Delay Analysis
The SCL Protocol, in Practice · Part 9 of 24
Prospective vs Retrospective: Two Different Jobs
There are two ways to look at delay. Prospectively — forward, from a point in time: "what is this event likely to do to completion?" And retrospectively — backward, with hindsight: "what actually happened, and what caused it?" They answer different questions, they can give different answers, and neither is universally right. Which one fits depends on the stage, the purpose, the contract and the records you have.
There are two ways to look at delay. Prospectively — forward, from a point in time: “what is this event likely to do to completion?” And retrospectively — backward, with hindsight: “what actually happened, and what caused it?” They answer different questions, they can give different answers, and neither is universally right. Which one fits depends on the stage, the purpose, the contract and the records you have.
The construction-site version
Think of a match. Before kick-off, you forecast the likely result from the line-ups and conditions — that’s prospective. After the final whistle, you write the match report from what actually happened — that’s retrospective. Both are legitimate. Both are about the same game. And they frequently disagree, because one is a reasonable prediction and the other is the recorded outcome.
Delay analysis is the same. A prospective assessment made when the event arose is a reasoned forecast of impact. A retrospective assessment made at the end is a reconstruction of what the records show actually occurred. Confusing the two — or expecting them to match — is where a lot of arguments start.
The technical bit
The Protocol frames the analysis methods along two axes: whether the critical path is determined prospectively, contemporaneously or retrospectively, and whether the analysis runs cause → effect (start with the event, model forward to its impact) or effect → cause (start with the actual delay, work back to what caused it).
Prospective analysis is forward-looking and assessed as if from the moment the event arose, using the programme as it stood then. It reflects what was reasonably foreseeable at the time and sits naturally with contemporaneous EOT assessment (and with “don’t wait and see”). It does not know the actual outcome. Retrospective analysis is backward-looking, assessed after the fact, using as-built records to establish the actual critical path and the actual causes. It has the benefit of hindsight — and the risk of it, since hindsight can be selected to suit a case. The 2nd Edition deliberately stopped naming a preferred method for analysis done long after the event; the point is fit, not fashion.
How three roles should read it
The lens dictates the model. Prospective: use the programme current at the event (correct data date) and forecast forward. Retrospective: build and validate the as-built, then interrogate the actual critical path. Never run a forward forecast on hindsight actuals — that’s neither one thing nor the other.
Ask what question the forum is actually asking: entitlement as it stood at the time, or the actual outcome at the end? Pick the lens that fits the contract and the stage — and that your records can support. A beautiful retrospective analysis is worthless without reliable as-built data.
Don’t treat a contemporaneous (prospective) EOT and a final (retrospective) assessment as interchangeable. They can differ for good reasons. Understand which one is on the table before you argue the number.
The trap
Assuming the two lenses must agree — or that one is inherently superior. They answer different questions and can legitimately diverge. The related trap is mixing them: running a “prospective” analysis but quietly feeding it hindsight data, which produces a result that is neither defensible forecast nor honest reconstruction.
An event arises in month 6.
- Prospective, at the time: the month-6 programme shows the event likely to push completion 15 days. The contemporaneous EOT is assessed at ~15 days.
- Retrospective, at the end: the as-built shows the event ultimately delayed completion only 10 days, because other paths changed around it.
Both answers can be correct — for their respective questions. The 15 days was a reasonable forecast when it mattered; the 10 days is what the records show happened. The gap isn’t an error; it’s the difference between the two lenses.
What the Protocol says — and doesn’t
It identifies both prospective and retrospective approaches and classifies the delay-analysis methods by whether the critical path is determined prospectively, contemporaneously or retrospectively, and by the direction of the analysis (cause → effect or effect → cause). It no longer mandates a single method for analysis carried out long after the event.
What it does not say:
- That one lens is always right.
- That prospective and retrospective must produce the same number.
- That hindsight should be imported into a prospective assessment.
- That the choice is free of the contract, the stage and the records available.
”Prospective and retrospective should give the same answer — if they don’t, someone got it wrong.”
They answer different questions — likely impact at the time versus actual impact with hindsight — and can legitimately diverge. The divergence is information, not necessarily an error.
For a prospective analysis, set the data date to the point the event arose and forecast forward from the then-current update. For a retrospective one, build the as-built from reliable records and test the actual critical path across the period. Keep the two clean — a forward forecast contaminated with hindsight actuals is defensible as neither.
Evidence check
Prospective
- The programme current at the event (correct data date)
- The event records and the delay notice
Retrospective
- Complete, reliable as-built records
- Progress records and the programme updates across the period
Relevance always depends on the facts and the contract.
Rishi’s takeaway
- Prospective = likely impact from a point in time (forward). Retrospective = actual impact with hindsight (backward).
- They answer different questions and can legitimately give different answers.
- Choose the lens by purpose, stage, contract and the records you actually have.
- Never import hindsight into a prospective assessment — keep the lenses clean.
Prospective asks what was likely to happen; retrospective asks what did. Don’t confuse the two — and don’t expect them to agree.
References. Society of Construction Law, Delay and Disruption Protocol, 2nd Edition, February 2017 — guidance on delay analysis (paragraph 11 and the methods table at 11.5), including the prospective/contemporaneous/retrospective distinction and the removal of a preferred method for time-distant analysis. The appropriate approach depends on the contract, the stage, the purpose and the records. Educational commentary; not legal advice.
Common questions
What is the difference between prospective and retrospective delay analysis?
There are two ways to look at delay. Prospectively — forward, from a point in time: "what is this event likely to do to completion?" And retrospectively — backward, with hindsight: "what actually happened, and what caused it?" They answer different questions, they can give different answers, and neither is universally right.
Should prospective and retrospective analyses give the same answer?
They answer different questions — likely impact at the time versus actual impact with hindsight — and can legitimately diverge. The divergence is information, not necessarily an error.
What does the SCL Protocol say about prospective and retrospective analysis?
It identifies both prospective and retrospective approaches and classifies the delay-analysis methods by whether the critical path is determined prospectively, contemporaneously or retrospectively, and by the direction of the analysis (cause → effect or effect → cause). It no longer mandates a single method for analysis carried out long after the event.