Expertise

Project ControlsPlanning and Primavera P6Schedule AssuranceEOT ClaimsForensic Delay AnalysisProgramme ManagementPMO LeadershipDigital Project ControlsAll expertise

Framework

Project Controls Management System100-Point Schedule Assurance FrameworkHow I WorkOperating PrinciplesImplementation ChecklistsMaturity Model

Tools

Project Controls IntelligenceDecision Centre: start hereDirector’s 10-Minute ReviewForensic Delay LabProgramme DashboardProgramme SimulatorRisk and Early WarningExecutive Review GeneratorSchedule Assurance ChallengeProgramme Management toolsChecklists and templates

Academy

Learning pathwaysProfessional ReferencesPrimavera P6 GuidesThe SCL Protocol seriesGlossary

Insights

ArticlesCase StudiesProjectsDirector’s PlaybookRed Flags and Failure AtlasLessons from Major ProgrammesClaims and Delay articles

About

AboutExecutive ProfileDownload Executive CVLinkedIn
Search

Searches articles, case studies, guides and tools on this site. Runs in your browser — nothing is sent anywhere.

Director's Field Notes

Director's Field Notes · Part 3 of 10

When I Receive an EOT Submission, I Don't Start With the Narrative

The narrative is the contractor's case, and a good one is persuasive by design. I start somewhere less persuadable — the programme, the records, and the path that was actually driving completion when the event occurred.

By Rishi JaveriPublished 22-Jul-264 min read

An EOT submission arrives with a well-written narrative and a headline number. The narrative is where most reviews start. It is the last place I do.

The narrative is the contractor’s case, assembled to persuade. That does not make it wrong — but it means it is the argument, not the evidence. So I start with the things that are harder to shape.

The baseline it is measured against. Was it accepted? Is it realistic and logic-driven, or held together by constraints? If the starting line is contestable, the whole analysis is contestable — and I would rather know that first.

Delay-event mapping. I take each pleaded event and locate it: when did it occur, and what was the critical path at that moment? An event that hit a floated activity, or a path that was not driving completion, does not delay the job however painful it felt.

Affected milestones and critical-path impact. Which contractual milestone is actually threatened, and can the effect be demonstrated in the programme — a fragnet in the contemporaneous update — rather than asserted in a paragraph?

Cause, effect and evidence, together. Cause without a proven effect on completion is a bad week, not a claim. Effect without contemporaneous records is unprovable. I am looking for all three to stand up at once.

Net, not gross. The headline is usually the total slip. The entitlement is the Employer-risk, critical portion of it, net of the contractor’s own delay — and the gap between those two numbers is often the entire review.

Only once I have done all that do I read the narrative properly — now as a map to test against the evidence, rather than a conclusion to accept. Where it matches the programme and the records, it is persuasive. Where it does not, I have found exactly the question the submission has to answer.

Start with what is demonstrable. The story is easy to write; the evidence is what decides it.