Expertise

Project ControlsPlanning and Primavera P6Schedule AssuranceEOT ClaimsForensic Delay AnalysisProgramme ManagementPMO LeadershipDigital Project ControlsAll expertise

Framework

Project Controls Management System100-Point Schedule Assurance FrameworkHow I WorkOperating PrinciplesImplementation ChecklistsMaturity Model

Tools

Project Controls IntelligenceDecision Centre: start hereDirector’s 10-Minute ReviewForensic Delay LabProgramme DashboardProgramme SimulatorRisk and Early WarningExecutive Review GeneratorSchedule Assurance ChallengeProgramme Management toolsChecklists and templates

Academy

Learning pathwaysProfessional ReferencesPrimavera P6 GuidesThe SCL Protocol seriesGlossary

Insights

ArticlesCase StudiesProjectsDirector’s PlaybookRed Flags and Failure AtlasLessons from Major ProgrammesClaims and Delay articles

About

AboutExecutive ProfileDownload Executive CVLinkedIn
Search

Searches articles, case studies, guides and tools on this site. Runs in your browser — nothing is sent anywhere.

SAE / ECIA, ISO, AACE International

Earned value management: EIA-748-E and ISO 21508

EIA-748-E Earned Value Management SystemsRevision of 17-Feb-26 · Industry standard · PurchaseOfficial source →
ISO 21508:2026 Earned value management in project and programme management2nd edition, 06-Feb-26 (replaces 2018) · International standard · PurchaseOfficial source →
AACE RP 82R-13 Earned Value Management Overview04-May-17 · Recommended practice · AACE members; purchase for othersOfficial source →
Edition checked 02-Nov-26.

01What it covers

How scope, schedule and cost are integrated so that performance can be measured objectively: work broken into controlled elements, budgets planned over time, progress earned by objective rules, and variances analysed and acted on.

02Why it matters

Earned value is only as good as the system behind it. These standards describe that system, so a programme can tell a reliable performance index from a precise-looking number built on subjective progress.

03Key principles

  • Plan all the work, integrate it with the schedule and budget it over time.
  • Earn value by objective measures of physical progress, set before the work starts.
  • Compare earned value with planned value and actual cost, and explain significant variances.
  • Revise forecasts on the evidence, and control changes to the performance baseline.
  • Scale the system to the size, complexity and risk of the work.

04Practical application

  • Agree rules of credit for each type of work before the baseline is set.
  • Use one data date for earned value and the schedule forecast.
  • Report schedule performance in time (earned schedule) as well as money.

05Common mistakes

  • Calculating earned value from subjective percentages.
  • Reading a programme-level index without looking at the critical packages.
  • Letting the performance baseline drift through unrecorded change.
Guidance, contract and law. EIA-748 becomes mandatory only where a contract or government requirement applies it; ISO 21508 is guidance. AACE 82R-13 is cited by title and date; its full text was not reviewed for this guide.

06PCMS discipline

07Related tools

08Further reading

Written in my own words to explain principles; it does not reproduce the publication and implies no endorsement by SAE / ECIA, ISO, AACE International. Not legal advice.