitlement, time-bar provisions and the Engineer’s determination process — drawing on forensic analysis and arbitration experience.
08 — The Decision
Integrated project controls — schedule assurance, earned value, risk and change, contractor-performance surveillance, and an interactive executive dashboard (schedule performance, cost variance, earned-value trend, risk exposure, change status) connected to the programme’s document platform — producing one defensible view of time, cost, risk and performance. Decision support, not just reporting. The same integrated-planning approach was then taken upstream, into the delivery strategy for the programme’s next phase.
09 — The Outcome
A single, reconciled programme picture and executive decision support across the seven packages — programme-level visibility where there had been fragments. A common controls standard adopted as the Employer’s template; a baseline-review discipline reused across other Abu Dhabi programmes; a planning function of fifteen professionals built into a functioning matrix across the contractors; and a forensic and assurance capability that held contractor programmes to a defined standard.
10 — Director’s Lesson
At AED 28.1B and seven concurrent packages, the controls challenge is not any single schedule — it is reconciliation and consistency. Integrated programme controls, built on one common standard, is what turns many packages into one governable programme — without eliminating the judgement each package team brings.
Apply this to your programme
Reconciling many packages into one picture? Start by checking:
- Can you reconcile time, cost, risk and change into one programme view?
- Is contractor performance evidenced, or still impression?
- Does reporting reach the decision-maker in time to act?
- Is schedule assurance applied the same way across every package?
Then put it to work: Executive Dashboard KPI Framework · Project Controls Intelligence · 100-Point Framework · Playbook — Reporting.
Follow the thread
Case study → method → evidence → decision: 100-Point Framework · Forensic Delay Analysis · Programme Governance · Director’s Playbook. See the decision framework behind it in How I Work.
This case study describes Rishi Javeri's professional project-controls role and methodology; it does not disclose confidential parties, contracts, schedules or commercially sensitive material, and does not imply sole delivery of the programme. It describes professional practice, not legal advice.