Expertise

Project ControlsPlanning and Primavera P6Schedule AssuranceEOT ClaimsForensic Delay AnalysisProgramme ManagementPMO LeadershipDigital Project ControlsAll expertise

Framework

Project Controls Management System100-Point Schedule Assurance FrameworkHow I WorkOperating PrinciplesImplementation ChecklistsMaturity Model

Tools

Project Controls IntelligenceDecision Centre: start hereDirector’s 10-Minute ReviewForensic Delay LabProgramme DashboardProgramme SimulatorRisk and Early WarningExecutive Review GeneratorSchedule Assurance ChallengeProgramme Management toolsChecklists and templates

Academy

Learning pathwaysProfessional ReferencesPrimavera P6 GuidesThe SCL Protocol seriesGlossary

Insights

ArticlesCase StudiesProjectsDirector’s PlaybookRed Flags and Failure AtlasLessons from Major ProgrammesClaims and Delay articles

About

AboutExecutive ProfileDownload Executive CVLinkedIn
Search

Searches articles, case studies, guides and tools on this site. Runs in your browser — nothing is sent anywhere.

Framework

EOT Review Checklist

Purpose

Structure the review of an extension-of-time submission so entitlement is tested against cause, criticality and the contract — not just the headline number.

Who it’s for

Contract administrators, PMC / Employer controls and claims reviewers.

When to use it

When assessing an EOT application or preparing a determination.

Key areas covered
  • Cause & Employer risk
  • Criticality & the critical path
  • Net vs gross delay
  • Notices & particulars
  • Time vs money
Related framework Claims & Delay Strategy →
Download PDF ↓ // Tick items on screen for your own review

A structured way to review an Extension of Time submission — so the assessment is disciplined, consistent and defensible, whichever side of it you are on.

  1. Contractual basis — valid mechanism; notices served in time.
  2. Baseline validity — delay measured against a sound, accepted baseline.
  3. Method — suited to timing and records, and applied consistently.
  4. Cause & effect — each event tied by evidence to a critical-path impact.
  5. Critical-path impact — the event drives completion, not merely float.
  6. Concurrency — true concurrency identified and addressed honestly.
  7. Mitigation — reasonable steps taken and reflected.
  8. Records — contemporaneous evidence, not reconstruction.
  9. Conclusion — entitlement stated with reasoning and the residual gap explained.