Expertise

Project ControlsPlanning and Primavera P6Schedule AssuranceEOT ClaimsForensic Delay AnalysisProgramme ManagementPMO LeadershipDigital Project ControlsAll expertise

Framework

Project Controls Management System100-Point Schedule Assurance FrameworkHow I WorkOperating PrinciplesImplementation ChecklistsMaturity Model

Tools

Project Controls IntelligenceDecision Centre: start hereDirector’s 10-Minute ReviewForensic Delay LabProgramme DashboardProgramme SimulatorRisk and Early WarningExecutive Review GeneratorSchedule Assurance ChallengeProgramme Management toolsChecklists and templates

Academy

Learning pathwaysProfessional ReferencesPrimavera P6 GuidesThe SCL Protocol seriesGlossary

Insights

ArticlesCase StudiesProjectsDirector’s PlaybookRed Flags and Failure AtlasLessons from Major ProgrammesClaims and Delay articles

About

AboutExecutive ProfileDownload Executive CVLinkedIn
Search

Searches articles, case studies, guides and tools on this site. Runs in your browser — nothing is sent anywhere.

Methodology

Forensic Delay Analysis

Reconstructing, from the programme and the record, how specific events actually affected completion — so entitlement rests on evidence another analyst could reproduce, not on the story a claim would prefer to tell.

This sits beneath Forecast Integrity in the wider framework, and alongside Extension of Time.

Evidence of thinking
Problem

A claimed extension-of-time position that has to be tested against the record.

Method

Windowed, longest-path forensic analysis — validity, criticality and causation, event by event.

Evidence

The baseline, the contemporaneous updates, and the instruction and correspondence record.

Decision

The Employer-risk critical delay that is actually demonstrable.

Outcome

A defensible, evidence-based entitlement rather than a negotiated number.

Try a Time Impact Analysis in the Forensic Delay Lab →

Why it becomes difficult

The simple version collapses under its own complexity.

By the time a delay is disputed, “the job is late, so we’re owed time” has usually stopped being true in any simple sense. A credible analysis has to hold several hard things at once.

Concurrent events

Several delays running at once, each arguably driving completion over the same window.

A migrating critical path

The path that controls completion moves as the work progresses — what was critical in month four may not be in month nine.

Baseline integrity

If the accepted programme is weak, everything measured against it inherits the weakness.

Mitigation & acceleration

Recovery effort masks delay; the analysis has to see through it to what actually happened.

Contractor vs Employer risk

The same slip can be excusable, compensable, or neither — depending on whose risk it was.

Contemporaneous records

A claim is only as strong as the record made while events unfolded; reconstruction reads differently.

Causation, not correlation

Two things going wrong together is not proof that one caused the other.

Effect on the milestone

Only delay that reaches a contractual completion milestone moves entitlement.

100% 50% 0% Programme duration → Cumulative % slip Planned Actual
Planned versus actual cumulative progress. Delay shows in the data as a widening gap between the curves; the horizontal distance at completion is the slip the analysis has to explain — event by event, on the critical path.

The analytical workflow

From contract to entitlement.

Every step is measured against the contemporaneous record. Skip one and the result stops being reproducible — which is the only thing that makes a determination defensible.

01

Contract

↓

What the contract requires — notice provisions, risk allocation, the completion milestones that matter.

02

Baseline

↓

The accepted, logic-linked programme the analysis is measured against.

03

Updates

↓

Contemporaneous progress — establishing where the driving path actually ran when each event bit.

04

Delay events

↓

Each event isolated, evidenced, and tested for a valid contractual trigger.

05

Critical path

↓

Which path drove completion in each window — and how it migrated across the programme.

06

Causation

↓

Cause and effect demonstrated rather than asserted; concurrency identified honestly.

07

Time impact

↓

The days each event genuinely added to completion — net of float and mitigation.

08

Entitlement

The Employer-risk critical delay that supports an extension of time — kept separate from the money question.

Contract → Baseline → Updates → Delay events → Critical path → Causation → Time impact → Entitlement

Choosing the method

No single correct method — a correct method for the evidence.

AACE 29R-03 recognises a family of techniques — impacted as-planned, time impact analysis, as-planned versus as-built, windows, and collapsed as-built — each with a proper application and a characteristic weakness. Selection is driven by the records, the programme quality, the timing and the purpose; the real test is whether an independent analyst, given the same records, would reach a comparable result. Where the choice of method is doing the work the evidence should be doing, it is advocacy, not assessment. This is set out in full in how a delay is measured, with the honest treatment of concurrency and risk ownership alongside it.

  • Time Impact Analysis models an event into the programme current when it arose, to show its prospective effect on completion.
  • Windows or time-slice analysis divides the works into periods and measures delay within each against the schedule then in force.
  • As-planned versus as-built compares the intended sequence with what actually happened.
  • Impacted as-planned and collapsed as-built are used where the records or programmes constrain the options.

Prospective methods look forward from a point in time; retrospective methods reconstruct from the as-built record. The work is informed by AACE International's Recommended Practice 29R-03 and the Society of Construction Law Delay and Disruption Protocol, as reference points for method and terminology rather than any endorsement. See the 29R-03 reference guide and the SCL Protocol reference guide.

Get in touch

Discuss forensic delay analysis, critical-path cause and effect, and Extension of Time.

Connect with Rishi →

Frequently asked questions

What is the difference between prospective and retrospective delay analysis?

Prospective analysis forecasts the likely effect of an event on completion at the time it happens, usually with a time impact analysis. Retrospective analysis looks back at what actually happened, using methods such as windows analysis or as-planned versus as-built comparison.

Which delay analysis method is best?

None is best in every case. The right method depends on the contract, the nature of the events, the quality of the programme updates and records, and the time and cost available. Both the SCL Protocol and AACE 29R-03 say the choice should be explained.

What is critical path migration?

The critical path can move between updates as work progresses and events occur. A sound analysis tracks the path in each window rather than assuming the baseline critical path still drives completion.

What records does a forensic delay analysis rely on?

Accepted programme updates and their native files, progress records, correspondence, instructions, minutes, site diaries and notices. Gaps in contemporaneous records limit which methods can be used and how much weight the result carries.