SCL Delay and Disruption Protocol (2nd Ed.): Reference Guide
01What it covers
Practical guidance on extensions of time and compensation for delay and disruption: the records and programme a project should keep, how delay should be assessed during the project and afterwards, float, concurrency, mitigation, and how to show disruption.
02Why it matters
It is the most widely referenced common ground on delay in the UK, the Middle East and many international projects. Tribunals, engineers and contract administrators often use it as a reference point, so a submission or determination that departs from it needs a reason.
03Key principles
- Keep and update an accepted programme, and keep contemporaneous records good enough to show what happened and when.
- Deal with extension of time applications as close as practicable to the delay event, rather than waiting until the end of the project.
- Choose the delay analysis method to suit the contract, the events, the records and the time available; the Protocol does not rank the methods.
- Treat float, concurrency and mitigation openly, and explain the position taken on each.
- For disruption, prefer a comparison of productivity on the same work with and without the disrupting events (the measured mile) over a global claim.
04Practical application
- Write the Protocol’s record-keeping expectations into the project’s controls procedures from day one, not when a claim arrives.
- Assess each notified event with a prospective analysis on the current accepted update, and record the basis of the determination.
- Hold an event register that links each event to its notice, its records and its effect on the programme.
05Common mistakes
- Treating the Protocol as if it were the contract. It is guidance; the contract terms and the governing law decide entitlement.
- Leaving delay assessment until completion, when the records are weakest and positions have hardened.
- Choosing the method that produces the preferred answer instead of the one the records can support.
06PCMS discipline
07Related tools
08Further reading
- The SCL Protocol, in Practice (24-part series)
- Time Impact Analysis: a practical guide
- Delay and Disruption Protocol (publisher)
Written in my own words to explain principles; it does not reproduce the publication and implies no endorsement by Society of Construction Law. Not legal advice.
Other references
- Schedule assessment frameworks: DCMA, GAO, PMI and the 100-point framework
- The GAO schedule and cost guides
- AACE forensic schedule analysis (RP 29R-03)
- AACE planning and scheduling practices
- Earned value management: EIA-748-E and ISO 21508
- Risk and change: ISO 31000 and AACE practices
- Programme governance: PMI, ISO 21503 and MSP