Expertise

Project ControlsPlanning and Primavera P6Schedule AssuranceEOT ClaimsForensic Delay AnalysisProgramme ManagementPMO LeadershipDigital Project ControlsAll expertise

Framework

Project Controls Management System100-Point Schedule Assurance FrameworkHow I WorkOperating PrinciplesImplementation ChecklistsMaturity Model

Tools

Project Controls IntelligenceDecision Centre: start hereDirector’s 10-Minute ReviewForensic Delay LabProgramme DashboardProgramme SimulatorRisk and Early WarningExecutive Review GeneratorSchedule Assurance ChallengeProgramme Management toolsChecklists and templates

Academy

Learning pathwaysProfessional ReferencesPrimavera P6 GuidesThe SCL Protocol seriesGlossary

Insights

ArticlesCase StudiesProjectsDirector’s PlaybookRed Flags and Failure AtlasLessons from Major ProgrammesClaims and Delay articles

About

AboutExecutive ProfileDownload Executive CVLinkedIn
Search

Searches articles, case studies, guides and tools on this site. Runs in your browser — nothing is sent anywhere.

Foundation pathway · Planning and scheduling fundamentals

Planning and Scheduling Fundamentals

A programme is a model of how the work will be built. Get the building blocks right and everything downstream, from progress to delay analysis, has something solid to stand on.

By Rishi Javeri · 01-Nov-26 · 8 min read

Every control decision on a project eventually leans on the programme. Progress is measured against it, delay is analysed through it, and the forecast completion date comes out of it. That is why the fundamentals matter more than the software.

Plan first, then schedule

Planning decides what will be done, how and in what order: the scope, the construction method, the sequence, who does what. Scheduling puts that plan on a timeline: durations, links, calendars and dates. Teams that skip straight to scheduling produce programmes that look complete but cannot answer the question “why is this activity here, in this order?”

The building blocks

ElementWhat it isWhat goes wrong
Work breakdown structureThe scope divided into manageable partsBuilt around departments, not deliverables, so reporting never matches the work
ActivityA piece of work with a clear start, finish and ownerToo long to measure (“Fit-out, 180 days”) or too vague (“Works”)
LogicThe relationships between activities: finish-to-start, start-to-start, finish-to-finishMissing links (open ends) and heavy lags that hide real work
DurationHow long the activity takes, from quantity and productivityDurations chosen to fit a date instead of the method
CalendarWhen work can happenOne calendar for everything, ignoring shifts, holidays or summer working limits
ConstraintA date imposed on an activityUsed to force dates the logic does not support

Float and the critical path

Once logic and durations are in place, the scheduling engine calculates, for every activity, the earliest and latest it could start and finish without delaying completion. The difference is total float: how far an activity can slip before it delays the project end date (or a constrained milestone).

The critical path is the longest chain of logically linked activities through the programme. Its activities have the least float, usually zero. Delay anything on it and completion moves.

Two points catch people out:

  • Float is shared along a path. If three activities in a chain each show 10 days of float, there are 10 days for the whole chain, not 30.
  • The critical path moves. As work progresses, other paths can become longer. That is why it must be traced at every update, not assumed.

A worked example

A small fictional sequence: excavate (5 days), pour foundations (8 days), then two parallel streams before handover.

ActivityDurationFollowsEarly finishTotal float
A Excavate5startday 50
B Foundations8Aday 130
C Superstructure20Bday 330
D Drainage10Bday 2310
E Handover2C and Dday 350

The critical path is A–B–C–E (35 days). Drainage has 10 days of float because it only needs to finish before handover, which waits for the superstructure. If drainage slips by 12 days, it finishes on day 35, handover starts on day 35 instead of 33, and the project finishes two days late. The critical path now runs through drainage.

Signs of a sound programme

  • Every activity, except the first and last, has a predecessor and a successor.
  • Constraints are few, justified and visible.
  • Durations can be explained from quantities and output rates.
  • The critical path runs continuously from the data date to completion, through work that obviously drives the finish.
  • It is coded so that it can be reported by area, package and contractor.
Go further: the Primavera P6 guides cover the mechanics in the software, and the Schedule Health Check gives a quick read of a programme you have received.

Check your understanding

Three questions. Choose an answer in your head, then open it to compare.

1Activities A, B and C form a single chain to completion, and each shows 10 days of total float. A finishes 6 days late. How much total float do B and C now have?

  1. 10 days each: A used its own float
  2. 4 days each
  3. None: the chain is now critical
  4. Minus 6 days each
Show the answer

B. 4 days each The 10 days are shared by the whole chain, not owned by each activity. A's 6-day slip uses 6 of them, leaving 4 days for B and C together.

2Which is the strongest sign that a programme's dates are driven by constraints rather than logic?

  1. Many activities have start-to-start links
  2. Many milestones carry 'must finish on' or 'finish no later than' constraints
  3. The programme has more than 2,000 activities
  4. Durations are in working days
Show the answer

B. Many milestones carry 'must finish on' or 'finish no later than' constraints Hard constraints fix dates regardless of logic. When many key dates are constrained, the programme stops modelling cause and effect, and float and the critical path become unreliable.

3What is the difference between a plan and a schedule?

  1. There is none; the words are interchangeable
  2. The plan decides what will be done, how and in what order; the schedule puts that onto a timeline with durations and dates
  3. A schedule is produced by the employer, a plan by the contractor
  4. A plan is in P6; a schedule is in Excel
Show the answer

B. The plan decides what will be done, how and in what order; the schedule puts that onto a timeline with durations and dates Planning is the thinking: scope, method, sequence and responsibilities. Scheduling turns that thinking into time. A schedule without a plan behind it is just dates.