Expertise

Project ControlsPlanning and Primavera P6Schedule AssuranceEOT ClaimsForensic Delay AnalysisProgramme ManagementPMO LeadershipDigital Project ControlsAll expertise

Framework

Project Controls Management System100-Point Schedule Assurance FrameworkHow I WorkOperating PrinciplesImplementation ChecklistsMaturity Model

Tools

Project Controls IntelligenceDecision Centre: start hereDirector’s 10-Minute ReviewForensic Delay LabProgramme DashboardProgramme SimulatorRisk and Early WarningExecutive Review GeneratorSchedule Assurance ChallengeProgramme Management toolsChecklists and templates

Academy

Learning pathwaysProfessional ReferencesPrimavera P6 GuidesThe SCL Protocol seriesGlossary

Insights

ArticlesCase StudiesProjectsDirector’s PlaybookRed Flags and Failure AtlasLessons from Major ProgrammesClaims and Delay articles

About

AboutExecutive ProfileDownload Executive CVLinkedIn
Search

Searches articles, case studies, guides and tools on this site. Runs in your browser — nothing is sent anywhere.

Delay Analysis

The SCL Protocol, in Practice · Part 9 of 24

Prospective vs Retrospective: Two Different Jobs

There are two ways to look at delay. Prospectively — forward, from a point in time: "what is this event likely to do to completion?" And retrospectively — backward, with hindsight: "what actually happened, and what caused it?" They answer different questions, they can give different answers, and neither is universally right. Which one fits depends on the stage, the purpose, the contract and the records you have.

By Rishi JaveriPublished 13-Nov-266 min read
The 30-second version

There are two ways to look at delay. Prospectively — forward, from a point in time: “what is this event likely to do to completion?” And retrospectively — backward, with hindsight: “what actually happened, and what caused it?” They answer different questions, they can give different answers, and neither is universally right. Which one fits depends on the stage, the purpose, the contract and the records you have.

The construction-site version

Think of a match. Before kick-off, you forecast the likely result from the line-ups and conditions — that’s prospective. After the final whistle, you write the match report from what actually happened — that’s retrospective. Both are legitimate. Both are about the same game. And they frequently disagree, because one is a reasonable prediction and the other is the recorded outcome.

Delay analysis is the same. A prospective assessment made when the event arose is a reasoned forecast of impact. A retrospective assessment made at the end is a reconstruction of what the records show actually occurred. Confusing the two — or expecting them to match — is where a lot of arguments start.

The technical bit

The Protocol frames the analysis methods along two axes: whether the critical path is determined prospectively, contemporaneously or retrospectively, and whether the analysis runs cause → effect (start with the event, model forward to its impact) or effect → cause (start with the actual delay, work back to what caused it).

Prospective analysis is forward-looking and assessed as if from the moment the event arose, using the programme as it stood then. It reflects what was reasonably foreseeable at the time and sits naturally with contemporaneous EOT assessment (and with “don’t wait and see”). It does not know the actual outcome. Retrospective analysis is backward-looking, assessed after the fact, using as-built records to establish the actual critical path and the actual causes. It has the benefit of hindsight — and the risk of it, since hindsight can be selected to suit a case. The 2nd Edition deliberately stopped naming a preferred method for analysis done long after the event; the point is fit, not fashion.

PART 09Two lenses on delayForward from a point in time, or backward with hindsight. Different questions.PROSPECTIVE — FORWARDAssessed from the time of the eventlikely impact →event / nowforecast finishWhat is the event likely to do to completion?cause → effectRETROSPECTIVE — BACKWARDAssessed afterwards, from the records← what actually drove itactual finishas-built causeWhat actually happened — and what caused it?effect → causeDifferent questions — and they can legitimately give different answers.Illustrative (Part 9). Primary reference: SCL Delay & Disruption Protocol, 2nd Edition, 2017. Not legal advice.
Prospective runs cause → effect from the event forward; retrospective runs effect → cause from the actual finish back. Same project, two legitimate questions.

How three roles should read it

The planner

The lens dictates the model. Prospective: use the programme current at the event (correct data date) and forecast forward. Retrospective: build and validate the as-built, then interrogate the actual critical path. Never run a forward forecast on hindsight actuals — that’s neither one thing nor the other.

The claims team

Ask what question the forum is actually asking: entitlement as it stood at the time, or the actual outcome at the end? Pick the lens that fits the contract and the stage — and that your records can support. A beautiful retrospective analysis is worthless without reliable as-built data.

The project manager

Don’t treat a contemporaneous (prospective) EOT and a final (retrospective) assessment as interchangeable. They can differ for good reasons. Understand which one is on the table before you argue the number.

The trap

Assuming the two lenses must agree — or that one is inherently superior. They answer different questions and can legitimately diverge. The related trap is mixing them: running a “prospective” analysis but quietly feeding it hindsight data, which produces a result that is neither defensible forecast nor honest reconstruction.

Worked example

An event arises in month 6.

  • Prospective, at the time: the month-6 programme shows the event likely to push completion 15 days. The contemporaneous EOT is assessed at ~15 days.
  • Retrospective, at the end: the as-built shows the event ultimately delayed completion only 10 days, because other paths changed around it.

Both answers can be correct — for their respective questions. The 15 days was a reasonable forecast when it mattered; the 10 days is what the records show happened. The gap isn’t an error; it’s the difference between the two lenses.

What the Protocol says — and doesn’t

It identifies both prospective and retrospective approaches and classifies the delay-analysis methods by whether the critical path is determined prospectively, contemporaneously or retrospectively, and by the direction of the analysis (cause → effect or effect → cause). It no longer mandates a single method for analysis carried out long after the event.

What it does not say:

  • That one lens is always right.
  • That prospective and retrospective must produce the same number.
  • That hindsight should be imported into a prospective assessment.
  • That the choice is free of the contract, the stage and the records available.
Myth

”Prospective and retrospective should give the same answer — if they don’t, someone got it wrong.”

Reality

They answer different questions — likely impact at the time versus actual impact with hindsight — and can legitimately diverge. The divergence is information, not necessarily an error.

P6Reality check

For a prospective analysis, set the data date to the point the event arose and forecast forward from the then-current update. For a retrospective one, build the as-built from reliable records and test the actual critical path across the period. Keep the two clean — a forward forecast contaminated with hindsight actuals is defensible as neither.

Evidence check

Prospective

  • The programme current at the event (correct data date)
  • The event records and the delay notice

Retrospective

  • Complete, reliable as-built records
  • Progress records and the programme updates across the period

Relevance always depends on the facts and the contract.

Rishi’s takeaway

  • Prospective = likely impact from a point in time (forward). Retrospective = actual impact with hindsight (backward).
  • They answer different questions and can legitimately give different answers.
  • Choose the lens by purpose, stage, contract and the records you actually have.
  • Never import hindsight into a prospective assessment — keep the lenses clean.

Prospective asks what was likely to happen; retrospective asks what did. Don’t confuse the two — and don’t expect them to agree.


References. Society of Construction Law, Delay and Disruption Protocol, 2nd Edition, February 2017 — guidance on delay analysis (paragraph 11 and the methods table at 11.5), including the prospective/contemporaneous/retrospective distinction and the removal of a preferred method for time-distant analysis. The appropriate approach depends on the contract, the stage, the purpose and the records. Educational commentary; not legal advice.

Common questions

What is the difference between prospective and retrospective delay analysis?

There are two ways to look at delay. Prospectively — forward, from a point in time: "what is this event likely to do to completion?" And retrospectively — backward, with hindsight: "what actually happened, and what caused it?" They answer different questions, they can give different answers, and neither is universally right.

Should prospective and retrospective analyses give the same answer?

They answer different questions — likely impact at the time versus actual impact with hindsight — and can legitimately diverge. The divergence is information, not necessarily an error.

What does the SCL Protocol say about prospective and retrospective analysis?

It identifies both prospective and retrospective approaches and classifies the delay-analysis methods by whether the critical path is determined prospectively, contemporaneously or retrospectively, and by the direction of the analysis (cause → effect or effect → cause). It no longer mandates a single method for analysis carried out long after the event.