Calculator · Planning and schedule control
Critical Path Stability Monitor
How much the critical path changes between updates, what joined and left, and how completion moved.
Enter your own figures in any currency or unit, used consistently. The form opens with a fictional worked example so you can see how it reads. Calculations run in your browser; nothing is sent or stored. It does not connect to any scheduling or cost system.
Calculator How this tool works: inputs, method and limitations
- Purpose
- Spot critical path migration and instability across a run of programme updates.
- Intended user
- Planners, schedule reviewers and delay analysts reviewing monthly updates.
- Output
- Similarity and status for each pair of updates, activities joining and leaving, completion movement, core critical activities and runs of later forecasts.
- How the result is produced
- Calculated.
- PCMS discipline
- Planning and scheduling · Volume 2: Planning, Scheduling and Progress Management
- Learn the method
- Planning and scheduling fundamentals (Foundation pathway)
- Worked example
- The tool opens with a fictional worked example; “Load example” restores it and “Clear” resets every input. Results can be downloaded as CSV or printed.
- Inputs
- For each update, oldest first: a label, the forecast completion (day number or days late) and the IDs of the critical activities
- Method
- Similarity between consecutive updates = activities critical in both ÷ activities critical in either (Jaccard index).
- Stable at 80% and above, shifting at 50% and above, migrated below 50%. Volatility = 1 − average similarity.
- Core critical activities are critical in at least 75% of updates.
- Limitations
- Depends on consistent activity IDs between updates.
- Says that the path moved, not why: check logic, constraints and progress for each migration.
- Suggested actions
- Require a narrative for every migration.
- Escalate when completion moves later in consecutive updates.
- How to read the result
- The result is indicative: a structured prompt for professional judgement, not a determination. Use it to decide what to check next, then confirm against the programme, the records and the contract.