AACE International
AACE planning and scheduling practices
01What it covers
A family of practices that together describe a controlled schedule: how to build logic, what level of detail suits each audience, how to document the basis of a schedule, how to identify the critical path, and how to review a baseline, review an update and manage change to the schedule.
02Why it matters
They give a reviewer specific, recognised questions to ask at each point in a schedule’s life, from the first baseline to the monthly update and every change in between. Each sits within the project control process of AACE’s Total Cost Management Framework.
03Key principles
- Logic should reflect how the work will actually be done; every activity needs a reason to start and a reason to finish.
- Different audiences need different levels of detail, and the levels must stay consistent with each other.
- A written basis of schedule records the scope, assumptions, calendars, methods and risks behind the dates.
- The critical path is identified and tested, not assumed from software flags alone.
- Each update is reviewed for progress integrity and logic changes, and every change to the schedule baseline is controlled and recorded.
04Practical application
- Ask for a basis of schedule with every baseline submission and review the two together.
- Use a structured baseline review and a structured update review as the acceptance step every cycle.
- Log every change to the baseline with its reason and approval.
05Common mistakes
- Accepting a baseline on its format, without testing logic and the critical path.
- Reviewing updates for dates only, missing changed logic and out-of-sequence progress.
- Re-baselining informally, so performance can no longer be measured against an approved reference.
06PCMS discipline
07Related tools
08Further reading
- How to review a Primavera P6 baseline
- Critical path vs longest path
- RP 24R-03 Developing Activity Logic (publisher)
- RP 37R-06 Schedule Levels of Detail, as applied in EPC (publisher)
- RP 38R-06 Documenting the Schedule Basis (publisher)
- RP 49R-06 Identifying the Critical Path (publisher)
- RP 53R-06 Schedule Update Review, as applied in EPC (publisher)
- RP 78R-13 Original Baseline Schedule Review, as applied in EPC (publisher)
- RP 109R-19 Schedule Change Management, as applied in construction (publisher)
Written in my own words to explain principles; it does not reproduce the publication and implies no endorsement by AACE International. Not legal advice.
Other references
- SCL Delay and Disruption Protocol (2nd Ed.): Reference Guide
- Schedule assessment frameworks: DCMA, GAO, PMI and the 100-point framework
- The GAO schedule and cost guides
- AACE forensic schedule analysis (RP 29R-03)
- Earned value management: EIA-748-E and ISO 21508
- Risk and change: ISO 31000 and AACE practices
- Programme governance: PMI, ISO 21503 and MSP