Expertise

Project ControlsPlanning and Primavera P6Schedule AssuranceEOT ClaimsForensic Delay AnalysisProgramme ManagementPMO LeadershipDigital Project ControlsAll expertise

Framework

Project Controls Management System100-Point Schedule Assurance FrameworkHow I WorkOperating PrinciplesImplementation ChecklistsMaturity Model

Tools

Project Controls IntelligenceDecision Centre: start hereDirector’s 10-Minute ReviewForensic Delay LabProgramme DashboardProgramme SimulatorRisk and Early WarningExecutive Review GeneratorSchedule Assurance ChallengeProgramme Management toolsChecklists and templates

Academy

Learning pathwaysProfessional ReferencesPrimavera P6 GuidesThe SCL Protocol seriesGlossary

Insights

ArticlesCase StudiesProjectsDirector’s PlaybookRed Flags and Failure AtlasLessons from Major ProgrammesClaims and Delay articles

About

AboutExecutive ProfileDownload Executive CVLinkedIn
Search

Searches articles, case studies, guides and tools on this site. Runs in your browser — nothing is sent anywhere.

Practitioner pathway · Earned Value Management

Earned Value and Earned Schedule

Earned value joins scope, time and cost into one measure. Earned Schedule fixes its best-known weakness by measuring schedule slippage in time instead of money.

By Rishi Javeri · 01-Nov-26 · 9 min read

Earned value management (EVM) answers a question that neither the programme nor the cost report answers alone: for the money spent and the time passed, how much of the work is actually done?

The three numbers

  • Planned value (PV): the budgeted cost of the work scheduled to be done by now.
  • Earned value (EV): the budgeted cost of the work actually done by now. It comes from measured progress.
  • Actual cost (AC): what the work done actually cost.

Everything else is derived from these, against the budget at completion (BAC).

MeasureFormulaReading
Schedule varianceSV = EV − PVNegative: less work done than planned
Cost varianceCV = EV − ACNegative: the work done cost more than its budget
Schedule performance indexSPI = EV ÷ PVBelow 1: behind
Cost performance indexCPI = EV ÷ ACBelow 1: over cost

A worked example

A fictional package with a budget of 120 (any currency unit) over 10 months. The cumulative planned value by month is 4, 10, 20, 34, 50, 66, 82, 96, 110, 120. At the end of month 6, measured progress gives EV = 58 and the cost report gives AC = 63.

  • PV at month 6 = 66
  • SV = 58 − 66 = −8; SPI = 58 ÷ 66 = 0.88
  • CV = 58 − 63 = −5; CPI = 58 ÷ 63 = 0.92

The package is behind and over cost. But by how much time is it behind? SV says “8”, which is money, not weeks.

The problem with SPI

SV and SPI measure schedule performance in money. Near the end of a project, PV stops growing (it reaches BAC) and EV catches up as the last work finishes. So SPI drifts back to 1.00 and SV to zero however late the project is. A project finishing three months late ends with SPI = 1.00.

Earned Schedule

Earned Schedule (ES) asks: at what point in the plan should today’s earned value have been reached?

In the example, EV = 58. The plan reached 50 at the end of month 5 and 66 at the end of month 6. So 58 was due 8/16 of the way through month 6:

ES = 5 + (58 − 50) ÷ (66 − 50) = 5.5 months

With actual time AT = 6 months:

  • SV(t) = ES − AT = 5.5 − 6 = −0.5 months: half a month behind.
  • SPI(t) = ES ÷ AT = 5.5 ÷ 6 = 0.92.
  • An independent duration estimate = planned duration ÷ SPI(t) = 10 ÷ 0.92 ≈ 10.9 months.

SPI(t) stays meaningful through to completion. A project that ends three months late on a ten-month plan finishes with SPI(t) of 10 ÷ 13 ≈ 0.77, not 1.00.

Using it well

  • EVM is only as good as progress measurement. Agree rules of credit first.
  • Programme-level indices average everything. A critical package can be late while non-critical work runs ahead, and the total looks fine. Break the indices down by package.
  • SPI(t) is a trend indicator. The forecast completion date still comes from the critical path. When they disagree, find out why.

Check your understanding

Three questions. Choose an answer in your head, then open it to compare.

1PV = 66, EV = 58, AC = 63. Which statement is correct?

  1. Ahead of schedule and under budget
  2. Behind schedule (SPI 0.88) and over cost (CPI 0.92)
  3. Behind schedule (SPI 0.92) and under cost (CPI 1.09)
  4. On schedule; only cost is a problem
Show the answer

B. Behind schedule (SPI 0.88) and over cost (CPI 0.92) SPI = EV ÷ PV = 58 ÷ 66 = 0.88. CPI = EV ÷ AC = 58 ÷ 63 = 0.92. Both are below 1.

2A project finishes three months late. What is its SPI at completion?

  1. About 0.75
  2. Exactly 1.00
  3. It cannot be calculated
  4. Below 1.00, depending on the delay
Show the answer

B. Exactly 1.00 At completion EV equals BAC and so does PV, so SPI returns to 1.00 however late the project is. This is why Earned Schedule is used.

3Earned value equals the value planned for the end of period 5.5, and 6 periods have passed. What is SV(t)?

  1. +0.5 periods
  2. −0.5 periods
  3. 0.92
  4. −8
Show the answer

B. −0.5 periods SV(t) = ES − AT = 5.5 − 6 = −0.5 periods: the work is half a period behind.

Self-paced reading for practitioners. Not a course, certificate or accredited qualification. Worked examples use fictional figures.