Expertise

Project ControlsPlanning and Primavera P6Schedule AssuranceEOT ClaimsForensic Delay AnalysisProgramme ManagementPMO LeadershipDigital Project ControlsAll expertise

Framework

Project Controls Management System100-Point Schedule Assurance FrameworkHow I WorkOperating PrinciplesImplementation ChecklistsMaturity Model

Tools

Project Controls IntelligenceDecision Centre: start hereDirector’s 10-Minute ReviewForensic Delay LabProgramme DashboardProgramme SimulatorRisk and Early WarningExecutive Review GeneratorSchedule Assurance ChallengeProgramme Management toolsChecklists and templates

Academy

Learning pathwaysProfessional ReferencesPrimavera P6 GuidesThe SCL Protocol seriesGlossary

Insights

ArticlesCase StudiesProjectsDirector’s PlaybookRed Flags and Failure AtlasLessons from Major ProgrammesClaims and Delay articles

About

AboutExecutive ProfileDownload Executive CVLinkedIn
Search

Searches articles, case studies, guides and tools on this site. Runs in your browser — nothing is sent anywhere.

Digital

Using Python to Improve Primavera P6 Schedule Assurance

Reviewing schedule quality by hand does not scale. On a large programme, no team can check thousands of activities across a dozen contractors every month and stay consistent — so the check itself has to become code.

By Rishi JaveriPublished 04-Aug-26Updated 12-Aug-267 min read

Why manual review breaks down

Across many contractors and tens of thousands of activities, manual review becomes slow, inconsistent and impossible to keep honest. Quality becomes a matter of who looked and when.

Rules as code

Every check that matters can be written as a precise rule, and any rule can be applied by code — identically, every time. The DCMA 14-point checks are the natural starting set because they are already defined as measurable tests.

How it works, end to end

Export the schedule from P6 as an XER file, parse it in Python, apply each rule across the whole network, and produce a score plus an itemised list of failures. The monthly assurance cycle stops being a bottleneck and becomes a button — and every contractor’s programme is scored the same way.

Beyond DCMA, and where judgement still rules

Layer bespoke Employer rules on top, as the 100-Point Employer Schedule Assurance Framework does. On one package programme, this approach lifted schedule quality from around 25% to over 83% on the framework’s 100-point scale, and held it. But automation only raises the floor: a schedule can pass every check and still be unbuildable. The code handles the objective thousands; expert judgement handles whether the plan is actually real.