Expertise

Project ControlsPlanning and Primavera P6Schedule AssuranceEOT ClaimsForensic Delay AnalysisProgramme ManagementPMO LeadershipDigital Project ControlsAll expertise

Framework

Project Controls Management System100-Point Schedule Assurance FrameworkHow I WorkOperating PrinciplesImplementation ChecklistsMaturity Model

Tools

Project Controls IntelligenceDecision Centre: start hereDirector’s 10-Minute ReviewForensic Delay LabProgramme DashboardProgramme SimulatorRisk and Early WarningExecutive Review GeneratorSchedule Assurance ChallengeProgramme Management toolsChecklists and templates

Academy

Learning pathwaysProfessional ReferencesPrimavera P6 GuidesThe SCL Protocol seriesGlossary

Insights

ArticlesCase StudiesProjectsDirector’s PlaybookRed Flags and Failure AtlasLessons from Major ProgrammesClaims and Delay articles

About

AboutExecutive ProfileDownload Executive CVLinkedIn
Search

Searches articles, case studies, guides and tools on this site. Runs in your browser — nothing is sent anywhere.

Module · Delay analysis

Forensic Delay Lab

Two exercises on one small fictional programme. A prospective Time Impact Analysis: model a delay event as a fragnet in the update current at the time and see its effect on completion. And a retrospective windows analysis: work through the contemporaneous updates window by window, find what drove completion in each, and build a reasoned delay assessment from the records.

The schedule is calculated by a real critical path engine in your browser (forward and backward pass, finish-to-start, start-to-start and finish-to-finish links with lags). It is a teaching model: calendar days, no working calendars or resources, and a fictional project. It is not a forensic analysis of any real dispute, and it does not decide entitlement.

Time Impact Analysis, in eleven steps

Fictional project: Office Building, Package 2. Fourteen activities, one completion milestone. Day 0 is 04-Jan-27.

Windows analysis, from records to a reasoned assessment

Retrospective, on the same fictional project after it has run for 220 days. Four contemporaneous updates divide the period into four windows. In each, compare the programme at the start and end, find the critical path, read the records, decide which event drove completion, and record your conclusion.

Methods

The main delay analysis methods and ideas

One paragraph each, with where to read more in The SCL Protocol, in Practice and the wider library. The method is chosen by the records available and the question being asked, not by preference.

Critical Path Method

The longest chain of logically linked work sets the completion date. Every delay method rests on it: delay only matters if it reaches the path that drives completion.

Time Impact Analysis

Prospective. Insert a fragnet modelling the event into the programme update current at the time, and measure the change in forecast completion. The simulator below works this way.

Windows analysis

Retrospective. Divide the project into periods and, for each, find where the critical path ran and how much completion moved, using the updates at each window boundary.

  • Time slice windows publishes 11-Dec-26

As-planned versus as-built

Retrospective. Compare planned and actual dates on the critical path to show where and when delay arose. Simple, but needs judgement on causation.

  • As-planned vs as-built windows publishes 18-Dec-26

Impacted as-planned

Add delay events to the baseline and measure the effect. Quick, but theoretical: it ignores what actually happened.

  • Impacted as-planned: the theoretical one publishes 27-Nov-26

Collapsed as-built

Retrospective. Remove events from an as-built programme to ask “but for this event, when would we have finished?”. Powerful and easy to abuse.

  • Retrospective longest path and collapsed as-built publishes 25-Dec-26

Prospective and retrospective assessment

Assessing likely delay while it happens is a different job from analysing actual delay afterwards. The method should match the moment and the records.

Concurrent delay

Two delays at once is not automatically concurrency. True concurrency needs both to be effective causes of delay to completion in the same period.

Critical path migration

As work progresses, other paths can become longest. Analysis has to follow the path as it moves, update by update.

Delay event assessment

Each event needs a cause, an effect on the programme and evidence. Without all three it is a complaint, not a claim.

Extension of time entitlement

Time is decided by the contract, the events’ risk allocation, notice and the evidence. An EOT protects against damages; payment is a separate question.

See also: Forensic delay analysis, contract to entitlement · EOT Triage · Advanced learning pathway

Module How this tool works: inputs, method and limitations
Purpose
Teach how a Time Impact Analysis is built and read: baseline, update, critical path, fragnet, logic, impact, path migration, concurrency and evidence.
Intended user
Planners, delay analysts, contract administrators and claims practitioners learning or explaining TIA.
Output
Gantt charts before and after, impact on completion, affected activities, critical path changes, a concurrency check, an evidence rating and a printable analytical summary.
How the result is produced
Calculated (critical path method).
PCMS discipline
Claims, delay analysis and EOT management · Volume 2: Planning, Scheduling and Progress Management
Learn the method
Time Impact Analysis: a practical guide (Advanced pathway)
Inputs
  • TIA: a choice of three fictional delay events, fragnet durations, the activity each fragnet holds up and its lag, and seven evidence answers
  • Windows analysis: your view of which recorded event drove completion in each of four windows
Method
  • Critical path method: forward and backward pass with finish-to-start, start-to-start and finish-to-finish links and lags; total float = late finish − early finish.
  • Progress at the data date: complete work keeps its actual dates; work in progress finishes after the data date by its remaining duration; unstarted work cannot start before the data date.
  • Impact = forecast completion with the fragnets − forecast completion without them. Each event is also run alone, and employer and contractor events separately, to show concurrency.
  • Windows analysis: each of five contemporaneous records (baseline and four updates) is scheduled at its own data date; movement in completion per window = forecast at the end − forecast at the start; critical path compared at both ends.
Limitations
  • Teaching model: calendar days, no working calendars, resources or constraints beyond start-no-earlier-than.
  • Fictional project; not a forensic analysis of any real dispute and not a determination of entitlement.
Suggested actions
  • Check the update’s reliability before relying on any TIA built on it.
  • Tie each fragnet only to the work the event actually affects.
  • Assess the contractor’s own delays over the same period before concluding.
How to read the result
The result is indicative: a structured prompt for professional judgement, not a determination. Use it to decide what to check next, then confirm against the programme, the records and the contract.