Expertise

Project ControlsPlanning and Primavera P6Schedule AssuranceEOT ClaimsForensic Delay AnalysisProgramme ManagementPMO LeadershipDigital Project ControlsAll expertise

Framework

Project Controls Management System100-Point Schedule Assurance FrameworkHow I WorkOperating PrinciplesImplementation ChecklistsMaturity Model

Tools

Project Controls IntelligenceDecision Centre: start hereDirector’s 10-Minute ReviewForensic Delay LabProgramme DashboardProgramme SimulatorRisk and Early WarningExecutive Review GeneratorSchedule Assurance ChallengeProgramme Management toolsChecklists and templates

Academy

Learning pathwaysProfessional ReferencesPrimavera P6 GuidesThe SCL Protocol seriesGlossary

Insights

ArticlesCase StudiesProjectsDirector’s PlaybookRed Flags and Failure AtlasLessons from Major ProgrammesClaims and Delay articles

About

AboutExecutive ProfileDownload Executive CVLinkedIn
Search

Searches articles, case studies, guides and tools on this site. Runs in your browser — nothing is sent anywhere.

Construction Claims

The SCL Protocol, in Practice · Part 7 of 24

Records: The Boring Thing That Wins Cases

Delay claims are rarely lost on principle. They're lost because the records that would have proved cause and effect were never kept — or were reconstructed after the dispute started, when they carry far less weight. Contemporaneous records are the single biggest thing separating a claim you can prove from a story you can only tell.

By Rishi JaveriPublished 30-Oct-267 min read
The 30-second version

Delay claims are rarely lost on principle. They’re lost because the records that would have proved cause and effect were never kept — or were reconstructed after the dispute started, when they carry far less weight. Good, contemporaneous records are the single biggest thing separating a claim you can prove from a story you can only tell.

The construction-site version

Two projects, same Employer delay. On the first, the site team kept dated daily allocation sheets, a clean RFI log and progress photos. When the claim comes, the effect is demonstrable in an afternoon. On the second there’s a recollection, a couple of emails, and a programme that wasn’t updated for three months.

Same entitlement on paper — but one team can prove it and the other can’t. The delay didn’t decide the outcome. The records did.

The technical bit

The Protocol puts records at the very front: Core Principle 1 is “programme and records,” and its guidance treats good record-keeping as the most important single factor in avoiding and resolving disputes. Records matter because the burden of demonstrating cause and effect sits with the party claiming — and contemporaneous records are what discharge it.

The guidance frames records across categories, with typical examples in Appendix B. Two principles run through all of it: keep them as a matter of routine, not when a dispute looms; and keep them contemporaneously, because a record made at the time carries far more weight than a narrative assembled afterwards.

The six record categories · CP1 / Appendix B
1 · Programme

Baseline, updates and revisions

2 · Progress

Actual dates, % complete, as-built

3 · Resource

Labour, plant, subcontractor, timesheets

4 · Cost

Cost reports, applications, valuations

5 · Correspondence

RFIs, instructions, notices, minutes

6 · Contract

The contract and tender documents

Kept contemporaneously, these make cause and effect demonstrable; reconstructed later, they get discounted.

How three roles should read it

The planner

The programme is itself a record — arguably the most important one. Save dated update snapshots with correct actuals and data dates, don\u2019t overwrite them, and keep the revision history intact. An audit trail of updates is worth more than any after-the-fact reconstruction.

The claims team

You can only prove what the records support. Before you draft, map each event to the record that proves it happened and the record that proves its effect. Where a link has no record behind it, that is the weak point an opponent will find first.

The project manager

Records are a month-one management decision, not a month-thirty scramble. The cheapest delay claim to run is the one where the evidence already exists because someone kept it at the time.

Myth

”We’ll build the record when we need to make a claim.”

Reality

Contemporaneous records made in the ordinary course of the works carry far more weight than a narrative assembled after the dispute. Retrospective reconstruction is challengeable and often discounted.

P6Reality check

Treat every programme update as a record — save it, date it, lock the data date, keep actuals honest, and never overwrite the history. A clean series of dated updates is prime evidence of the contemporaneous critical path; an overwritten single file destroys the audit trail you’ll later need.

Evidence check — the six categories

Programme (baseline, updates, revisions); progress (actual start/finish, % complete, as-built); resource (labour, plant, subcontractor allocations, timesheets); cost (cost reports, applications, valuations); correspondence and administration (RFIs, instructions, notices, minutes, drawing registers); and the contract and tender documents. Relevance always depends on the facts and the contract.

Rishi’s takeaway

  • Most delay claims fail on records, not on principle.
  • Keep records contemporaneously and as routine — not when a dispute looms.
  • The programme is a record; save dated updates and never overwrite the history.
  • Map every event to the record that proves it happened and the record that proves its effect.
  • Records prove facts; the contract and law decide entitlement — but with no facts, there’s nothing to decide.

The claim you can prove is the one whose records you kept the day it happened.


References. Society of Construction Law, Delay and Disruption Protocol, 2nd Edition, February 2017 — Core Principle 1 (programme and records) and Appendix B (typical records within each category). What is relevant depends on the facts and the contract. Educational commentary; not legal advice.

Common questions

Why do most delay claims fail?

Not on principle — on records. The party claiming carries the burden of demonstrating cause and effect, and without contemporaneous records made at the time, there is often nothing to discharge it with.

What are the six categories of records under the SCL Protocol?

Broadly (Core Principle 1, Appendix B): programme records; progress records; resource records; cost records; correspondence and administration records; and the contract and tender documents. What is actually relevant depends on the facts and the contract.

Why do contemporaneous records carry more weight than reconstructed ones?

A record made at the time, in the ordinary course of the works, is far harder to challenge than a narrative assembled after a dispute begins. Retrospective reconstruction is challengeable and often discounted.

Is the programme itself a record?

Yes — arguably the most important one. Dated update snapshots with correct actuals and data dates are prime evidence of the contemporaneous critical path, provided the history is never overwritten.

Does keeping good records guarantee entitlement?

No. Records prove facts; the contract and the governing law decide entitlement. But with no facts proven, there is nothing for the contract and law to decide.