Practitioner pathway · Earned Value Management
Earned Value and Earned Schedule
Earned value joins scope, time and cost into one measure. Earned Schedule fixes its best-known weakness by measuring schedule slippage in time instead of money.
By Rishi Javeri · 01-Nov-26 · 9 min read
Earned value management (EVM) answers a question that neither the programme nor the cost report answers alone: for the money spent and the time passed, how much of the work is actually done?
The three numbers
- Planned value (PV): the budgeted cost of the work scheduled to be done by now.
- Earned value (EV): the budgeted cost of the work actually done by now. It comes from measured progress.
- Actual cost (AC): what the work done actually cost.
Everything else is derived from these, against the budget at completion (BAC).
| Measure | Formula | Reading |
|---|---|---|
| Schedule variance | SV = EV − PV | Negative: less work done than planned |
| Cost variance | CV = EV − AC | Negative: the work done cost more than its budget |
| Schedule performance index | SPI = EV ÷ PV | Below 1: behind |
| Cost performance index | CPI = EV ÷ AC | Below 1: over cost |
A worked example
A fictional package with a budget of 120 (any currency unit) over 10 months. The cumulative planned value by month is 4, 10, 20, 34, 50, 66, 82, 96, 110, 120. At the end of month 6, measured progress gives EV = 58 and the cost report gives AC = 63.
- PV at month 6 = 66
- SV = 58 − 66 = −8; SPI = 58 ÷ 66 = 0.88
- CV = 58 − 63 = −5; CPI = 58 ÷ 63 = 0.92
The package is behind and over cost. But by how much time is it behind? SV says “8”, which is money, not weeks.
The problem with SPI
SV and SPI measure schedule performance in money. Near the end of a project, PV stops growing (it reaches BAC) and EV catches up as the last work finishes. So SPI drifts back to 1.00 and SV to zero however late the project is. A project finishing three months late ends with SPI = 1.00.
Earned Schedule
Earned Schedule (ES) asks: at what point in the plan should today’s earned value have been reached?
In the example, EV = 58. The plan reached 50 at the end of month 5 and 66 at the end of month 6. So 58 was due 8/16 of the way through month 6:
ES = 5 + (58 − 50) ÷ (66 − 50) = 5.5 months
With actual time AT = 6 months:
- SV(t) = ES − AT = 5.5 − 6 = −0.5 months: half a month behind.
- SPI(t) = ES ÷ AT = 5.5 ÷ 6 = 0.92.
- An independent duration estimate = planned duration ÷ SPI(t) = 10 ÷ 0.92 ≈ 10.9 months.
SPI(t) stays meaningful through to completion. A project that ends three months late on a ten-month plan finishes with SPI(t) of 10 ÷ 13 ≈ 0.77, not 1.00.
Using it well
- EVM is only as good as progress measurement. Agree rules of credit first.
- Programme-level indices average everything. A critical package can be late while non-critical work runs ahead, and the total looks fine. Break the indices down by package.
- SPI(t) is a trend indicator. The forecast completion date still comes from the critical path. When they disagree, find out why.
Check your understanding
Three questions. Choose an answer in your head, then open it to compare.
1PV = 66, EV = 58, AC = 63. Which statement is correct?
- Ahead of schedule and under budget
- Behind schedule (SPI 0.88) and over cost (CPI 0.92)
- Behind schedule (SPI 0.92) and under cost (CPI 1.09)
- On schedule; only cost is a problem
Show the answer
B. Behind schedule (SPI 0.88) and over cost (CPI 0.92) SPI = EV ÷ PV = 58 ÷ 66 = 0.88. CPI = EV ÷ AC = 58 ÷ 63 = 0.92. Both are below 1.
2A project finishes three months late. What is its SPI at completion?
- About 0.75
- Exactly 1.00
- It cannot be calculated
- Below 1.00, depending on the delay
Show the answer
B. Exactly 1.00 At completion EV equals BAC and so does PV, so SPI returns to 1.00 however late the project is. This is why Earned Schedule is used.
3Earned value equals the value planned for the end of period 5.5, and 6 periods have passed. What is SV(t)?
- +0.5 periods
- −0.5 periods
- 0.92
- −8
Show the answer
B. −0.5 periods SV(t) = ES − AT = 5.5 − 6 = −0.5 periods: the work is half a period behind.