Expertise

Project ControlsPlanning and Primavera P6Schedule AssuranceEOT ClaimsForensic Delay AnalysisProgramme ManagementPMO LeadershipDigital Project ControlsAll expertise

Framework

Project Controls Management System100-Point Schedule Assurance FrameworkHow I WorkOperating PrinciplesImplementation ChecklistsMaturity Model

Tools

Project Controls IntelligenceDecision Centre: start hereDirector’s 10-Minute ReviewForensic Delay LabProgramme DashboardProgramme SimulatorRisk and Early WarningExecutive Review GeneratorSchedule Assurance ChallengeProgramme Management toolsChecklists and templates

Academy

Learning pathwaysProfessional ReferencesPrimavera P6 GuidesThe SCL Protocol seriesGlossary

Insights

ArticlesCase StudiesProjectsDirector’s PlaybookRed Flags and Failure AtlasLessons from Major ProgrammesClaims and Delay articles

About

AboutExecutive ProfileDownload Executive CVLinkedIn
Search

Searches articles, case studies, guides and tools on this site. Runs in your browser — nothing is sent anywhere.

Society of Construction Law

SCL Delay and Disruption Protocol (2nd Ed.): Reference Guide

Delay and Disruption Protocol2nd edition, February 2017 (replaces the 1st edition of 2002 and its Rider 1) · Professional protocol · Free to download from the SCLOfficial source →
Edition checked 02-Nov-26.

01What it covers

Practical guidance on extensions of time and compensation for delay and disruption: the records and programme a project should keep, how delay should be assessed during the project and afterwards, float, concurrency, mitigation, and how to show disruption.

02Why it matters

It is the most widely referenced common ground on delay in the UK, the Middle East and many international projects. Tribunals, engineers and contract administrators often use it as a reference point, so a submission or determination that departs from it needs a reason.

03Key principles

  • Keep and update an accepted programme, and keep contemporaneous records good enough to show what happened and when.
  • Deal with extension of time applications as close as practicable to the delay event, rather than waiting until the end of the project.
  • Choose the delay analysis method to suit the contract, the events, the records and the time available; the Protocol does not rank the methods.
  • Treat float, concurrency and mitigation openly, and explain the position taken on each.
  • For disruption, prefer a comparison of productivity on the same work with and without the disrupting events (the measured mile) over a global claim.

04Practical application

  • Write the Protocol’s record-keeping expectations into the project’s controls procedures from day one, not when a claim arrives.
  • Assess each notified event with a prospective analysis on the current accepted update, and record the basis of the determination.
  • Hold an event register that links each event to its notice, its records and its effect on the programme.

05Common mistakes

  • Treating the Protocol as if it were the contract. It is guidance; the contract terms and the governing law decide entitlement.
  • Leaving delay assessment until completion, when the records are weakest and positions have hardened.
  • Choosing the method that produces the preferred answer instead of the one the records can support.
Guidance, contract and law. Protocol recommendations are good practice, not obligations. Contract terms (notice periods, time bars, the method an engineer must use) and the governing law take precedence, and the legal treatment of concurrency differs between jurisdictions.

06PCMS discipline

07Related tools

08Further reading

Written in my own words to explain principles; it does not reproduce the publication and implies no endorsement by Society of Construction Law. Not legal advice.