Expertise

Project ControlsPlanning and Primavera P6Schedule AssuranceEOT ClaimsForensic Delay AnalysisProgramme ManagementPMO LeadershipDigital Project ControlsAll expertise

Framework

Project Controls Management System100-Point Schedule Assurance FrameworkHow I WorkOperating PrinciplesImplementation ChecklistsMaturity Model

Tools

Project Controls IntelligenceDecision Centre: start hereDirector’s 10-Minute ReviewForensic Delay LabProgramme DashboardProgramme SimulatorRisk and Early WarningExecutive Review GeneratorSchedule Assurance ChallengeProgramme Management toolsChecklists and templates

Academy

Learning pathwaysProfessional ReferencesPrimavera P6 GuidesThe SCL Protocol seriesGlossary

Insights

ArticlesCase StudiesProjectsDirector’s PlaybookRed Flags and Failure AtlasLessons from Major ProgrammesClaims and Delay articles

About

AboutExecutive ProfileDownload Executive CVLinkedIn
Search

Searches articles, case studies, guides and tools on this site. Runs in your browser — nothing is sent anywhere.

Construction Claims

The SCL Protocol, in Practice · Part 8 of 24

Don't 'Wait and See': Why Timing Beats Cleverness

'We'll sort the EOT at the end' is how a good claim quietly dies. The Protocol's guidance is to assess the time impact of delay events as the work proceeds — contemporaneously — rather than wait and see, then reconstruct it all later with hindsight. Assessing as you go keeps the programme a live tool, keeps entitlement current, and produces the records that make the analysis defensible.

By Rishi JaveriPublished 06-Nov-267 min read
The 30-second version

”We’ll sort the EOT at the end” is how a good claim quietly dies. The Protocol’s guidance is to assess the time impact of delay events as the work proceeds — contemporaneously — rather than “wait and see” and reconstruct it all later with hindsight. Assessing as you go keeps the programme a live management tool, keeps entitlement current, and produces the records that make the analysis defensible.

The construction-site version

An event hits in month 4. Nobody assesses the EOT — everyone’s busy, and besides, “we’ll see how it plays out.” By month 18 the job is disputed and both sides are reconstructing month 4 from memory, arguing about a critical path nobody captured at the time.

Contrast the team that modelled the event’s likely impact within the window, updated the programme, and had a decision on the table while it still mattered. Same event; one team managed it, the other is litigating it.

The technical bit

The 2nd Edition elevated contemporaneous assessment. Core Principle 4 recommends dealing with the time impact of delay events as the works proceed and discourages the “wait and see” approach — the Contract Administrator assessing an EOT application promptly rather than deferring to see whether the delay materialises.

The benefits are practical: the programme stays a live management tool; both parties can manage and mitigate in real time; the impact is recorded contemporaneously; and you avoid the distortions and disputes that come from hindsight reconstruction. This connects to the procedure for granting an EOT (Core Principle 5) and to incremental review as more information emerges (Core Principle 7). Two caveats matter: the contract governs the timing and mechanics of notices and assessment; and where an event’s effect genuinely cannot be assessed prospectively, the Protocol acknowledges that — but that’s the exception, not a licence to defer everything to the end. It’s the practical face of the prospective-versus-retrospective question.

Assess as you go

Event 1 → assess ✓
Event 2 → assess ✓
Event 3 → assess ✓

Entitlement stays current & managed.

Wait and see

Event 1
Event 2
Event 3
— no assessment; impacts pile up

Reconstruct at the end → dispute.

The same three events. Assessed within each window, entitlement stays current and the programme stays a management tool; deferred, they become one hindsight reconstruction and a dispute.

How three roles should read it

The planner

Assess each event against the current update at the time — correct data date, a fragnet for the event, a re-forecast — not against a stale baseline months later. The window in which you assess is the window whose critical path matters.

The claims team

A timely, contemporaneous assessment is worth more than a polished retrospective one. It creates a dated record of the impact and forces the causation question while the evidence is fresh. Watch the contract\u2019s notice periods — a contemporaneous entitlement can still be lost on a missed deadline.

The project manager

"We\u2019ll deal with it at the end" feels efficient and is the opposite. Assessing as you go is what lets you actually manage — mitigate, re-sequence, escalate — while there is still time to change the outcome rather than just argue about it.

Myth

”You can only really assess delay with hindsight, so wait until the end.”

Reality

The Protocol favours assessing as the work proceeds. Hindsight has its place through incremental review, but “wait and see” as a default undermines the programme and the records — and the contract usually requires timely notice and assessment anyway.

P6Reality check

Assess the event against the contemporaneous update — set the data date to the point the event arose, insert a fragnet, and re-forecast to see the impact on the current critical path. Don’t wait to reconstruct from a stale baseline; the whole point is to capture the picture while it’s live.

Evidence check

Timely delay notices and particulars; the contemporaneous programme update used for the assessment; the Contract Administrator’s contemporaneous determination or response; and the records made at the time of the event. Relevance always depends on the facts and the contract.

Rishi’s takeaway

  • Assess the time impact of events as you go — don’t “wait and see.”
  • Contemporaneous assessment keeps the programme a live management tool and entitlement current.
  • Hindsight has a role through incremental review — but not as a reason to defer everything.
  • Assess against the update at the time (right data date, fragnet), not a stale baseline later.
  • The contract still governs timing — a live entitlement dies on a missed notice.

Assess the delay while you can still manage it — leave it to the end and all you can do is argue about it.


References. Society of Construction Law, Delay and Disruption Protocol, 2nd Edition, February 2017 — Core Principle 4 (do not “wait and see”; contemporaneous assessment), with Core Principle 5 (procedure for granting an EOT) and Core Principle 7 (incremental review). The timing and mechanics of notices and assessment depend on the contract and the governing law. Educational commentary; not legal advice.

Common questions

What does 'don't wait and see' mean under the SCL Protocol?

Core Principle 4 recommends assessing the time impact of delay events as the works proceed, and discourages deferring assessment to see whether a delay materialises. The Contract Administrator should assess an EOT application promptly rather than waiting.

Why is contemporaneous assessment better than hindsight?

Assessing as you go keeps the programme a live management tool, lets both parties mitigate in real time, and records the impact while the evidence is fresh — avoiding the distortions and disputes that come from hindsight reconstruction.

Is there ever a place for retrospective analysis?

Yes — through incremental review as more information emerges (Core Principle 7), and where an event's effect genuinely cannot be assessed prospectively. But that is the exception, not a licence to defer everything to the end.

Does the contract still matter if I assess contemporaneously?

Very much. The contract governs the timing and mechanics of notices and assessment. A live, well-evidenced entitlement can still be lost on a missed notice period.

How do you assess a delay event contemporaneously in P6?

Set the data date to the point the event arose, insert a fragnet for the event, and re-forecast to see its impact on the current critical path — rather than reconstructing from a stale baseline months later.

Rishi JaveriProject Controls & Programme Governance · FCIArb · FIE · PMP · PSP · MCIOB · MAPM