Expertise

Project ControlsPlanning and Primavera P6Schedule AssuranceEOT ClaimsForensic Delay AnalysisProgramme ManagementPMO LeadershipDigital Project ControlsAll expertise

Framework

Project Controls Management System100-Point Schedule Assurance FrameworkHow I WorkOperating PrinciplesImplementation ChecklistsMaturity Model

Tools

Project Controls IntelligenceDecision Centre: start hereDirector’s 10-Minute ReviewForensic Delay LabProgramme DashboardProgramme SimulatorRisk and Early WarningExecutive Review GeneratorSchedule Assurance ChallengeProgramme Management toolsChecklists and templates

Academy

Learning pathwaysProfessional ReferencesPrimavera P6 GuidesThe SCL Protocol seriesGlossary

Insights

ArticlesCase StudiesProjectsDirector’s PlaybookRed Flags and Failure AtlasLessons from Major ProgrammesClaims and Delay articles

About

AboutExecutive ProfileDownload Executive CVLinkedIn
Search

Searches articles, case studies, guides and tools on this site. Runs in your browser — nothing is sent anywhere.

Delay Analysis

Time Impact Analysis (TIA): A Practical Guide

Time Impact Analysis models a delay event into the programme as it stood at the time, to show its prospective effect on completion. It is the method most contracts and protocols reach for first — when the records support it.

By Rishi JaveriPublished 14-Aug-267 min read

What TIA is

Time Impact Analysis is a prospective delay method: it takes the programme that was current and reasonably up to date at the point a delay event arose, inserts a sub-network representing that event, and re-calculates to show the effect on the completion date. It answers “what was the likely impact of this event, judged at the time it happened?”

When to use it

TIA suits situations where you have a reliable, regularly updated baseline and can identify the event’s timing clearly — which is why the SCL Delay and Disruption Protocol favours it for prospective assessment. It is less suitable where programmes were poorly maintained or where you are reconstructing events long after the fact; there, windows or as-built methods may serve better (see what is delay analysis).

The method, step by step

  1. Select the programme current at the point of the delay event, updated for actual progress.
  2. Build a delay fragnet — a small logic network representing the event and its consequences.
  3. Insert it at the correct point and re-calculate the schedule.
  4. Read the movement in the completion date — that is the event’s prospective impact.
  5. Repeat, in sequence, for each event, so impacts are assessed against an evolving programme rather than all at once.

Strengths and limitations

TIA’s strength is that it reflects what was known at the time, which courts and tribunals often prefer. Its weakness is its dependence on the quality of the programme it is applied to: a flawed baseline produces a flawed result. It also does not, by itself, resolve concurrent delay — that requires separate analysis. Applied honestly, it is a cornerstone of defensible Extension of Time assessment.

This is a general explanation of professional practice, not legal or contractual advice.