Cost Control and Forecasting
Cost control is not tracking spend. It is knowing, every period, what the job will cost at the end and why, early enough to change it.
By Rishi Javeri · 01-Nov-26 · 8 min read
A cost report that only compares spend with budget tells you the past. Cost control is about the future: the estimate at completion (EAC), how it is moving, and what can still be done about it.
The four positions to reconcile
- Budget: the approved cost, including approved change.
- Commitments: what has been contracted or ordered.
- Actual cost: what has been incurred to date.
- Forecast: what the whole scope will cost by the end.
Every period, these should be reconciled at the same cut-off, by the same structure (package, WBS, cost code) as the programme and progress. If cost and schedule use different structures, earned value is impossible and the two teams will argue about whose number is right.
Estimating at completion
There are two ways to forecast:
- Bottom-up: re-estimate the cost of the remaining work (the estimate to complete, ETC) and add it to actual cost: EAC = AC + ETC. This is the best method when done honestly, and the slowest.
- Formula: extrapolate from performance so far. Quick, objective, and a good test of the bottom-up figure.
The standard formula EACs, each with its assumption:
| Assumption | Formula |
|---|---|
| Past variance will not recur | EAC = AC + (BAC − EV) |
| Cost performance continues | EAC = BAC ÷ CPI |
| Cost and schedule pressure both continue | EAC = AC + (BAC − EV) ÷ (CPI × SPI) |
| Bottom-up | EAC = AC + ETC |
Variance at completion is VAC = BAC − EAC. The to-complete performance index is TCPI = (BAC − EV) ÷ (BAC − AC): the cost efficiency the remaining work needs to finish within budget.
A worked example
The fictional package from the earned value lesson: BAC = 120, PV = 66, EV = 58, AC = 63. So CPI = 0.92 and SPI = 0.88. The contractor’s bottom-up ETC is 66, and the monthly report shows a forecast of 118.
| Assumption | EAC | VAC |
|---|---|---|
| Past variance will not recur | 63 + 62 = 125.0 | −5.0 |
| Bottom-up | 63 + 66 = 129.0 | −9.0 |
| Cost performance continues | 120 ÷ 0.92 = 130.3 | −10.3 |
| Cost and schedule pressure | 63 + 62 ÷ 0.81 = 139.6 | −19.6 |
The formula range is 125 to about 140. The reported 118 sits below all of them. To finish within the budget of 120, TCPI = 62 ÷ 57 = 1.09, against 0.92 achieved. That does not make 118 wrong, but it does mean someone must explain, with evidence, what will make the remaining work 18% more efficient than the work done so far.
Practices that keep forecasts honest
- Record the basis of every forecast: what is in it and what is not.
- Show pending change and significant risk separately from the base forecast.
- Track the EAC month to month; a forecast that only moves at the end was never a forecast.
- Break forecasts down by package before reporting a programme total.
Check your understanding
Three questions. Choose an answer in your head, then open it to compare.
1BAC = 120, EV = 58, AC = 63 (CPI 0.92). What is the EAC if current cost performance continues?
- 120.0
- 125.0
- about 130.3
- about 139.6
Show the answer
C. about 130.3 EAC = BAC ÷ CPI = 120 ÷ (58 ÷ 63) ≈ 130.3.
2A TCPI of 1.09 against a CPI achieved of 0.92 means:
- The project will finish under budget
- To finish within budget, the remaining work must be done 9% more efficiently than planned, much better than achieved so far
- The forecast is correct
- Schedule performance is good
Show the answer
B. To finish within budget, the remaining work must be done 9% more efficiently than planned, much better than achieved so far TCPI is the cost efficiency the remaining work needs to hit a target. Needing 1.09 after achieving 0.92 calls for a clear, evidenced recovery case.
3Which cost belongs in the forecast but often goes missing from it?
- Approved variations
- Actual cost to date
- Pending change and known risks not yet approved
- The original budget
Show the answer
C. Pending change and known risks not yet approved Forecasts often exclude change that is expected but not approved, and risks that are likely. Show them separately, but show them.