Expertise

Project ControlsPlanning and Primavera P6Schedule AssuranceEOT ClaimsForensic Delay AnalysisProgramme ManagementPMO LeadershipDigital Project ControlsAll expertise

Framework

Project Controls Management System100-Point Schedule Assurance FrameworkHow I WorkOperating PrinciplesImplementation ChecklistsMaturity Model

Tools

Project Controls IntelligenceDecision Centre: start hereDirector’s 10-Minute ReviewForensic Delay LabProgramme DashboardProgramme SimulatorRisk and Early WarningExecutive Review GeneratorSchedule Assurance ChallengeProgramme Management toolsChecklists and templates

Academy

Learning pathwaysProfessional ReferencesPrimavera P6 GuidesThe SCL Protocol seriesGlossary

Insights

ArticlesCase StudiesProjectsDirector’s PlaybookRed Flags and Failure AtlasLessons from Major ProgrammesClaims and Delay articles

About

AboutExecutive ProfileDownload Executive CVLinkedIn
Search

Searches articles, case studies, guides and tools on this site. Runs in your browser — nothing is sent anywhere.

Template

Delay Event Register

Purpose

Log delay events as they arise so cause, effect and evidence are captured contemporaneously — because the claim you can prove is the one whose records you kept at the time.

Who it’s for

Planners and claims teams tracking delay events on a live programme.

When to use it

From the first delay event — maintained every cycle, not reconstructed at the end.

Key areas covered
  • Event & date
  • Contract mechanism
  • Cause & risk party
  • Notice & records
  • Milestone & critical-path impact
  • Status
Related framework Claims & Delay Strategy →
Download PDF ↓

Maintain one row per delay event, updated every cycle. The point is contemporaneous capture — cause, effect and evidence recorded while they are fresh, not assembled after a dispute begins. For each event, record:

  • Event reference & date — a unique ID and when the event arose.
  • Description — what happened, concisely and factually.
  • Contract mechanism — the clause the event is claimed under (variation, instruction, EOT).
  • Cause & risk party — Employer-risk or Contractor-risk, on the facts and the contract.
  • Notice — whether contractual notice was served, and when.
  • Records held — the instruction, RFI, correspondence, progress and site records that evidence it.
  • Affected milestone — which contractual milestone is said to be affected.
  • Critical-path impact — whether, and in which window, the event affected the driving path.
  • Programme model — whether a fragnet has been inserted into the contemporaneous update.
  • EOT claimed / assessed — the days claimed and, later, the days assessed.
  • Status — open, under assessment, agreed, or rejected — and the resolution.